Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Marana, Arizona.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
Ed Honea Marana Municipal Complex, Development Services Counter, 2nd Floor, Bldg. A2, 11555 W. Civic Center Drive, Marana, AZ 85653
Phone
520-382-2600
Office hours
Monday - Friday, 8:00 a.m. - 5:00 p.m. Walk-in customers welcome at the Development Services Counter (One-Stop Shop) on the 2nd floor of the Marana Municipal Complex. Applications and plans are submitted via the Permit Tracker (eTRAKiT) online portal at maranaegov.com/etrakit or in person at the Development Services Counter. Inspections are scheduled through Permit Tracker (contractors) or by calling the inspection line at 520-382-2637 and leaving a voicemail (homeowners); inspections are performed Monday - Friday, 7:00 a.m. - 3:00 p.m., and can be scheduled as early as the next business day if requested before 3:00 p.m.

Published scheduling rules

  • Inspections are scheduled through the Permit Tracker (eTRAKiT) portal for contractors, or by leaving a voicemail at the homeowner inspection line (520-382-2637); requests before 3:00 p.m. can be scheduled as early as the next business day. (Residential Building Permit (New Custom Home / Model Home / SFR-Based-on-Model))
  • Applications and inspection scheduling run through the Permit Tracker (eTRAKiT) online portal at maranaegov.com/etrakit; homeowners without portal access can call the dedicated inspection line (520-382-2637) and leave a voicemail instead. (General)
  • Inspections run Monday-Friday 7:00 a.m.-3:00 p.m.; requests made before 3:00 p.m. can be scheduled as early as the next business day. After-hours inspections are available but not guaranteed, require 3 business days' advance notice, and carry a 2-hour-minimum after-hours fee. (General)

Inspection sequence

Applies to: Residential Building Permit (New Custom Home / Model Home / SFR-Based-on-Model)

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Framing

    Structural framing, connections, egress per 2024 IRC and Town of Marana Design Criteria

  3. 3

    Rough-In (Electrical/Plumbing/Mechanical)

    Trade rough-ins before walls are closed

  4. 4

    Final

    All work complete per approved plans, verified using the Building Final Inspection Checklist before Certificate of Occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation/Footing

    Required before concrete pour for additions

  2. 2

    Framing

    Structural connections to existing structure

  3. 3

    Final

    Completed work verified against approved plans

Applies to: Electrical Permit (Miscellaneous / Building Permit Electrical Scope)

  1. 1

    Rough-In

    Wiring, box placement, and panel connections before walls are closed

  2. 2

    Final

    Devices installed, panel labeled, protections verified per 2023 NEC

Applies to: Fence and Retaining Wall Permit

  1. 1

    Footing

    Required for retaining walls exceeding the 4-foot exemption threshold, before backfill

  2. 2

    Final

    Completed fence/wall verified against approved plans

Applies to: Mechanical / HVAC Permit (Heating and Cooling Replacement)

  1. 1

    Rough-In

    Ductwork and equipment placement before walls closed (where applicable)

  2. 2

    Final

    Equipment operational, clearances and connections verified

Applies to: Photovoltaic (Solar) System Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Utility Clearance

    Panel mounting, roof-penetration sealing, electrical connections verified; utility clearance obtained from the electrical provider before grid connection

Applies to: Plumbing Permit (Water Heater Replacement / Interior Re-Pipe / Miscellaneous Plumbing)

  1. 1

    Rough-In

    After pipes installed, before walls closed

  2. 2

    Final

    Fixtures connected, water heater/re-pipe connections verified, no leaks; a safety inspection is conducted for water heater replacements and irrigation potable-water reconnections

Applies to: Pool and Spa Permit

  1. 1

    Pre-Gunite/Excavation

    Verifies excavation, steel placement, and equipment location before shotcrete/gunite for in-ground pools

  2. 2

    Pool Barrier/Final

    Barrier/fencing compliance and completed pool equipment verified against approved plans

Marana building permits

Get alerts for Marana

We'll email you when Marana's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.