Photovoltaic (Solar) System Permit in Marana, Arizona

Required for installation of any photovoltaic (PV) system in the Town of Marana, including rooftop solar panels, ground-mounted systems, and pool/water heaters, governed by the 2023 NEC as adopted and locally amended (Exhibit G, Ordinance 2025.013). Inspections include a utility clearance required by the electrical provider prior to grid connection, and the Town publishes separate flat fees for residential vs. commercial systems and for pool/water-heater PV specifically.

Verified 2026-07-06 · Source

When you need this permit

  • Permit required for ALL photovoltaic installations: rooftop solar panels, ground-mounted systems, pool heaters, and water heaters
  • Governed by the 2023 NEC as adopted by the Town of Marana with local amendments (Exhibit G)
  • Inspections verify building code compliance AND include a utility clearance required by the electrical provider before the system is connected to the grid
  • Submit a Permit Application plus the Photovoltaic Solar System Application Checklist (rev. 2017.02.13)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Photovoltaic System; Single Family ResidentialPer permit. Town of Marana Comprehensive Fee Schedule (Feb. 6, 2026)
$150.00
Photovoltaic System; CommercialPer permit; includes multi-family developments. Town of Marana Comprehensive Fee Schedule (Feb. 6, 2026)
$750.00
Photovoltaic System for water/pool heater; ResidentialPer permit; includes structural review of roof loading, backflow preventer, and pump. Town of Marana Comprehensive Fee Schedule (Feb. 6, 2026)
$50.00
Photovoltaic System for water/pool heater; CommercialPer permit. Town of Marana Comprehensive Fee Schedule (Feb. 6, 2026)
$150.00

Review timeline

Plan reviewMarana’s published plan-review target
60–180 business days

How long did your Photovoltaic (Solar) System Permit permit actually take in Marana?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Utility Clearance

    Panel mounting, roof-penetration sealing, electrical connections verified; utility clearance obtained from the electrical provider before grid connection

See the full Marana inspection guide — scheduling & re-inspection fees →

Tips

  • Marana's PV fees are flat, not valuation-based: $150 for residential rooftop/ground-mount systems, $750 for commercial (including multi-family), $50 for residential pool/water-heater PV, and $150 for commercial pool/water-heater PV.
  • The residential pool/water-heater PV fee specifically includes a structural review of roof loading plus review of the backflow preventer and pump, per the Town's Fee Schedule notes.
  • PV is not one of the itemized Licensing Time Frames rows, so it falls under the Town's general 'Building permit (not listed elsewhere)' maximum time frame of 60/120/180 calendar days; in practice, flat-fee miscellaneous-style permits like PV typically move faster than that ceiling.

Frequently asked questions

Marana requires a photovoltaic (solar) system permit for: Permit required for ALL photovoltaic installations: rooftop solar panels, ground-mounted systems, pool heaters, and water heaters; Governed by the 2023 NEC as adopted by the Town of Marana with local amendments (Exhibit G); Inspections verify building code compliance AND include a utility clearance required by the electrical provider before the system is connected to the grid; Submit a Permit Application plus the Photovoltaic Solar System Application Checklist (rev. 2017.02.13). If your project isn't listed, confirm with Town of Marana Development Services Department — Building Safety at 520-382-2600 before starting work.

$150.00 per permit for a residential rooftop or ground-mounted photovoltaic system, per the Town of Marana Comprehensive Fee Schedule. A residential PV system for a pool or water heater is $50.00.

Marana's published plan-review target for a photovoltaic (solar) system permit is 60–180 business days.

You'll need: Permit Application; Photovoltaic Solar System Application Checklist (rev. 2017.02.13). Depending on your project, Marana may also ask for: Owner Applicant Authorization Form. See the required-documents checklist on this page for details on each.

Marana requires 2 inspection(s) for a photovoltaic (solar) system permit, in order: Rough Electrical, Final / Utility Clearance. Schedule each through Town of Marana Development Services Department — Building Safety (520-382-2600).

Apply through Town of Marana Development Services Department — Building Safety at Ed Honea Marana Municipal Complex, Development Services Counter, 2nd Floor, Bldg. A2, 11555 W. Civic Center Drive, Marana, AZ 85653. Phone: 520-382-2600, email: maranaplanning@maranaaz.gov. Office hours: Monday - Friday, 8:00 a.m. - 5:00 p.m. Walk-in customers welcome at the Development Services Counter (One-Stop Shop) on the 2nd floor of the Marana Municipal Complex. Applications and plans are submitted via the Permit Tracker (eTRAKiT) online portal at maranaegov.com/etrakit or in person at the Development Services Counter. Inspections are scheduled through Permit Tracker (contractors) or by calling the inspection line at 520-382-2637 and leaving a voicemail (homeowners); inspections are performed Monday - Friday, 7:00 a.m. - 3:00 p.m., and can be scheduled as early as the next business day if requested before 3:00 p.m.. Official information: https://www.maranaaz.gov/Departments/Development-Services.

Marana, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/town/county authority under state enabling statutes (A.R.S. Title 9 for municipalities). The Town of Marana independently adopts and administers its own construction codes through its Development Services Department / Building Safety division and does not defer permitting to Pima County or Pinal County. Source: Town of Marana Building Code Amendments page (maranaaz.gov/Departments/Development-Services/Building-Code-Amendments) and Marana Town Code Chapter 7-1 (Building Codes).; 2024 International Building Code (IBC), adopted by reference with Town of Marana local amendments (Marana Town Code Section 7-1-2). The Marana Town Council adopted this code cycle via Ordinance 2025.013 on June 17, 2025; all new applications received after July 18, 2025 must comply, while plans already in review or approved before that date may remain on the prior (2018) code cycle. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013.; 2024 International Residential Code (IRC), adopted by reference with Town of Marana local amendments (Exhibit D to Ordinance 2025.013), effective for new applications after July 18, 2025. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013; Exhibit D — Amendments to 2024 IRC.; 2024 International Existing Building Code (IEBC), adopted by reference with local amendments (Exhibit B), effective July 18, 2025. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013.; 2024 International Plumbing Code (IPC), adopted by reference with local amendments (Exhibit C), effective July 18, 2025. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013.; 2024 International Mechanical Code (IMC), adopted by reference with local amendments (Exhibit E), effective July 18, 2025. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013.; 2024 International Fuel Gas Code (IFGC), adopted by reference with local amendments (Exhibit I), effective July 18, 2025. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013.; 2024 International Fire Code (IFC), adopted by reference with local amendments (Exhibit H) as the Town's uniform fire code, effective July 18, 2025; the Town issues the permit but inspections for fire-code compliance are completed by the serving fire district. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013; Development Services Forms page (Fire Permits section).; 2023 National Electrical Code (NEC), adopted by reference with local amendments (Exhibit G), effective July 18, 2025 — one edition behind the 2024 ICC set, consistent with the national NEC 3-year cycle. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013.; 2024 International Property Maintenance Code (IPMC), adopted by reference with local amendments (Exhibit F), effective July 18, 2025. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013.; 2024 International Swimming Pool and Spa Code (ISPSC), adopted by reference with local amendments (Exhibit J), effective July 18, 2025. Source: Town of Marana Building Code Amendments page; Ordinance 2025.013.; 2018 International Energy Conservation Code (IECC), adopted by reference with local amendments (Exhibit G to Ordinance 2019.011) — the Town has NOT moved to a newer IECC cycle alongside the 2024 ICC suite; the 2018 edition remains in force. Source: Town of Marana Building Code Amendments page; Ordinance 2019.011.; 2021 Town of Marana Outdoor Lighting Code, adopted by reference (Ordinance 2021.007), governing dark-sky/lighting-area requirements Town-wide with an accompanying Lighting Area Map. Source: Town of Marana Building Code Amendments page; Ordinance 2021.007.; Manufactured homes and factory-built buildings follow a dedicated Manufactured Homes Procedural Guide (rev. 2019.01.18) for site placement, foundation, and zoning compliance, administered by Development Services Planning in coordination with Building Safety. Source: Town of Marana Development Services Forms page (Manufactured Home section).. Local amendments apply — see the Marana overview page for the full list.

Yes — in addition to Town building-code inspections, a utility clearance from the electrical provider is required before the system can be connected to the grid.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Marana building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.