Electric Vehicle (EV) Charging Station / EVSE Permit (Electric Upgrade OTC Permit) in Unincorporated Yavapai County, Arizona

Yavapai County Development Services has no dedicated EV charger/EVSE permit application or fee line. An EV charging station installation is billed under the county's existing Over-the-Counter (OTC) permit category 'Electric Upgrade, Repair, or Reconnection of Service' -- the same OTC category used for panel upgrades and other electrical service work, per the county's Miscellaneous Permit Applications and Plan Review Criteria page (live URL returns 403 to automated fetch as of 2026-07-20, confirmed via a 2025-04-30 Wayback Machine snapshot of the same page, which lists the full OTC category set: Electric Upgrade, Repair, or Reconnection of Service; Natural Gas/Propane Installations or Conversions; Plumbing Repairs or Alterations; Woodstoves; Fireplace Inserts; Demolition; and Stucco). No electric-vehicle, EV charger, or EVSE term appears anywhere on that page or its listed submittal-requirement PDFs.

Verified 2026-07-20 · Source

When you need this permit

  • No standalone EV charger/EVSE permit application exists; EV charging station circuit installation is permitted under the existing 'Electric Upgrade, Repair, or Reconnection of Service' Over-the-Counter (OTC) permit category
  • OTC permits are issued without the full plan-review process applied to new construction -- apply through the same Customer Service & Permitting Unit counters (Prescott or Cottonwood) or the CitizenServe Online Permit Portal used for other permits
  • Work must be performed/permitted consistent with the electrical code Yavapai County has adopted for general electrical work (see the county's electrical-permit sourcing referenced elsewhere in this file for the applicable NEC edition)
  • As with the county's OTC panel-upgrade permit (referenced in the paired solar-pv-permit entry), confirm current OTC fee and submittal specifics directly with Development Services (928-771-3214), since the numeric OTC fee schedule was not independently retrievable in this session

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

OTC Electric Upgrade Permit (EV charger/EVSE circuit) — up to $5,000 valuationYavapai County Development Services, 2019 Valuation & Fee Schedule (adopted by the Board of Supervisors 12/5/2018, effective 1/14/2019, still the current schedule in force -- "shall supercede any previously adopted Building Safety fee schedules"), "UTILITIES" table: "SINGLE PERMIT; ELECTRICAL OR PLUMBING OR MECHANICAL EACH TRADE" -- $150.00 up to $5,000.00 valuation. The live fee-schedule PDF returns HTTP 403 to automated fetch tools (Cloudflare/WAF block); directly re-chased and confirmed via a Wayback Machine snapshot dated 2025-02-07 of the same PDF URL still linked from the live Building Safety Unit page.
$150.00 flat fee
OTC Electric Upgrade Permit (EV charger/EVSE circuit) — $5,001+ valuationSame 2019 Valuation & Fee Schedule, Part I general valuation table -- applies once electrical work exceeds $5,000 in declared value.
Per Valuation Table (Building Permit Fee only) -- e.g. $100.00 for $1-$5,000, plus $14.00 per additional $1,000 (or fraction) up to $25,000
Commercial Electric Upgrade (plans required)Same 2019 Valuation & Fee Schedule, "UTILITIES" table, Commercial line -- applies to non-residential/commercial EV charging installations regardless of valuation tier.
Per Valuation (Building Permit Fee)

Review timeline

Plan review
Not published — contact the department

How long did your Electric Vehicle (EV) Charging Station / EVSE Permit (Electric Upgrade OTC Permit) permit actually take in Unincorporated Yavapai County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical

    Standard electrical inspection tied to the OTC Electric Upgrade permit

See the full Unincorporated Yavapai County inspection guide — scheduling & re-inspection fees →

Tips

  • There is no dedicated EV charger permit category in Yavapai County -- apply for the existing 'Electric Upgrade, Repair, or Reconnection of Service' OTC permit and specify EV charging equipment installation in the application scope.
  • The OTC Electric Upgrade fee is $150.00 flat for installations valued up to $5,000 (typical for a residential EV charger circuit), per the county 2019 Valuation & Fee Schedule -- confirmed via Wayback Machine after the live PDF returned HTTP 403 to automated fetch tools; call Development Services directly (928-771-3214) to reconfirm the current amount if needed.

Frequently asked questions

Unincorporated Yavapai County requires an electric vehicle (ev) charging station / evse permit (electric upgrade otc permit) for: No standalone EV charger/EVSE permit application exists; EV charging station circuit installation is permitted under the existing 'Electric Upgrade, Repair, or Reconnection of Service' Over-the-Counter (OTC) permit category; OTC permits are issued without the full plan-review process applied to new construction -- apply through the same Customer Service & Permitting Unit counters (Prescott or Cottonwood) or the CitizenServe Online Permit Portal used for other permits; Work must be performed/permitted consistent with the electrical code Yavapai County has adopted for general electrical work (see the county's electrical-permit sourcing referenced elsewhere in this file for the applicable NEC edition); As with the county's OTC panel-upgrade permit (referenced in the paired solar-pv-permit entry), confirm current OTC fee and submittal specifics directly with Development Services (928-771-3214), since the numeric OTC fee schedule was not independently retrievable in this session. If your project isn't listed, confirm with Yavapai County Development Services — Customer Service & Permitting Unit (Building Safety Unit) at 928-771-3214 before starting work.

In Unincorporated Yavapai County, the published OTC Electric Upgrade Permit (EV charger/EVSE circuit) — up to $5,000 valuation is: $150.00 flat fee. Additional published fees: OTC Electric Upgrade Permit (EV charger/EVSE circuit) — $5,001+ valuation — Per Valuation Table (Building Permit Fee only) -- e.g. $100.00 for $1-$5,000, plus $14.00 per additional $1,000 (or fraction) up to $25,000; Commercial Electric Upgrade (plans required) — Per Valuation (Building Permit Fee). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Yavapai County does not publish a plan-review timeline for this permit. Contact Yavapai County Development Services — Customer Service & Permitting Unit (Building Safety Unit) at 928-771-3214 for current turnaround.

You'll need: OTC (Over-The-Counter) Electrical Permit Application. See the required-documents checklist on this page for details on each.

Unincorporated Yavapai County requires 1 inspection(s) for an electric vehicle (ev) charging station / evse permit (electric upgrade otc permit), in order: Electrical. Schedule each through Yavapai County Development Services — Customer Service & Permitting Unit (Building Safety Unit) (928-771-3214).

Apply through Yavapai County Development Services — Customer Service & Permitting Unit (Building Safety Unit) at 1120 Commerce Drive, Prescott, AZ 86305 (also: 10 S. 6th Street, Cottonwood, AZ 86326). Phone: 928-771-3214, email: web.development.services@yavapaiaz.gov. Office hours: Permit Technicians available 7:00 AM - 5:00 PM Monday through Friday. Two public counters: Prescott (1120 Commerce Drive, 928-771-3214, fax 928-771-3432) and Cottonwood (10 S. 6th Street, 928-639-8151). All permit applications are submitted through the CitizenServe Online Permit Portal (https://www4.citizenserve.com/Portal/PortalController?Action=showHomePage&ctzPagePrefix=Portal_&installationID=300). Source: https://www.yavapaiaz.gov/Development-and-Permits/Development-Services/Customer-Service-Permitting-Unit. Official information: https://www.yavapaiaz.gov/Development-and-Permits/Development-Services/Customer-Service-Permitting-Unit.

Unincorporated Yavapai County, Arizona has adopted: Arizona has no statewide mandatory building code floor for general construction — code adoption is a per-county/city authority. Yavapai County's Board of Supervisors independently adopts and administers its own construction codes for the unincorporated areas of the county through Development Services (Building Safety Unit); this is separate from, and does not apply within, the county's nine incorporated cities/towns (Prescott, Prescott Valley, Sedona, Cottonwood, Camp Verde, Chino Valley, Clarkdale, Dewey-Humboldt, Jerome), each of which adopts and enforces its own codes.; 2024 International Building Code (IBC), adopted by reference with Yavapai County amendments — Ordinance 2025-3, repealing and replacing Ordinance 2019-2, effective January 1, 2026. Includes Appendices A-P as amended. Source: 'Ordinances Adopting the 2024 International Building Codes...for the Unincorporated Areas of Yavapai County' (207-page ordinance compilation), https://www.yavapaiaz.gov/files/sharedassets/public/v/2/development-and-permits/codes-amp-regulations/documents/code-update/2025-signed-ordinance-secured.pdf.; 2024 International Residential Code for One- and Two-Family Dwellings (IRC), adopted with Yavapai County amendments — Ordinance 2025-4, effective January 1, 2026. Table R301.2 Climatic and Geographic Design Criteria is amended county-wide: basic wind speed 105 mph (Exposure C); Seismic Design Category C (county-wide, per amended R301.2.2.1); ground snow load 20-70 psf depending on elevation (footnote: over 7,000 ft requires site-specific analysis per Section R301.2.3); frost line depth 12 in below 4,500 ft, 18 in at 4,500-6,499 ft, 24 in at or above 6,500 ft; weathering negligible below 3,500 ft, moderate above 3,500 ft; termite damage potential negligible to moderate at/above 6,500 ft (see footnote); ice barrier underlayment NOT required; mean annual temperature 60°F at/below 3,500 ft, 50°F above 3,500 ft; air freezing index 1,500 or less. Source: same 2025-signed ordinance compilation, Ordinance 2025-4/IRC Table R301.2 amendment.; 2024 International Plumbing Code (IPC), adopted with Yavapai County amendments — Ordinance 2025-5, effective January 1, 2026.; 2024 International Mechanical Code (IMC), adopted with Yavapai County amendments — Ordinance 2025-6, effective January 1, 2026.; 2024 International Fuel Gas Code (IFGC), adopted with Yavapai County amendments — Ordinance 2025-7, effective January 1, 2026.; 2023 National Electrical Code (NEC), adopted with Yavapai County amendments — Ordinance 2025-8, effective January 1, 2026 (one edition behind the otherwise-2024 ICC set, consistent with the standard NFPA 3-year NEC cycle). Prior edition adopted under Ordinance 2007-7.; 2024 International Property Maintenance Code (IPMC), adopted with Yavapai County amendments — Ordinance 2025-9, effective January 1, 2026.; Yavapai County Grading Ordinance, adopted/updated — Ordinance 2025-10, effective January 1, 2026 (supersedes Grading Ordinance 2019-9, cited in the county's PB-22 Grading Submittal Requirements policy).; 2024 International Existing Building Code (IEBC), adopted with Yavapai County amendments — Ordinance 2025-11, effective January 1, 2026.; 2024 International Swimming Pool and Spa Code (ISPSC), adopted with Yavapai County amendments — Ordinance 2025-12, effective January 1, 2026 (newly adopted as its own title in this code cycle).; 2012 International Energy Conservation Code (IECC), adopted with Yavapai County amendments — Ordinance 2025-13, effective January 1, 2026. The county has NOT moved to a newer IECC edition; energy compliance for the 2024 code cycle is still evaluated under the 2012 IECC, mirroring the same 2012 IECC retention documented in this KB's Prescott entry.; Fire code enforcement in the unincorporated county is delegated to each area's local fire district under its own adopted fire code; where no authorized fire district exists, the State Fire Marshal's adopted fire code applies. Source: 2025 ordinance compilation, IBC Section on fire code applicability.. Local amendments apply — see the Unincorporated Yavapai County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Yavapai County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.