Skip to main content
PermitBase

Bow Mar building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Bow Mar, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
2 Middlefield Road, Columbine Valley, CO 80123
Phone
303-795-2063
Office hours
8:00am - 4:00pm, Monday through Friday (Building Department office, per the Town's live Building Permits page; the page notes these hours 'will be shortened due to COVID-19' — an apparently stale caveat still present on the live page as of the last verification). Building Department Coordinator Bonnie Zapata-Diaz. Bow Mar Building Inspector Terry Weis (reviews all plans and conducts all inspections) direct line 303-522-3331.

Published scheduling rules

  • Applications and inspection scheduling are submitted through SMFR's own Accela Permit Portal — a wholly separate system from the Town of Bow Mar's own permitting process used for the Building, Plumbing, Roofing, and Demolition permits documented elsewhere in this record (Fire Sprinkler & Fire Alarm System Permit (South Metro Fire Rescue))
  • Routine inspection requests submitted through the Accela Portal by 4:00 p.m. are conducted the next business day, or a later date up to 5 business days out if specifically requested; inspectors provide an estimated arrival window the morning of inspection (Fire Sprinkler & Fire Alarm System Permit (South Metro Fire Rescue))

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Location / Setback

    Per Bow Mar Ordinance Sec. 18-6 inspection list

  2. 2

    Footings, Trenches, Caissons, Pads and Foundation Wall

  3. 3

    Steel

  4. 4

    Waterproofing

  5. 5

    Ground Plumbing

  6. 6

    Rough Plumbing

  7. 7

    Rough Heating

  8. 8

    Frame

  9. 9

    Insulation

  10. 10

    Drywall

  11. 11

    Final Inspection

    Required before Certificate of Occupancy is issued; no building may be occupied until a Certificate of Occupancy has been issued

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footings/Foundation (if applicable)

  2. 2

    Rough Plumbing/Electrical/Mechanical

  3. 3

    Frame

  4. 4

    Insulation

  5. 5

    Final Inspection

Applies to: Fire Sprinkler & Fire Alarm System Permit (South Metro Fire Rescue)

  1. 1

    Plan Review

    SMFR reviews submitted system plans/hydraulic calculations/shop drawings before permit issuance, via the Accela Permit Portal

  2. 2

    Rough-In Inspection

    Piping (sprinkler) or wiring/devices (alarm) in place before concealment

  3. 3

    Final / Acceptance Test

    Hydrostatic and flow test for sprinkler systems; full alarm functional test for detection systems

Applies to: Change of Use / Change of Occupancy Permit (South Metro Fire Rescue)

  1. 1

    SMFR Occupancy Compliance Review

    South Metro Fire Rescue reviews the proposed change of occupancy against applicable fire-code requirements before permit issuance

  2. 2

    Town of Bow Mar Certificate of Occupancy Inspection

    Final inspection by the Town Building Department confirming the property is ready for occupancy under Sec. 18-7, if a new or updated Certificate of Occupancy is required as part of the change

Applies to: Deck / Patio / Fence Permit

  1. 1

    Footing Inspection

    For deck/patio structures involving new footings

  2. 2

    Final Inspection

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Heating

  2. 2

    Final Inspection

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Bow Mar Inspector lists inspections on the permit card (pass/fail)

  2. 2

    Final Plumbing

    When Final Plumbing Inspection has passed, the permit is completed and the job closed

Applies to: Roofing Permit

  1. 1

    Mid-Roof Inspection

    Required at 25% of installation

  2. 2

    Final Inspection

Re-inspection fees

Fire Sprinkler & Fire Alarm System Permit (South Metro Fire Rescue)Re-Inspection Fee / Release of Stop Work Order · SMFR 'Systems and Other Fees' schedule
$284.63

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bow Mar building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Bow Mar building permits

Get alerts for Bow Mar

We'll email you when Bow Mar's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.