How to schedule
Inspections are requested through the building department below.
- Address
- 2 Middlefield Road, Columbine Valley, CO 80123
- Phone
- 303-795-2063
- Office hours
- 8:00am - 4:00pm, Monday through Friday (Building Department office, per the Town's live Building Permits page; the page notes these hours 'will be shortened due to COVID-19' — an apparently stale caveat still present on the live page as of the last verification). Building Department Coordinator Bonnie Zapata-Diaz. Bow Mar Building Inspector Terry Weis (reviews all plans and conducts all inspections) direct line 303-522-3331.
- Website
- Official site
Published scheduling rules
- Applications and inspection scheduling are submitted through SMFR's own Accela Permit Portal — a wholly separate system from the Town of Bow Mar's own permitting process used for the Building, Plumbing, Roofing, and Demolition permits documented elsewhere in this record (Fire Sprinkler & Fire Alarm System Permit (South Metro Fire Rescue))
- Routine inspection requests submitted through the Accela Portal by 4:00 p.m. are conducted the next business day, or a later date up to 5 business days out if specifically requested; inspectors provide an estimated arrival window the morning of inspection (Fire Sprinkler & Fire Alarm System Permit (South Metro Fire Rescue))
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Location / Setback
Per Bow Mar Ordinance Sec. 18-6 inspection list
- 2
Footings, Trenches, Caissons, Pads and Foundation Wall
- 3
Steel
- 4
Waterproofing
- 5
Ground Plumbing
- 6
Rough Plumbing
- 7
Rough Heating
- 8
Frame
- 9
Insulation
- 10
Drywall
- 11
Final Inspection
Required before Certificate of Occupancy is issued; no building may be occupied until a Certificate of Occupancy has been issued
Applies to: Residential Addition / Remodel Permit
- 1
Footings/Foundation (if applicable)
- 2
Rough Plumbing/Electrical/Mechanical
- 3
Frame
- 4
Insulation
- 5
Final Inspection
Applies to: Fire Sprinkler & Fire Alarm System Permit (South Metro Fire Rescue)
- 1
Plan Review
SMFR reviews submitted system plans/hydraulic calculations/shop drawings before permit issuance, via the Accela Permit Portal
- 2
Rough-In Inspection
Piping (sprinkler) or wiring/devices (alarm) in place before concealment
- 3
Final / Acceptance Test
Hydrostatic and flow test for sprinkler systems; full alarm functional test for detection systems
Applies to: Change of Use / Change of Occupancy Permit (South Metro Fire Rescue)
- 1
SMFR Occupancy Compliance Review
South Metro Fire Rescue reviews the proposed change of occupancy against applicable fire-code requirements before permit issuance
- 2
Town of Bow Mar Certificate of Occupancy Inspection
Final inspection by the Town Building Department confirming the property is ready for occupancy under Sec. 18-7, if a new or updated Certificate of Occupancy is required as part of the change
Applies to: Deck / Patio / Fence Permit
- 1
Footing Inspection
For deck/patio structures involving new footings
- 2
Final Inspection
Applies to: Mechanical / HVAC Permit
- 1
Rough Heating
- 2
Final Inspection
Applies to: Plumbing Permit
- 1
Rough Plumbing
Bow Mar Inspector lists inspections on the permit card (pass/fail)
- 2
Final Plumbing
When Final Plumbing Inspection has passed, the permit is completed and the job closed
Applies to: Roofing Permit
- 1
Mid-Roof Inspection
Required at 25% of installation
- 2
Final Inspection
Final inspection only: Demolition Permit, Electrical Permit, EV Charger / EVSE Permit, Furnace / Water Heater Replacement Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bow Mar building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Bow Mar building permits
Get alerts for Bow Mar
We'll email you when Bow Mar's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.