Bow Mar building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Bow Mar, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
2 Middlefield Road, Columbine Valley, CO 80123
Phone
303-795-2063
Office hours
8:00am - 4:00pm, Monday through Friday (Building Department office, per the Town's live Building Permits page; the page notes these hours 'will be shortened due to COVID-19' — an apparently stale caveat still present on the live page as of this review). Building Department Coordinator Bonnie Zapata-Diaz. Bow Mar Building Inspector Terry Weis (reviews all plans and conducts all inspections) direct line 303-522-3331.

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Location / Setback

    Per Bow Mar Ordinance Sec. 18-6 inspection list

  2. 2

    Footings, Trenches, Caissons, Pads and Foundation Wall

  3. 3

    Steel

  4. 4

    Waterproofing

  5. 5

    Ground Plumbing

  6. 6

    Rough Plumbing

  7. 7

    Rough Heating

  8. 8

    Frame

  9. 9

    Insulation

  10. 10

    Drywall

  11. 11

    Final Inspection

    Required before Certificate of Occupancy is issued; no building may be occupied until a Certificate of Occupancy has been issued

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footings/Foundation (if applicable)

  2. 2

    Rough Plumbing/Electrical/Mechanical

  3. 3

    Frame

  4. 4

    Insulation

  5. 5

    Final Inspection

Applies to: Deck / Patio / Fence Permit

  1. 1

    Footing Inspection

    For deck/patio structures involving new footings

  2. 2

    Final Inspection

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Heating

  2. 2

    Final Inspection

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Bow Mar Inspector lists inspections on the permit card (pass/fail)

  2. 2

    Final Plumbing

    When Final Plumbing Inspection has passed, the permit is completed and the job closed

Applies to: Roofing Permit

  1. 1

    Mid-Roof Inspection

    Required at 25% of installation

  2. 2

    Final Inspection

Bow Mar building permits

Get alerts for Bow Mar

We'll email you when Bow Mar's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.