Fire Sprinkler & Fire Alarm System Permit (South Metro Fire Rescue) in Bow Mar, Colorado
Required for installation, alteration, or modification of an automatic fire sprinkler system or a fire alarm/detection system anywhere in Bow Mar. This permit is issued and inspected by South Metro Fire Rescue (SMFR), a separate fire protection district — NOT the Town of Bow Mar Building Department. Bow Mar's own Ordinance No. 340 amends the locally-adopted 2021 IFC (Secs. 103.1/103.2) to create the SMFR Fire Marshal's Office as the Town's fire code official, and SMFR's own live 'About Us' page confirms Bow Mar as a directly served jurisdiction. SMFR runs its own submittal portal (Accela), its own fee schedule, and publishes its own plan-review turnaround goal — genuinely separate from, and in addition to, the Town's own Building Permit process documented elsewhere in this file.
Verified 2026-08-13 · Source
When you need this permit
- Issued and inspected by South Metro Fire Rescue (SMFR), not the Town of Bow Mar Building Department — Ordinance No. 340 amends 2021 IFC Sec. 103.1 to create 'the South Metro Fire Rescue Fire Protection District...as the Fire Marshal's Office within the jurisdiction of the Town of Bow Mar' and Sec. 103.2 appoints 'the Fire Marshal of the South Metro Fire Rescue Fire Protection District, or designee' as the fire code official
- SMFR's own live 'About Us' page independently confirms Bow Mar as a served jurisdiction: 'SMFR proudly serves the cities of Bow Mar, Castle Pines, Centennial, Cherry Hills Village, Columbine Valley, Foxfield, Greenwood Village, Littleton, Lone Tree, and Parker...'
- Under IFC Sec. 105.6 (Required construction permits) as locally adopted, a construction permit is required to install, alter, or modify an automatic fire sprinkler system or a fire alarm system
- Governed by the 2021 IFC as locally amended by Ordinance No. 340; SMFR's own current fee schedule references NFPA 13/13D/13R sprinkler classifications (13D applies to one- and two-family dwellings, the relevant classification for nearly all Bow Mar construction) and NFPA 72 for fire alarm systems
- Applications and inspection scheduling are submitted through SMFR's own Accela Permit Portal — a wholly separate system from the Town of Bow Mar's own permitting process used for the Building, Plumbing, Roofing, and Demolition permits documented elsewhere in this file
- SMFR's own published plan-review turnaround GOAL (not a Town commitment): 'Our plan review turnaround time goal is to have comments back to the applicant in 5 business days or less, 90% of the time' — projects with higher complexity or submitted during heavy volume may take longer
- Over-the-Counter (OTC) same-business-day review is available for qualifying minor alterations to an EXISTING system if submitted by 11:00 a.m. — e.g. wet-pipe sprinkler alterations affecting up to 50 heads at light/ordinary hazard classification, fire alarm device substitution/relocation (up to 25 devices) or addition (up to 10 new devices), and emergency fire alarm control panel/dialer replacement; a brand-new system install does not qualify for OTC and goes through the standard 5-business-day-goal review instead
- Routine inspection requests submitted through the Accela Portal by 4:00 p.m. are conducted the next business day, or a later date up to 5 business days out if specifically requested; inspectors provide an estimated arrival window the morning of inspection
- This is a GENUINELY SEPARATE permit, fee, and review process from the Town of Bow Mar's own Building Permit (documented elsewhere in this file) — a new home in Bow Mar with a fire sprinkler system needs BOTH the Town's own Building Permit (with fire protection plans as part of the submitted plan set) AND this separate SMFR construction permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Plan Review
SMFR reviews submitted system plans/hydraulic calculations/shop drawings before permit issuance, via the Accela Permit Portal
- 2
Rough-In Inspection
Piping (sprinkler) or wiring/devices (alarm) in place before concealment
- 3
Final / Acceptance Test
Hydrostatic and flow test for sprinkler systems; full alarm functional test for detection systems
See the full Bow Mar inspection guide — scheduling & re-inspection fees →
Tips
- Budget for TWO entirely separate permit processes and fee schedules on any Bow Mar home with fire sprinklers or an alarm system: the Town's own Building Permit (this file's other entries, with fire protection plans as part of the submitted plan set) AND SMFR's own construction permit through the Accela Permit Portal — SMFR's review is not part of, or coordinated through, the Town Building Department's own review.
- SMFR's 5-business-day plan review goal is explicitly a 90%-of-the-time GOAL, not a guaranteed maximum, and it is separate from however long the Town Building Department itself takes to review the accompanying Building Permit, which publishes no timeline at all.
- Simple alterations to an EXISTING sprinkler or alarm system (a limited number of relocated/added heads or devices) may qualify for SMFR's Over-the-Counter same-business-day review if submitted by 11:00 a.m. — a genuinely faster path than the standard 5-day goal that applies to a brand-new system install.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bow Mar building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bow Mar
Fire Sprinkler & Fire Alarm System Permit (South Metro Fire Rescue) in other cities
Compare fire sprinkler & fire alarm system permit (south metro fire rescue) fees across Colorado →