Electrical permitting in the Town of Bow Mar is fully deferred to the Colorado State Electrical Board (DORA Division of Professions and Occupations) — the Town does NOT run its own local electrical permit or inspection program. Bow Mar Municipal Code Sec. 18-6 explicitly directs permit holders to 'contact the State Electrical Board concerning the permits, inspections and fees.' Electrical work is still governed technically by the current NEC (National Electrical Code) as adopted by the State of Colorado, per Sec. 18-19.

Verified 2026-07-06 · Source

When you need this permit

  • Contact the Colorado State Electrical Board (DORA) directly for the electrical permit, inspections, and fee schedule — per Bow Mar Municipal Code Sec. 18-6
  • Electricians must hold a current State of Colorado electrical license (master electrician or electrical contractor license) — the Town's Non-Structural Building Permit Application form requires proof of state licensing at time of registration Contractor
  • There is no separate Town of Bow Mar Electrical Contractor registration fee category (unlike General, Mechanical, Plumbing, and Roofing contractors) — consistent with electrical work routing entirely to the state program rather than a Town-run track Contractor
  • Governed technically by the current NFPA 70 National Electrical Code as adopted by the State of Colorado (2023 NEC, per the Town's own Non-Structural Building Permit Application form)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit FeeBow Mar Municipal Code Sec. 18-6 directs permit holders to the State Electrical Board for permits, inspections, and fees; no Town-level electrical fee is published or applicable
Set by the Colorado State Electrical Board (DORA), not the Town of Bow Mar

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Bow Mar?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    State Electrical Board Inspection

    Scheduled directly with the Colorado State Electrical Board, not the Town of Bow Mar Building Department

See the full Bow Mar inspection guide — scheduling & re-inspection fees →

Tips

  • Do not attempt to apply for an electrical permit through the Bow Mar Building Department / Columbine Valley Town Hall office — Bow Mar Municipal Code Sec. 18-6 directs applicants to the Colorado State Electrical Board directly for permits, inspections, and fees.
  • Electricians working in Bow Mar must still be Colorado state-licensed and are expected to provide proof of state licensing when registering subcontractor work with the Town, even though the permit itself is a state (not Town) permit. Contractor

Frequently asked questions

Bow Mar requires an electrical permit for: Contact the Colorado State Electrical Board (DORA) directly for the electrical permit, inspections, and fee schedule — per Bow Mar Municipal Code Sec. 18-6; Electricians must hold a current State of Colorado electrical license (master electrician or electrical contractor license) — the Town's Non-Structural Building Permit Application form requires proof of state licensing at time of registration; There is no separate Town of Bow Mar Electrical Contractor registration fee category (unlike General, Mechanical, Plumbing, and Roofing contractors) — consistent with electrical work routing entirely to the state program rather than a Town-run track; Governed technically by the current NFPA 70 National Electrical Code as adopted by the State of Colorado (2023 NEC, per the Town's own Non-Structural Building Permit Application form). If your project isn't listed, confirm with Town of Bow Mar Building Department at 303-795-2063 before starting work.

In Bow Mar, the published Electrical Permit Fee is: Set by the Colorado State Electrical Board (DORA), not the Town of Bow Mar. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Bow Mar does not publish a plan-review timeline for this permit. Contact Town of Bow Mar Building Department at 303-795-2063 for current turnaround.

You'll need: Colorado State Electrical Board Permit Application. See the required-documents checklist on this page for details on each.

Bow Mar requires 1 inspection(s) for an electrical permit, in order: State Electrical Board Inspection. Schedule each through Town of Bow Mar Building Department (303-795-2063).

Apply through Town of Bow Mar Building Department at 2 Middlefield Road, Columbine Valley, CO 80123. Phone: 303-795-2063, email: bzapata-diaz@columbinevalley.org. Office hours: 8:00am - 4:00pm, Monday through Friday (Building Department office, per the Town's live Building Permits page; the page notes these hours 'will be shortened due to COVID-19' — an apparently stale caveat still present on the live page as of this review). Building Department Coordinator Bonnie Zapata-Diaz. Bow Mar Building Inspector Terry Weis (reviews all plans and conducts all inspections) direct line 303-522-3331.. Official information: https://www.townofbowmar.org/building-permits.

Bow Mar, Colorado has adopted: 2021 International Building Code (IBC), including all Appendices — Bow Mar Municipal Code Sec. 18-8, adopted by Ordinance No. 340 (executed February 26, 2024); 2021 International Residential Code (IRC), including all Appendices, with local amendments — Sec. 18-9; 2021 International Mechanical Code (IMC) — Sec. 18-10; 2021 International Plumbing Code (IPC) — Sec. 18-11; 2021 International Fuel Gas Code (IFGC) — Sec. 18-12; 2021 International Property Maintenance Code (IPMC) — Sec. 18-13; 2021 International Fire Code (IFC), including Appendices B, C, and D, with local amendments — Sec. 18-14; 2021 International Energy Conservation Code (IECC) — Sec. 18-15; 2021 International Swimming Pool and Spa Code (ISPSC) — Sec. 18-16; 2021 International Existing Building Code (IEBC) — Sec. 18-17; ASME A17.1-2022 Safety Code for Elevators and Escalators — Sec. 18-18; National Electrical Code (NFPA 70), 'as currently adopted by the State of Colorado or as is from time to time modified, re-enacted, or re-adopted by the State of Colorado' — Sec. 18-19. This is a dynamic, floating adoption clause (not a fixed local edition); the Town's own Non-Structural Building Permit Application form states in writing that 'The Town of Bow Mar has adopted the 2021 International Building Code and the 2023 National Electric Code,' confirming the 2023 NEC is the currently-referenced edition as of this review.; All codes adopted via Ordinance No. 340, 'AN ORDINANCE OF THE BOARD OF TRUSTEES OF THE TOWN OF BOW MAR AMENDING CHAPTER 18 OF THE BOW MAR MUNICIPAL CODE BY THE ADOPTION OF VARIOUS REGULATIONS FROM THE INTERNATIONAL CODE COUNCIL, THE NATIONAL FIRE PROTECTION ASSOCIATION, AND THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS,' which repealed and replaced the prior 2015-edition code set (the ordinance's own recitals state Chapter 18 'previously adopted the 2015 edition of various codes published by the ICC') — full ordinance text retrieved directly as a PDF from the Town's website.. Local amendments apply — see the Bow Mar overview page for the full list.

No. Bow Mar Municipal Code Sec. 18-6 explicitly states that permit holders must contact the Colorado State Electrical Board concerning electrical permits, inspections, and fees. The Town has no separate electrical-contractor registration fee category, consistent with this full deferral to the state program.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bow Mar building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.