How to schedule
Inspections are requested through the building department below.
- Address
- 2 Middlefield Road, Columbine Valley, CO 80123
- Phone
- 303-795-1434
- Office hours
- Monday through Friday, 8 a.m. to 1 p.m., or by appointment (Town Hall itself is open until 4 p.m.). Building Department Coordinator: Bonnie Zapata-Diaz. Inspection requests must be called in to 303-795-1434 between 8 a.m. and noon, Monday through Friday. Dispatch line (non-emergency): 303-795-4711.
- Website
- Official site
Inspection sequence
Applies to: Building Permit with Plan Review (Addition / Structural Remodel)
- 1
Foundation (if new footings)
- 2
Rough Frame
Framing complete, tie-in to existing structure verified
- 3
Rough Electrical / Plumbing / Mechanical
- 4
Final Inspection
Applies to: Building Permit with Plan Review (New Construction)
- 1
Foundation
Before concrete pour
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment; electrical inspections specifically scheduled Mon/Wed/Thu/Fri 3:30-5:00 p.m.
- 4
Final Inspection
All work complete; Certificate of Occupancy issued following a passed final inspection
Applies to: Deck / Covered Patio Permit
- 1
Footing (if anchored by footings/caissons)
- 2
Final Inspection
Applies to: Electric Vehicle Charging Station Permit
- 1
Rough Electrical
New circuit/outlet wiring before concealment
- 2
Final Inspection
Charger installed, circuit verified, system energized
Applies to: Electrical Permit (Non-Structural Building Permit / Building Permit with Plan Review)
- 1
Rough Electrical
Wiring before concealment; electrical inspections specifically scheduled Monday, Wednesday, Thursday, Friday 3:30-5:00 p.m.
- 2
Final Inspection
Applies to: Mechanical / HVAC Permit (Non-Structural Building Permit)
- 1
Rough Mechanical
Ductwork/flue/equipment placement before concealment (larger installs only; simple like-for-like replacements may only require a final)
- 2
Final Inspection
Applies to: Plumbing Permit (Building Permit with Plan Review)
- 1
Rough Plumbing
Pipe, drain, waste, vent installation before concealment
- 2
Final Inspection
Applies to: Rooftop Solar / Photovoltaic Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before cover
- 2
Final Inspection
Racking, roof penetrations, and electrical connections verified
Final inspection only: Demolition Permit, Roofing Permit (Re-Roof)
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Columbine Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Columbine Valley building permits
Get alerts for Columbine Valley
We'll email you when Columbine Valley's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.