Electric Vehicle Charging Station Permit — Columbine Valley, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://columbinevalley.org/wp-content/uploads/2025/12/CV_Building_ProjectEvaluationFees_01.01.26.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle Charging Station Permit in Columbine Valley, Colorado
The Town does not publish a standalone EV charger/EVSE permit page or application. Checked the Building Permits, Other Permits, and Fee Schedule pages directly (columbinevalley.org/building-permits/, /street-cut-permit/, /fee-schedule/) — none name electric vehicle charging stations, EV chargers, or EVSE specifically. Based on the Town's own permit-track structure, installing an EV charger (a new circuit/outlet or electrical service modification) would fall under the 'Non-Structural Building Permit' track, the same track the Town names for other electrical service changes; a charger installation bundled with a larger structural remodel would instead fall under 'Building Permit with Plan Review.' Re-chased 2026-07-20: located and directly fetched the Town's actual, currently-effective Building Permit Fee Schedule PDF (CV_Building_ProjectEvaluationFees_01.01.26.pdf, effective Jan. 1, 2026), confirming the valuation-tiered fee table below is real and governs this permit track (no separate EV/EVSE line exists in it).
Verified 2026-07-20 · Source
When you need this permit
- No dedicated EV charger/EVSE permit application exists on the Town's website
- Electrical service change for a new circuit/outlet (the typical Level 1/Level 2 EV charger installation) would qualify for the Non-Structural Building Permit track, consistent with the Town's treatment of other electrical service modifications
- A charger installation involving structural work (e.g., new panel/service upgrade tied to a larger remodel) would instead require the Building Permit with Plan Review track
- Homeowners occupying their own property may perform electrical work without a contractor license, per the Town's FAQs, but must still obtain the applicable permit Contractor
- Governed by the 2023 NEC as adopted by the Town for the electrical work itself
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
New circuit/outlet wiring before concealment
- 2
Final Inspection
Charger installed, circuit verified, system energized
See the full Columbine Valley inspection guide — scheduling & re-inspection fees →
Tips
- Confirm directly with the Building Department (303-795-1434) which permit track (Non-Structural vs. Plan Review) applies to your specific EV charger installation, since the Town's website does not name EV chargers as their own category anywhere.
- A simple Level 1/Level 2 charger installed via a new outlet or circuit is most consistent with the Town's own named examples of Non-Structural Building Permit work (e.g., electrical service modifications).
- The general Building Permit Fee Schedule's $33 minimum tier (for $1-$500 valuation) will cover most simple EV charger circuit installations; larger service-upgrade projects scale up the same valuation-tiered table.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Columbine Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Columbine Valley
Electric Vehicle Charging Station Permit in other cities
Compare electric vehicle charging station permit fees across Colorado →
Look up this fee in a different city →