Change of Use / Change of Occupancy in Nederland, Colorado

All businesses starting in an existing brick-and-mortar building in Nederland require a One-Stop Building Permit for either Change of Occupancy (same use, new occupant) or Change of Use (alteration to a different type of business use), per the Town's own 'How-To Guide: Starting a Business in a Brick-and-Mortar' (revised 11/30/2021). A Change of Use permit requires review and approval of electronic floor plans provided by the applicant; work beyond this scope requires a full building remodel permit. Work must pass a full set of inspections before a new Certificate of Occupancy is issued for the changed use.

Verified 2026-08-14 · Source

When you need this permit

  • Submit a One-Stop Building Permit for Change of Occupancy (same use, new occupant) if there is nothing to remodel — just placing product on shelves and opening
  • Submit a One-Stop Building Permit for Change of Use (different type of business use) if the use type is changing; requires review/approval of electronic floor plans provided by the applicant
  • Changes beyond a simple change of use/occupancy (i.e., an interior remodel) require the full building-permit remodel process, including existing and new floor plans and payment of the plan review fee before plans are reviewed
  • Work must pass a full set of inspections for issuance of a new Certificate of Occupancy (C.O.) for the changed use
  • The Nederland Fire Protection District (NFPD) reviews plans for all new businesses: if the use type doesn't change and no remodeling is needed, the fire review is brief (inspection only, no fee, one-week notice required); if a change of use or remodel is planned, NFPD conducts a full plan review (submitted to inspections@nfpd.org) expected to take 3-4 weeks
  • NFPD full-review submittal must include: description of new business/use, site plan, current and planned floor plans, utility changes, egress changes, fire suppression/detection/alarm system changes, proposed lighting, and other significant changes
  • NFPD fees for a full plan review are assessed on a square-foot basis and must be paid prior to the Certificate of Occupancy being signed

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit / Plan Review Fee (remodel scope)Payment of the plan review fee is required before plans are reviewed for a remodel-scope change of use; specific dollar figure not published in the Town's How-To Guide. Contact the Building Department (303-258-3266).
Not published — contact the department
NFPD Fire Plan Review Fee (change of use or remodel only)Per the Town's How-To Guide: Starting a Business in a Brick-and-Mortar (11/30/2021). No fee applies for a same-use/no-remodel Change of Occupancy inspection.
Assessed on a square-foot basis; applicant notified of the fee once plans are submitted

Review timeline

Plan reviewNederland’s published plan-review target
21–28 business days

How long did your Change of Use / Change of Occupancy permit actually take in Nederland?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Department Inspection (no use change / no remodel)

    Brief inspection only, no fee; Town notifies NFPD when needed, one-week notice required

  2. 2

    Fire Department Full Plan Review and Inspection (change of use or remodel)

    Full review of submitted plans (expected 3-4 weeks), followed by inspection; fee assessed on a square-foot basis, paid before C.O. is signed

  3. 3

    Final Building Inspection / Certificate of Occupancy

    Work must pass a full set of building inspections before a new C.O. is issued for the changed use

See the full Nederland inspection guide — scheduling & re-inspection fees →

Tips

  • A same-use Change of Occupancy (new tenant, same business type, no remodel) is comparatively fast — brief fire inspection only, no fire-department fee, one week's notice. A true Change of Use or any remodel triggers a much longer path: full NFPD plan review (3-4 weeks) plus square-footage-based fire fees, on top of the Building Department's own floor-plan review.
  • Don't skip the fire department leg — NFPD reviews plans for ALL new businesses in Nederland, not just ones with a fire-suppression system, and its full review submittal (site plan, floor plans, egress, utility changes) is emailed directly to inspections@nfpd.org, separate from the Town's own Building Department submittal.

Frequently asked questions

Nederland requires a change of use / change of occupancy permit for: Submit a One-Stop Building Permit for Change of Occupancy (same use, new occupant) if there is nothing to remodel — just placing product on shelves and opening; Submit a One-Stop Building Permit for Change of Use (different type of business use) if the use type is changing; requires review/approval of electronic floor plans provided by the applicant; Changes beyond a simple change of use/occupancy (i.e., an interior remodel) require the full building-permit remodel process, including existing and new floor plans and payment of the plan review fee before plans are reviewed; Work must pass a full set of inspections for issuance of a new Certificate of Occupancy (C.O.) for the changed use; The Nederland Fire Protection District (NFPD) reviews plans for all new businesses: if the use type doesn't change and no remodeling is needed, the fire review is brief (inspection only, no fee, one-week notice required); if a change of use or remodel is planned, NFPD conducts a full plan review (submitted to inspections@nfpd.org) expected to take 3-4 weeks; NFPD full-review submittal must include: description of new business/use, site plan, current and planned floor plans, utility changes, egress changes, fire suppression/detection/alarm system changes, proposed lighting, and other significant changes; NFPD fees for a full plan review are assessed on a square-foot basis and must be paid prior to the Certificate of Occupancy being signed. If your project isn't listed, confirm with Town of Nederland Building, Planning & Zoning Department (Community Development) at 303-258-3266 before starting work.

Nederland's published plan-review target for a change of use / change of occupancy permit is 21–28 business days.

You'll need: One-Stop Building Permit Application (Change of Occupancy or Change of Use). Depending on your project, Nederland may also ask for: NFPD Fire Plan Review Submittal (change of use or remodel only). See the required-documents checklist on this page for details on each.

Nederland requires 3 inspection(s) for a change of use / change of occupancy permit, in order: Fire Department Inspection (no use change / no remodel), Fire Department Full Plan Review and Inspection (change of use or remodel), Final Building Inspection / Certificate of Occupancy. Schedule each through Town of Nederland Building, Planning & Zoning Department (Community Development) (303-258-3266).

Apply through Town of Nederland Building, Planning & Zoning Department (Community Development) at 45 West First Street, Nederland, CO 80466 (mailing: PO Box 396, Nederland, CO 80466). Phone: 303-258-3266, email: planner@nederlandco.org. Office hours: Nederland Town Hall open Monday to Friday, 9 a.m. to 5 p.m. In-person appointments with the Community Planner at Town Hall are available on a staggered schedule: first and third weeks of the month on Monday and Wednesday; second and fourth weeks on Wednesday and Friday. Virtual (Teams) meetings available any time by appointment. All Building/Right-of-Way permits and Land Use Applications are submitted to planner@nederlandco.org. Building inspections are scheduled directly with the Town's contracted plan-review/inspection firm, SAFEbuilt Colorado, at (303) 450-8745.. Official information: https://www.nederlandco.gov/building-planning-zoning-department.

Nederland, Colorado has adopted: 2024 ICC family of codes (IBC, IRC, IFC, IPC, IMC, IFGC, IECC, etc.) — per the Town of Nederland Building, Planning & Zoning Department's live 'Building Guides and Permits' webpage: 'The Town of Nederland is governed under the 2024 ICC codes, with 2026 National Electrical Code (NEC) in effect.' This is the department's actively maintained, currently published code-adoption statement and is treated as the governing current code cycle for this file.; Prior/superseded code-cycle documentation still in circulation on the Town's own site: the 'Nederland Design Criteria' PDF (Other Helpful Information page) lists 'ICC IBC/IRC (Bldg. codes) 2018' and 'Nat'l Electrical (NEC) 2020 or most current'; the Town's Residential Solar Photovoltaic (PV) System Permitting Checklist (dated 'effective 1/1/2022') lists a full adopted-code table of 2018 IBC/IRC/IMC/IPC/IFGC/IECC/IPMC/IEBC editions, 2020 NEC, ICC/ANSI 117.1 (2009), 2018 IFC, and 2018 International Swimming Pool and Spa Code; and the Residential Application Checklist (SAFEbuilt Colorado submittal list) references '2018 International Code Council IBC or IRC compliance' and '2018 IECC Energy Code Compliance.' These are static PDFs that have not yet been updated to match the live department webpage's current 2024 ICC / 2026 NEC statement — the same stale-PDF-vs-live-webpage pattern documented elsewhere in this corpus (e.g. Vail). The live webpage is treated as authoritative for the currently adopted cycle; the older documents are retained here for transparency since they remain published and may still describe design/plan-review expectations SAFEbuilt applies in practice.; HB22-1362 (Colorado statewide energy code floor / electrification-readiness requirements for municipalities adopting or updating a building code) was NOT found referenced anywhere on the Town of Nederland's Building, Planning & Zoning Department pages, adopted-codes statement, fee schedule, or permit-application PDFs during this review — checked directly. Nederland's own site states only that 2024 ICC codes (which as of the 2024 IECC cycle already carry more stringent efficiency provisions than 2018 IECC) are in effect, with no separate local ordinance citation for HB22-1362 compliance found. Not asserted as applying via a specific mechanism beyond the general 2024 IECC adoption; flagged as an area to verify further with the Building Department directly (303-258-3266) rather than invented.. Local amendments apply — see the Nederland overview page for the full list.

Yes. A new business in an existing building needs a One-Stop Building Permit for either Change of Occupancy (same use, new occupant — minimal review) or Change of Use (different business use — requires floor-plan review). The Nederland Fire Protection District also reviews plans for all new businesses, with a full review (change of use or remodel) expected to take 3-4 weeks.

Sources & verification

Verified against official sources. Last reviewed 2026-08-14.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nederland building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.