Skip to main content
PermitBase

Residential Addition / Remodel Permit in Nederland, Colorado

Required for additions and interior remodels to existing residential structures in Nederland. Renovations/alterations of 20% or more trigger the same mandatory Concept Review/Site Plan Review as new construction. Plan review and inspection performed by SAFEbuilt Colorado under the Town's currently adopted code cycle.

Reviewed 2026-07-06 · Source

When you need this permit

  • Concept Review/Site Plan Review with Town staff required before permit submittal if the project is a 20%+ alteration/enlargement of existing square footage, on sensitive land, or otherwise triggers Town review criteria
  • A survey may be substituted with an Improvement Location Certificate (ILC) for minimal development/renovation that does not change the building footprint; any footprint change requires a full survey
  • Active Town of Nederland Contractor License required for all contractors Contractor
  • Construction & Demolition (C&D) Debris Recycling Deposit applies if the project is an eligible alteration/remodel requiring a building permit (exempt if only mechanical/electrical/plumbing/HVAC permits are needed with no separate building-permit scope)
  • Electronic PDF plan submittal required

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Concept Review / Site Plan Review Fee (if triggered by 20%+ alteration)
Town of Nederland 2026 Fee Schedule, Building and Zoning section, page 2 — Concept Review/Site Plan for commercial and residential work involving 20% or more alteration or any new build, $275.00. Show full citationTown of Nederland 2026 Fee Schedule, Building and Zoning section, page 2 — Concept Review/Site Plan for commercial and residential work involving 20% or more alteration or any new build, $275.00. Consulting escrow is $1,000.00 residential, $1,500.00 commercial under one acre and $2,000.00 commercial at one acre or more. The Town's own pages publish both $250.00 and $275.00; the adopted 2026 schedule is $275.00, and the $250.00 previously recorded is the older figure.
$275.00 non-refundable + $1,000 residential escrow deposit
Building Permit FeeTown of Nederland Building Permit and Building Department Services Fee Schedule, Exhibit A, Table A — the schedule sets Table A as the fee for building permits generally and publishes no addition- or remodel-specific table
Same valuation-based Table A schedule as new construction (see residential-building-permit fees)
C&D Recycling Deposit
Town of Nederland Construction & Demolition Debris Recycling Deposit Program FAQ — deposits calculated at $0.25 per square foot of the project and collected at permit issuance, with 30% of the deposit non-refundable; Show full citationTown of Nederland Construction & Demolition Debris Recycling Deposit Program FAQ — deposits calculated at $0.25 per square foot of the project and collected at permit issuance, with 30% of the deposit non-refundable; the program page lists alteration/remodel among eligible project types
$0.25 per sq ft of project, 30% non-refundable, if the project scope triggers the program

Review timeline

Plan review
Not published — contact the department

How long did your Residential Addition / Remodel Permit permit actually take in Nederland?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment, per Residential Remodel Inspection List

  2. 2

    Final Inspection

    Final building, electrical, plumbing, and mechanical sign-off

See the full Nederland inspection guide — scheduling & re-inspection fees →

Tips

  • Only renovations/alterations of 20% or more of existing square footage trigger the mandatory Concept Review/Site Plan Review and its associated fees — smaller remodels may bypass this step, but confirm your project's percentage with the Building Department before assuming so.
  • An Improvement Location Certificate (ILC) is acceptable for minimal-scope renovations that don't change the building footprint, avoiding the cost and time of a full survey required for additions that do change the footprint.

Frequently asked questions

Nederland requires a residential addition / remodel permit for: Concept Review/Site Plan Review with Town staff required before permit submittal if the project is a 20%+ alteration/enlargement of existing square footage, on sensitive land, or otherwise triggers Town review criteria; A survey may be substituted with an Improvement Location Certificate (ILC) for minimal development/renovation that does not change the building footprint; any footprint change requires a full survey; Active Town of Nederland Contractor License required for all contractors; Construction & Demolition (C&D) Debris Recycling Deposit applies if the project is an eligible alteration/remodel requiring a building permit (exempt if only mechanical/electrical/plumbing/HVAC permits are needed with no separate building-permit scope); Electronic PDF plan submittal required. If your project isn't listed, confirm with Town of Nederland Building, Planning & Zoning Department (Community Development) at 303-258-3266 before starting work.

In Nederland, the published Concept Review / Site Plan Review Fee (if triggered by 20%+ alteration) is: $275.00 non-refundable + $1,000 residential escrow deposit. Additional published fees: Building Permit Fee — Same valuation-based Table A schedule as new construction (see residential-building-permit fees); C&D Recycling Deposit — $0.25 per sq ft of project, 30% non-refundable, if the project scope triggers the program. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Nederland does not publish a plan-review timeline for this permit. Contact Town of Nederland Building, Planning & Zoning Department (Community Development) at 303-258-3266 for current turnaround.

You'll need: Nederland Permit Application for New Residential and Commercial Construction; Residential Remodel Inspection List. See the required-documents checklist on this page for details on each.

Nederland requires 2 inspection(s) for a residential addition / remodel permit, in order: Rough-In Electrical / Plumbing / Mechanical, Final Inspection. Schedule each through Town of Nederland Building, Planning & Zoning Department (Community Development) (303-258-3266).

Apply through Town of Nederland Building, Planning & Zoning Department (Community Development) at 45 West First Street, Nederland, CO 80466 (mailing: PO Box 396, Nederland, CO 80466). Phone: 303-258-3266, email: planner@nederlandco.org. Office hours: Nederland Town Hall open Monday to Friday, 9 a.m. to 5 p.m. In-person appointments with the Community Planner at Town Hall are available on a staggered schedule: first and third weeks of the month on Monday and Wednesday; second and fourth weeks on Wednesday and Friday. Virtual (Teams) meetings available any time by appointment. All Building/Right-of-Way permits and Land Use Applications are submitted to planner@nederlandco.org. Building inspections are scheduled directly with the Town's contracted plan-review/inspection firm, SAFEbuilt Colorado, at (303) 450-8745.. Official information: https://www.nederlandco.gov/1289/Building-Planning-Zoning-Department.

Nederland, Colorado has adopted: 2024 ICC family of codes (IBC, IRC, IFC, IPC, IMC, IFGC, IECC, etc.) — per the Town of Nederland Building, Planning & Zoning Department's live 'Building Guides and Permits' webpage: 'The Town of Nederland is governed under the 2024 ICC codes, with 2026 National Electrical Code (NEC) in effect.' This is the department's actively maintained, currently published code-adoption statement and is treated as the governing current code cycle for this record.; Several documents still posted on the Town's site cite an older code cycle. The 'Nederland Design Criteria' PDF (Other Helpful Information page) lists 'ICC IBC/IRC (Bldg. codes) 2018' and 'Nat'l Electrical (NEC) 2020 or most current'. The Residential Solar Photovoltaic (PV) System Permitting Checklist (effective 1/1/2022) lists 2018 IBC/IRC/IMC/IPC/IFGC/IECC/IPMC/IEBC editions, 2020 NEC, ICC/ANSI 117.1 (2009), 2018 IFC, and the 2018 International Swimming Pool and Spa Code. The Residential Application Checklist (SAFEbuilt Colorado submittal list) references '2018 International Code Council IBC or IRC compliance' and '2018 IECC Energy Code Compliance.' The Building Department webpage states the current adopted cycle as 2024 ICC / 2026 NEC, and that is what governs. Use the older documents only as a guide to the design and plan-review detail SAFEbuilt asks for, and design to the current editions.; HB22-1362 (Colorado statewide energy code floor / electrification-readiness requirements for municipalities adopting or updating a building code) is not referenced anywhere on the Town of Nederland's Building, Planning & Zoning Department pages, adopted-codes statement, fee schedule, or permit-application PDFs. Nederland's own site states only that 2024 ICC codes (which as of the 2024 IECC cycle already carry more stringent efficiency provisions than 2018 IECC) are in effect, with no separate local ordinance citation for HB22-1362 compliance. No specific compliance mechanism beyond the general 2024 IECC adoption is asserted here; verify further with the Building Department directly (303-258-3266).. Local amendments apply — see the Nederland overview page for the full list.

Only if the remodel constitutes a 20% or greater alteration/enlargement of existing square footage, or is on sensitive land. Smaller remodels may not trigger this requirement, but the Building Department should be consulted to confirm.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nederland building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Nederland's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Nederland yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Nederland lands. Privacy.