Winter Park building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Winter Park, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
50 Vasquez Road, Suite B, P.O. Box 3327, Winter Park, CO 80482
Phone
(970) 726-8081
Office hours
Monday-Friday, 8:00am-5:00pm

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing and Foundation Inspection

    Must be performed/certified by a licensed Colorado design professional; includes reinforcing, UFER ground, damp-proofing, and perimeter drain as required

  2. 2

    Drilled Pier Inspection (if applicable)

    Made while piers are being drilled; licensed Colorado engineer of record or authorized representative must be present

  3. 3

    Lowest Floor Elevation / Elevation Certificate

    Submitted upon completion of footing/foundation and lowest floor placement, prior to further vertical construction and before framing begins, for Planning Division review

  4. 4

    Rough Framing / Rough Plumbing / Rough Mechanical

    Trade rough-ins before concealment; separate sub-permits required (plumbing per state-adopted IPC edition; mechanical per 2021 IMC)

  5. 5

    Energy Efficiency Inspection

    Envelope insulation R/U-values, fenestration U-values, duct system R-values, HVAC/water-heating efficiency; at owner's expense

  6. 6

    Final Building Inspection

    Requires all fees paid and sales/use tax audit completed or waived by the Town Manager before a certificate of occupancy is issued; 24 hours required after final inspection to prepare final documents

Applies to: Residential Addition / Remodel Permit

  1. 1

    Rough Framing (if structural)

  2. 2

    Rough Plumbing / Mechanical (if applicable to scope)

  3. 3

    Final Building Inspection

    Requires sales/use tax audit completion or waiver before certificate of occupancy/completion

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment installed but not concealed

  2. 2

    Final Mechanical

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Underground and rough-in plumbing installed, before concealment

  2. 2

    Final Plumbing

Applies to: Roofing Permit (Re-Roof)

  1. 1

    Underlayment / Ice Barrier Inspection

    Ice barrier and drip-edge installation verified before roof covering is completed

  2. 2

    Final Building Inspection

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Building Final (Winter Park/Fraser/Granby Building Department)

    Racking, roof penetrations, and structural attachment verified

  2. 2

    Electrical Final (State Electrical Board)

    Wiring, inverter, and interconnection verified before energizing

Re-inspection fees

Residential Building Permit (New Construction)Reinspection Fee
$47.00/hour (1-hour minimum)
Residential Addition / Remodel PermitReinspection Fee
$47.00/hour (1-hour minimum)
Plumbing PermitReinspection Fee
$47.00/hour (1-hour minimum)
Mechanical / HVAC PermitReinspection Fee
$47.00/hour (1-hour minimum)
Roofing Permit (Re-Roof)Reinspection Fee
$47.00/hour (1-hour minimum)

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Winter Park building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Winter Park building permits

Get alerts for Winter Park

We'll email you when Winter Park's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.