Residential Building Permit (New Construction) in Winter Park, Colorado
Required for new single-family homes, duplexes (two-family attached dwellings), and townhomes within the joint jurisdiction of Winter Park, Fraser, and Granby, administered by the Winter Park/Fraser/Granby Building Department. Reviewed under the 2021 IRC/IBC as locally amended by Winter Park Town Code Title 6, Chapter 1, including the Town's mountain-specific structural criteria (30-inch frost depth, ASCE-7-based snow/wind loads, 70 psf ground-snow-load stamping trigger).
Verified 2026-07-06 · Source
When you need this permit
- Fully completed and signed joint Building Permit Application (Towns of Winter Park, Fraser and Granby) — the job's town (Winter Park, Fraser, or Granby) must be circled; incomplete applications are not accepted
- All square footages must be GROSS square footage (outside to outside of exterior walls)
- Digital building plans, including a site plan previously approved by the Planning Commission (Minor Site Plan process for detached single-family/attached two-family homes), submitted in PDF to permits@wpgov.com
- Construction documents (foundations on caissons, non-conventional roof/wall framing, or site-specific ground snow load over 70 psf) must be prepared, stamped, and sealed by a licensed Colorado design professional
- Soils investigation report as required by subdivision plat notes
- Improvement Location Certificate (ILC) and Setback and Elevation Certificate from a licensed Colorado surveyor for all new foundations (Improvement Survey Plat required if within 5 ft of a property line or built into a variance-granted setback), submitted for Planning Division review/approval before framing begins
- Documentation of an approved water and sewer utility plan from the applicable water/sanitation district, including payment of tap fees
- Contractor Insurance Affidavit executed by the property owner
- Notification of Sales Tax Liability Agreement signed by the property owner
- East Grand Fire Protection District No. 4 Impact Fee Agreement signed by the property owner (Winter Park properties)
- Single-Family/Two-Family Attached Deposit Agreement plus $2,000.00 deposit (split between building exterior completion and landscaping/revegetation), required for detached single-family/attached two-family homes
- Foundation must be protected from frost per Town Code 6-1-2/6-1-3: extend 30 inches below the local frost line, design per ASCE 32, erect on solid rock, or per licensed design professional
- All footing/foundation systems must be designed AND inspected by a licensed Colorado design professional (reinforcing, UFER ground, damp-proofing/perimeter drain)
- Electrical permit is a SEPARATE application filed directly with the Colorado State Electrical Board, not with this Building Division
- Retaining walls of any height require a separate permit and licensed design professional
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 7 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing and Foundation Inspection
Must be performed/certified by a licensed Colorado design professional; includes reinforcing, UFER ground, damp-proofing, and perimeter drain as required
- 2
Drilled Pier Inspection (if applicable)
Made while piers are being drilled; licensed Colorado engineer of record or authorized representative must be present
- 3
Lowest Floor Elevation / Elevation Certificate
Submitted upon completion of footing/foundation and lowest floor placement, prior to further vertical construction and before framing begins, for Planning Division review
- 4
Rough Framing / Rough Plumbing / Rough Mechanical
Trade rough-ins before concealment; separate sub-permits required (plumbing per state-adopted IPC edition; mechanical per 2021 IMC)
- 5
Energy Efficiency Inspection
Envelope insulation R/U-values, fenestration U-values, duct system R-values, HVAC/water-heating efficiency; at owner's expense
- 6
Final Building Inspection
Requires all fees paid and sales/use tax audit completed or waived by the Town Manager before a certificate of occupancy is issued; 24 hours required after final inspection to prepare final documents
See the full Winter Park inspection guide — scheduling & re-inspection fees →
Tips
- Confirm which of the three towns (Winter Park, Fraser, Granby) your job site is in on the application — all three share this single Building Department, but the town circled affects which town's specific fee/tax ordinances and impact-fee agreements apply.
- Electrical work is NOT part of this Building Division's permit — apply separately and directly to the Colorado State Electrical Board.
- If your site-specific ground snow load exceeds 70 psf, or your framing departs from standard practice, budget for a licensed Colorado design professional's stamped plans — this is a lower, stricter trigger than in some peer mountain jurisdictions.
- The Town's own guidance is to allow at least two weeks just for first-round review comments — there is no published total-approval SLA, so build in schedule buffer accordingly.
- Retaining walls require a permit and a licensed design professional's design regardless of height in Winter Park — do not assume a low wall is exempt as it might be under a stock IBC/IRC reading.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Winter Park building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Winter Park
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Winter Park project checklist
Describe your project once and get every permit, document, and fee it triggers in Winter Park — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →