Morrison building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Morrison, Colorado.
Verified 2026-07-23 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 321 Highway 8, Morrison, CO 80465 (Town Hall); Building Department contract administration address listed as 4704 Harlan St, Suite 684, Lakeside, CO 80212
- Phone
- 303-697-8749
- Office hours
- Monday - Friday, 8:30 AM - 4:30 PM (Town of Morrison general hours, per website footer). Inspection requests must be submitted by 4:00 PM on the business day prior to the requested inspection date via the Town's online scheduling form.
- Website
- Official site
Inspection sequence
Applies to: Commercial Building Permit / Tenant Improvement
- 1
Foundation
Before concrete pour
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans and applicable codes, including occupancy approval
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans and applicable codes
Applies to: Residential Addition / Remodel Permit
- 1
Foundation (if new footings involved)
Before concrete pour
- 2
Rough Frame / Trade Rough-Ins
Framing, electrical, plumbing, and mechanical rough-ins before concealment
- 3
Final Inspection
All work complete per approved plans
Applies to: Solar PV Permit
- 1
Framing/Structural
Racking and roof-penetration/structural attachment inspection before cover
- 2
Rough Electrical
Wiring and panel installed before concealment; inspector may verify electrician identity/license at their discretion
- 3
Final Inspection
System energized and verified; devices installed and labeled per the adopted NEC edition
Applies to: Deck / Fence / Accessory Structure Permit
- 1
Footing/Foundation (deck)
Before concrete pour, for deck footings
- 2
Final Inspection
Structure complete, guardrail/handrail compliance verified for decks
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installed before concealment; inspector may verify electrician identity/license at their discretion
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified; inspector may verify electrician identity/license at their discretion
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Final inspection only: Demolition Permit, Roofing Permit (Re-Roof / Re-Shingle)
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Morrison building permits