Commercial Building Permit / Tenant Improvement in Morrison, Colorado
Required for commercial and multi-family construction, alteration, or tenant improvement work in Morrison. Reviewed under the 2015 IBC as locally adopted, using the Town's separate Commercial Plans Check List.
Verified 2026-07-23 · Source
When you need this permit
- Governed by the 2015 IBC as adopted by Morrison Municipal Code Section 9-1-2, as amended by Section 9-1-3
- Re-chased 2026-07-23: the Town's 'Commercial Plans Submittal Check List' (Document Center ID 13) was fetched and read in full — a 12-numbered-category list distinct from the residential checklist: (1) Building Permit Application fully completed (contractor/owner/contact/project address/estimated value); (2) Title Page stating building occupancy classification(s), construction type, gross and per-occupancy square footage, building height, occupant load, sprinklered/unsprinklered status, allowable building area, and area increases used; (3) Plot Plan (1/8"=1'-0" recommended) with lot dimensions, building footprint/projections to property lines, north arrow, easements, all parking including handicapped spaces/access aisles/curb ramps, handicapped access to the building from the public way, and location of any retaining walls (separate permit); (4) Foundation Plan with wet seal and signature by a design professional on each page (1/4"=1'-0" recommended) covering structural/architectural details, footings/foundations/piers/grade beams, post-and-girder intersections, and masonry-or-gas fireplaces; (5) Floor Plans (1/4"=1'-0" recommended), fully dimensioned/labeled, with an exit plan for each level detailing exit path and distance to exit discharge; (6) Exterior Elevations (1/4"=1'-0" recommended) identifying finish materials; (7) Structural and Architectural Details (3/4"=1'-0" recommended) covering roof/eaves/overhangs/rake/gables, floor changes (e.g. slab-to-wood-frame), handrail/guardrail/support details, structural framing details, fire wall/fire barrier/fire partition details, suspended ceiling plan with support details, structural sections at foundation/floor/roof levels, typical cross sections in each direction, and special inspections required; (8) Manufacturer's Specifications for Prefabricated Trusses; (9) HVAC Plan showing equipment location, duct layout for supply/return air, smoke/fire damper locations, CFMs of all HVAC units, and gas-line drawing with BTU input ratings; (10) Plumbing Layout showing all supply/drainage piping, water heaters, sewer connection location, grease/oil/sand interceptors with sizing calculations, and backflow-prevention device locations/types; (11) Electrical Plan showing panel size(s)/location(s), outlet layout, switching layout, and ground-fault/arc-fault outlet locations; (12) Handicapped Accessibility defining all access features for new construction per the then-current IBC and ANSI A-117.1 (1998 edition), with remodels/tenant improvements required to bring the improved area up to new-construction access standards including an accessible route of travel to the remodeled area
- All plans should be prepared to the same rigor implied by the residential checklist (engineer-stamped structural/foundation details, full architectural plan set) given the shared adopted-code basis
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans and applicable codes, including occupancy approval
See the full Morrison inspection guide — scheduling & re-inspection fees →
Tips
- The Commercial Plans Submittal Check List requires a Title Page (occupancy classification, construction type, square footage, height, occupant load, sprinkler status, allowable area) not required on the Residential checklist — budget extra time to compile these code-analysis figures, typically prepared by the project's architect/engineer of record.
- Foundation Plan pages require a wet seal AND signature by the design professional on each page — a stricter requirement than the residential checklist's foundation-plan language.
- Handicapped accessibility compliance is assessed against ANSI A-117.1 (1998 edition) as referenced in the Town's checklist alongside the current IBC; remodels/tenant improvements must bring the improved area up to new-construction accessibility standards, including an accessible route of travel to the remodeled area.
- Morrison contracts with a third-party provider for code enforcement/occupancy approval on both residential and commercial properties — confirm current provider and process expectations directly given the discrepancy noted elsewhere in this file between the Town's website and its most recent fee resolution/payment records.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Morrison.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Morrison
Commercial Building Permit / Tenant Improvement in other cities
Compare commercial building permit / tenant improvement fees across Colorado →