Required for installation of rooftop or ground-mounted solar photovoltaic systems in the Town of Morrison. No dedicated solar/photovoltaic line item appears in Resolution 2025-13's Single Stop Fees list (unlike furnace, AC, re-roof, or fence) — a PV installation is billed under the Town's general valuation-based Building Permit Fee for the structural/racking scope, plus the Town's own electrical permit process (with contemporaneous Colorado state-license review) for the interconnection scope, since Morrison issues both building and electrical permits itself rather than deferring to the state.

Verified 2026-07-20 · Source

When you need this permit

  • Structural/racking scope reviewed under the 2015 IBC/IRC as locally adopted (Morrison Municipal Code Section 9-1-2); electrical interconnection scope governed by the National Electrical Code edition currently adopted by the Colorado State Electrical Board (DORA), per Section 9-1-2
  • Electrical interconnection requires the listed electrician's name and Colorado state electrical license number on the permit application; the Town verifies the license is active via the DORA online License Lookup before approving the permit, per the Town's Electrical License Contemporaneous Review Guidelines (CRS 12-23-105/110.5/116(10))
  • No dedicated Solar/Photovoltaic Single Stop Fee line exists in Resolution 2025-13 (2026 Fee Schedule) — confirmed by direct review of the Town's most recent fee resolution, which lists Air Conditioner, Demolition, Fence, Furnace, Hot Tub & Spas, Lawn Sprinkler System, Roof, Siding, Water Heater, and Window Replacement as its Single Stop Fee categories, with no solar/PV item among them
  • Two sets of plans expected consistent with the Residential Plans Submittal Check List categories applicable to the scope (structural/architectural details for racking, electrical details showing service meter/breaker/sub-panel locations for interconnection)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (structural/racking scope)Resolution 2025-13 (2026 Fee Schedule), Section B — no dedicated solar/PV Single Stop Fee line exists; billed under the general valuation-based Building Permit Fee, same as the residential-building-permit entry in this file.
Per the adopted code (2015 IBC valuation-based fee table)
Plan Review FeeResolution 2025-13, Section B
70% of Building Permit Fee
Re-Inspection Fee
$100.00 per hour, 2-hour minimum

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Morrison?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing/Structural

    Racking and roof-penetration/structural attachment inspection before cover

  2. 2

    Rough Electrical

    Wiring and panel installed before concealment; inspector may verify electrician identity/license at their discretion

  3. 3

    Final Inspection

    System energized and verified; devices installed and labeled per the adopted NEC edition

See the full Morrison inspection guide — scheduling & re-inspection fees →

Tips

  • Morrison has no flat Single Stop Fee for solar (unlike furnace $100, AC $75, or re-roof $100) — a PV installation is billed under the full valuation-based Building Permit Fee plus 70% Plan Review Fee, so budget accordingly rather than assuming a flat-fee category applies.
  • The electrical interconnection component goes through the same Town-run contemporaneous license-review process as any other electrical work: your installer's Colorado state electrical license must be active and verifiable via the DORA License Lookup before the Town will approve the permit.
  • Morrison's NEC edition automatically tracks whichever edition the Colorado State Electrical Board (DORA) currently has adopted — confirm the current statewide-adopted edition with DORA if it is decision-critical for your project.

Frequently asked questions

Morrison requires a solar pv permit for: Structural/racking scope reviewed under the 2015 IBC/IRC as locally adopted (Morrison Municipal Code Section 9-1-2); electrical interconnection scope governed by the National Electrical Code edition currently adopted by the Colorado State Electrical Board (DORA), per Section 9-1-2; Electrical interconnection requires the listed electrician's name and Colorado state electrical license number on the permit application; the Town verifies the license is active via the DORA online License Lookup before approving the permit, per the Town's Electrical License Contemporaneous Review Guidelines (CRS 12-23-105/110.5/116(10)); No dedicated Solar/Photovoltaic Single Stop Fee line exists in Resolution 2025-13 (2026 Fee Schedule) — confirmed by direct review of the Town's most recent fee resolution, which lists Air Conditioner, Demolition, Fence, Furnace, Hot Tub & Spas, Lawn Sprinkler System, Roof, Siding, Water Heater, and Window Replacement as its Single Stop Fee categories, with no solar/PV item among them; Two sets of plans expected consistent with the Residential Plans Submittal Check List categories applicable to the scope (structural/architectural details for racking, electrical details showing service meter/breaker/sub-panel locations for interconnection). If your project isn't listed, confirm with Town of Morrison Building Department at 303-697-8749 before starting work.

No. Unlike furnace, AC, re-roof, and several other narrow-scope categories, Resolution 2025-13's Single Stop Fees list does not include a solar/photovoltaic line item. A PV installation is billed under the Town's general valuation-based Building Permit Fee (per the adopted 2015 IBC) plus a 70% Plan Review Fee.

Morrison does not publish a plan-review timeline for this permit. Contact Town of Morrison Building Department at 303-697-8749 for current turnaround.

You'll need: Morrison Building Permit Application; Electrical Permit component (listing licensed electrician). See the required-documents checklist on this page for details on each.

Morrison requires 3 inspection(s) for a solar pv permit, in order: Framing/Structural, Rough Electrical, Final Inspection. Schedule each through Town of Morrison Building Department (303-697-8749).

Apply through Town of Morrison Building Department at 321 Highway 8, Morrison, CO 80465 (Town Hall); Building Department contract administration address listed as 4704 Harlan St, Suite 684, Lakeside, CO 80212. Phone: 303-697-8749, email: building@morrisonco.us. Office hours: Monday - Friday, 8:30 AM - 4:30 PM (Town of Morrison general hours, per website footer). Inspection requests must be submitted by 4:00 PM on the business day prior to the requested inspection date via the Town's online scheduling form.. Official information: https://www.morrisonco.us/140/Building-Department.

Morrison, Colorado has adopted: 2015 International Building Code (IBC), chapters 1-35 inclusive and appendix chapter I — Morrison Municipal Code Section 9-1-2 (Codes Adopted By Reference), current through 2026 S-15 supplement; 2015 International Residential Code (IRC), chapters 1-44 inclusive and appendix chapter H — Section 9-1-2; 2015 International Mechanical Code (IMC), chapters 1-15 inclusive — Section 9-1-2; 2015 International Fuel Gas Code (IFGC), chapters 1-8 inclusive — Section 9-1-2; 2015 International Plumbing Code (IPC), chapters 1-15 inclusive — Section 9-1-2; 2015 International Fire Code (IFC), chapters 1-80 inclusive — Section 9-1-2; 2015 International Energy Conservation Code (IECC), Residential and Commercial chapters 1-6 — Section 9-1-2; 2015 International Existing Building Code (IEBC), chapters 1-16 inclusive with all appendices — Section 9-1-2; 2015 International Swimming Pool and Spa Code, chapters 1-11 inclusive with all appendices — Section 9-1-2; 2015 International Property Maintenance Code, chapters 1-8 inclusive with all appendices — Section 9-1-2; National Electrical Code (NEC), 'the most current edition adopted by the Colorado State Electrical Board, Department of Regulatory Agencies' — Morrison's own code text ties its NEC edition to whichever edition the Colorado State Electrical Board (DORA) currently has in force, rather than fixing a specific year itself; as of this review the Colorado State Electrical Board's currently adopted edition is the 2023 NEC (per DORA Division of Professions and Occupations rules), so 2023 NEC is the effective edition in Morrison, subject to change automatically if DORA updates its adopted edition; Colorado Wildfire Resiliency Code, 2025 edition, adopted and published by the Wildfire Resiliency Code Board within the Division of Fire Prevention and Control, Colorado Department of Public Safety — adopted by reference as the Town of Morrison wildfire resiliency code (Section 9-1-2, subsection M); HB22-1362 (Colorado statewide building greenhouse-gas-emissions / energy code law) note: HB22-1362 only obligates a municipality or county to adopt an equivalent-or-better energy code WHEN it next updates one or more of its building codes — it does not retroactively force an update on jurisdictions that haven't touched their codes. Morrison's adopted energy code is still the 2015 IECC (per Section 9-1-2, unchanged since original codification), so the HB22-1362 floor (2021 IECC-equivalent performance from 7/1/2023-6/30/2026; Model Low Energy and Carbon Code-equivalent performance from 7/1/2026 onward) has NOT yet been triggered for Morrison because the Town has not updated its building code since adopting the 2015 cycle. This is a genuine, current compliance gap/lag relative to HB22-1362's intent, not an omission by this file — confirmed against the Colorado Energy Office's published HB22-1362 timeline.. Local amendments apply — see the Morrison overview page for the full list.

The Town of Morrison issues its own electrical permit for the PV interconnection, with contemporaneous review of the installing electrician's Colorado state license (verified via the DORA License Lookup) — the same process used for all other electrical work in Morrison, per the Town's Electrical License Contemporaneous Review Guidelines.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.