Plumbing Permit in Morrison, Colorado
Required for plumbing work in Morrison, issued as part of the Town's general Building Permit process. Governed by the 2015 International Plumbing Code (IPC) as adopted by Morrison Municipal Code Section 9-1-2.
Verified 2026-07-23 · Source
When you need this permit
- Governed by the 2015 IPC as adopted by the Town of Morrison
- Issued under the Town's general Building Permit Application; the Residential Plans Submittal Check List requires Plumbing Details (2 sets) showing all plumbing fixture and water heater locations and all floor drain locations
- Contractors performing plumbing work must hold current Colorado State Plumbing Board (DORA) licensure. Re-chased 2026-07-23: located 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (Colorado Chapter ICC guide, adopted/hosted by the Town in its Building Department Document Center, Document ID 1229) — this guide, developed under HB19-1086 (Plumbing, effective 1/1/2020) and SB19-156 (Electrical, effective 7/1/2019), confirms inspections of projects requiring a plumbing permit must include a contemporaneous review of plumbing licenses (full or partial, at the inspector's discretion), with non-compliance reportable to the State Plumbing Board under C.R.S. Title 12, Article 58/155 — Morrison's plumbing-license review process is thus confirmed to mirror its electrical process rather than being an undocumented gap. This document was found via the Document Center's Building Department folder tree (Ant Design tree component, reachable via its internal AJAX API), not linked from the main Building Department webpage — a new avenue beyond the page/Document Center/code checks made in the prior (2026-07-06) review
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
See the full Morrison inspection guide — scheduling & re-inspection fees →
Tips
- Plumbing permits in Morrison are issued under the same general Building Permit Application as building/mechanical/electrical work, not a standalone plumbing-specific form, for new construction and additions.
- Morrison's plumbing-license verification follows the same 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' as electrical work — inspectors may conduct full or partial license reviews of plumbers/apprentices on site, with a focus on large commercial and multi-family projects; non-compliance is reportable to the Colorado State Plumbing Board.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Morrison
Plumbing Permit in other cities
Compare plumbing permit fees across Colorado →
Look up this fee in a different city →