Plumbing Permit in Morrison, Colorado
Required for plumbing work in Morrison, issued as part of the Town's general Building Permit process. Governed by the 2015 International Plumbing Code (IPC) as adopted by Morrison Municipal Code Section 9-1-2.
Verified 2026-07-23 · Source
When you need this permit
- Governed by the 2015 IPC as adopted by the Town of Morrison
- Issued under the Town's general Building Permit Application; the Residential Plans Submittal Check List requires Plumbing Details (2 sets) showing all plumbing fixture and water heater locations and all floor drain locations
- Contractors performing plumbing work must hold current Colorado State Plumbing Board (DORA) licensure. The Town adopts/hosts the 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (Colorado Chapter ICC guide, Building Department Document Center, Document ID 1229) — this guide, developed under HB19-1086 (Plumbing, effective 1/1/2020) and SB19-156 (Electrical, effective 7/1/2019), provides that inspections of projects requiring a plumbing permit must include a contemporaneous review of plumbing licenses (full or partial, at the inspector's discretion), with non-compliance reportable to the State Plumbing Board under C.R.S. Title 12, Article 58/155 — Morrison's plumbing-license review process mirrors its electrical process. The document lives in the Document Center's Building Department folder and is not linked from the main Building Department webpage
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Town of Morrison fee schedule adopted by Resolution 2026-01 (effective 7 April 2026), Section B, page 3 — Re-Inspection Fee, $80.00 flat. Show full citationHide
Town of Morrison fee schedule adopted by Resolution 2026-01 (effective 7 April 2026), Section B, page 3 — Re-Inspection Fee, $80.00 flat. The $100.00 per hour with a two-hour minimum previously recorded belongs to the Outside Regular Hours Inspection Fee on the row below, together with its “Minimum 2 hour charge” note; the two-line “Mobile, Manufactured, Factory Home” label above has an empty fee cell, which puts the fee column out of phase in extracted text. Section B is unchanged from the preceding schedule effective 1 January 2026.Review timeline
Inspection process
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
See the full Morrison inspection guide — scheduling & re-inspection fees →
Tips
- Plumbing permits in Morrison are issued under the same general Building Permit Application as building/mechanical/electrical work, not a standalone plumbing-specific form, for new construction and additions.
- Morrison's plumbing-license verification follows the same 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' as electrical work — inspectors may conduct full or partial license reviews of plumbers/apprentices on site, with a focus on large commercial and multi-family projects; non-compliance is reportable to the Colorado State Plumbing Board.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Applications & forms
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Morrison's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Morrison yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Morrison lands. Privacy.
Other permits in Morrison
Plumbing Permit in other cities
Compare plumbing permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Morrison project checklist
Describe your project once and get every permit, document, and fee it triggers in Morrison — in one checklist. Free, for any city and any number of projects.
Get started →