Required for plumbing work in Morrison, issued as part of the Town's general Building Permit process. Governed by the 2015 International Plumbing Code (IPC) as adopted by Morrison Municipal Code Section 9-1-2.

Verified 2026-07-23 · Source

When you need this permit

  • Governed by the 2015 IPC as adopted by the Town of Morrison
  • Issued under the Town's general Building Permit Application; the Residential Plans Submittal Check List requires Plumbing Details (2 sets) showing all plumbing fixture and water heater locations and all floor drain locations
  • Contractors performing plumbing work must hold current Colorado State Plumbing Board (DORA) licensure. Re-chased 2026-07-23: located 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (Colorado Chapter ICC guide, adopted/hosted by the Town in its Building Department Document Center, Document ID 1229) — this guide, developed under HB19-1086 (Plumbing, effective 1/1/2020) and SB19-156 (Electrical, effective 7/1/2019), confirms inspections of projects requiring a plumbing permit must include a contemporaneous review of plumbing licenses (full or partial, at the inspector's discretion), with non-compliance reportable to the State Plumbing Board under C.R.S. Title 12, Article 58/155 — Morrison's plumbing-license review process is thus confirmed to mirror its electrical process rather than being an undocumented gap. This document was found via the Document Center's Building Department folder tree (Ant Design tree component, reachable via its internal AJAX API), not linked from the main Building Department webpage — a new avenue beyond the page/Document Center/code checks made in the prior (2026-07-06) review

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (plumbing work billed under the general adopted-code fee table)Resolution 2025-13, Section B — no standalone plumbing-fee line is published separately from the general Building Permit Fee
Per the adopted code
Re-Inspection Fee
$100.00 per hour, 2-hour minimum

Review timeline

Plan review
Not published — contact the department

How long did your Plumbing Permit permit actually take in Morrison?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

See the full Morrison inspection guide — scheduling & re-inspection fees →

Tips

  • Plumbing permits in Morrison are issued under the same general Building Permit Application as building/mechanical/electrical work, not a standalone plumbing-specific form, for new construction and additions.
  • Morrison's plumbing-license verification follows the same 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' as electrical work — inspectors may conduct full or partial license reviews of plumbers/apprentices on site, with a focus on large commercial and multi-family projects; non-compliance is reportable to the Colorado State Plumbing Board.

Frequently asked questions

Morrison requires a plumbing permit for: Governed by the 2015 IPC as adopted by the Town of Morrison; Issued under the Town's general Building Permit Application; the Residential Plans Submittal Check List requires Plumbing Details (2 sets) showing all plumbing fixture and water heater locations and all floor drain locations; Contractors performing plumbing work must hold current Colorado State Plumbing Board (DORA) licensure. Re-chased 2026-07-23: located 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (Colorado Chapter ICC guide, adopted/hosted by the Town in its Building Department Document Center, Document ID 1229) — this guide, developed under HB19-1086 (Plumbing, effective 1/1/2020) and SB19-156 (Electrical, effective 7/1/2019), confirms inspections of projects requiring a plumbing permit must include a contemporaneous review of plumbing licenses (full or partial, at the inspector's discretion), with non-compliance reportable to the State Plumbing Board under C.R.S. Title 12, Article 58/155 — Morrison's plumbing-license review process is thus confirmed to mirror its electrical process rather than being an undocumented gap. This document was found via the Document Center's Building Department folder tree (Ant Design tree component, reachable via its internal AJAX API), not linked from the main Building Department webpage — a new avenue beyond the page/Document Center/code checks made in the prior (2026-07-06) review. If your project isn't listed, confirm with Town of Morrison Building Department at 303-697-8749 before starting work.

In Morrison, the published Building Permit Fee (plumbing work billed under the general adopted-code fee table) is: Per the adopted code. Additional published fees: Re-Inspection Fee — $100.00 per hour, 2-hour minimum. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Morrison does not publish a plan-review timeline for this permit. Contact Town of Morrison Building Department at 303-697-8749 for current turnaround.

You'll need: Morrison Building Permit Application. See the required-documents checklist on this page for details on each.

Morrison requires 2 inspection(s) for a plumbing permit, in order: Rough Plumbing, Final Inspection. Schedule each through Town of Morrison Building Department (303-697-8749).

Apply through Town of Morrison Building Department at 321 Highway 8, Morrison, CO 80465 (Town Hall); Building Department contract administration address listed as 4704 Harlan St, Suite 684, Lakeside, CO 80212. Phone: 303-697-8749, email: building@morrisonco.us. Office hours: Monday - Friday, 8:30 AM - 4:30 PM (Town of Morrison general hours, per website footer). Inspection requests must be submitted by 4:00 PM on the business day prior to the requested inspection date via the Town's online scheduling form.. Official information: https://www.morrisonco.us/140/Building-Department.

No standalone plumbing-only permit application was found for general plumbing work tied to new construction or additions — plumbing scope is submitted as part of the Town's general Building Permit Application and Residential/Commercial Plans Submittal Check List.

Yes. The Town's 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (adopted per HB19-1086 and SB19-156) applies the same contemporaneous license-review process to plumbing work as to electrical work, with inspectors empowered to review plumbers'/apprentices' Colorado state licenses on site and refer violations to the State Plumbing Board.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.