Required for demolition of a structure or portion of a structure in Morrison. Billed as a flat Single Stop Fee per Resolution 2025-13.

Verified 2026-07-06 · Source

When you need this permit

  • Governed by the 2015 IBC/IRC as adopted by Morrison Municipal Code Section 9-1-2
  • Demolition permit application submitted via the Town's general Building Permit Application process

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Single Stop Fee — DemolitionResolution 2025-13, Section B, Single Stop Fees list
$100.00

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit permit actually take in Morrison?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection (demolition)

    Site cleared/made safe per approved scope

See the full Morrison inspection guide — scheduling & re-inspection fees →

Tips

  • Demolition is billed at Morrison's flat Single Stop Fee ($100.00) per Resolution 2025-13 — confirm whether any utility disconnect coordination (water/sewer) is needed separately with the Town given Morrison's own municipal water/sewer utility.

Frequently asked questions

Morrison requires a demolition permit for: Governed by the 2015 IBC/IRC as adopted by Morrison Municipal Code Section 9-1-2; Demolition permit application submitted via the Town's general Building Permit Application process. If your project isn't listed, confirm with Town of Morrison Building Department at 303-697-8749 before starting work.

A demolition permit is billed at a flat $100.00 Single Stop Fee per Resolution 2025-13 (2026 Fee Schedule).

Morrison does not publish a plan-review timeline for this permit. Contact Town of Morrison Building Department at 303-697-8749 for current turnaround.

You'll need: Morrison Building Permit Application — Demolition scope. See the required-documents checklist on this page for details on each.

Morrison requires 1 inspection(s) for a demolition permit, in order: Final Inspection (demolition). Schedule each through Town of Morrison Building Department (303-697-8749).

Apply through Town of Morrison Building Department at 321 Highway 8, Morrison, CO 80465 (Town Hall); Building Department contract administration address listed as 4704 Harlan St, Suite 684, Lakeside, CO 80212. Phone: 303-697-8749, email: building@morrisonco.us. Office hours: Monday - Friday, 8:30 AM - 4:30 PM (Town of Morrison general hours, per website footer). Inspection requests must be submitted by 4:00 PM on the business day prior to the requested inspection date via the Town's online scheduling form.. Official information: https://www.morrisonco.us/140/Building-Department.

Morrison, Colorado has adopted: 2015 International Building Code (IBC), chapters 1-35 inclusive and appendix chapter I — Morrison Municipal Code Section 9-1-2 (Codes Adopted By Reference), current through 2026 S-15 supplement; 2015 International Residential Code (IRC), chapters 1-44 inclusive and appendix chapter H — Section 9-1-2; 2015 International Mechanical Code (IMC), chapters 1-15 inclusive — Section 9-1-2; 2015 International Fuel Gas Code (IFGC), chapters 1-8 inclusive — Section 9-1-2; 2015 International Plumbing Code (IPC), chapters 1-15 inclusive — Section 9-1-2; 2015 International Fire Code (IFC), chapters 1-80 inclusive — Section 9-1-2; 2015 International Energy Conservation Code (IECC), Residential and Commercial chapters 1-6 — Section 9-1-2; 2015 International Existing Building Code (IEBC), chapters 1-16 inclusive with all appendices — Section 9-1-2; 2015 International Swimming Pool and Spa Code, chapters 1-11 inclusive with all appendices — Section 9-1-2; 2015 International Property Maintenance Code, chapters 1-8 inclusive with all appendices — Section 9-1-2; National Electrical Code (NEC), 'the most current edition adopted by the Colorado State Electrical Board, Department of Regulatory Agencies' — Morrison's own code text ties its NEC edition to whichever edition the Colorado State Electrical Board (DORA) currently has in force, rather than fixing a specific year itself; as of this review the Colorado State Electrical Board's currently adopted edition is the 2023 NEC (per DORA Division of Professions and Occupations rules), so 2023 NEC is the effective edition in Morrison, subject to change automatically if DORA updates its adopted edition; Colorado Wildfire Resiliency Code, 2025 edition, adopted and published by the Wildfire Resiliency Code Board within the Division of Fire Prevention and Control, Colorado Department of Public Safety — adopted by reference as the Town of Morrison wildfire resiliency code (Section 9-1-2, subsection M); HB22-1362 (Colorado statewide building greenhouse-gas-emissions / energy code law) note: HB22-1362 only obligates a municipality or county to adopt an equivalent-or-better energy code WHEN it next updates one or more of its building codes — it does not retroactively force an update on jurisdictions that haven't touched their codes. Morrison's adopted energy code is still the 2015 IECC (per Section 9-1-2, unchanged since original codification), so the HB22-1362 floor (2021 IECC-equivalent performance from 7/1/2023-6/30/2026; Model Low Energy and Carbon Code-equivalent performance from 7/1/2026 onward) has NOT yet been triggered for Morrison because the Town has not updated its building code since adopting the 2015 cycle. This is a genuine, current compliance gap/lag relative to HB22-1362's intent, not an omission by this file — confirmed against the Colorado Energy Office's published HB22-1362 timeline.. Local amendments apply — see the Morrison overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.