Electric Vehicle (EV) Charger Permit in Morrison, Colorado

Morrison publishes no distinct EV-charger permit type, checklist, or fee line — confirmed against the Town's Permits & Checklists page, which lists Building, Commercial, Residential, Electrical, and various how-to guides (garage, patio, carport, deck, reroof, etc.) with no EV-charger/EVSE entry. A new circuit, outlet, or panel/service upgrade to serve an EV charger would be processed as a standalone 'electrical only permit,' governed by the National Electrical Code edition adopted by the Colorado State Electrical Board and reviewed under Morrison's contemporaneous electrician-license-verification process (CRS 12-23-105/110.5/116(10)). Morrison's small population (roughly 430 residents) is well below the 10,000-resident municipal threshold that triggers Colorado HB24-1173's EV-charging-permit mandate.

Verified 2026-07-23 · Source

When you need this permit

  • A new circuit, outlet, or panel/service upgrade to serve an EV charger requires a standalone 'electrical only permit,' governed by the National Electrical Code edition currently adopted by the Colorado State Electrical Board (Morrison Municipal Code Section 9-1-2)
  • The listed electrician's name and Colorado state electrical license number must appear on the permit application; applications without a listed, verifiable electrician are rejected
  • The Town verifies the listed electrician's license via the DORA online License Lookup
  • No EV-specific application, checklist, or expedited process was found published — apply via the standard Morrison Building Permit Application marked as electrical-only work

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (electrical work billed under the general adopted-code fee table)Confirmed 2026-07-23 directly against the Town's standalone Fee Schedule documents (Resolution 2025-13/eff. 1/1/2026; and the currently-governing Resolution 2026-01, eff. 4/7/2026) — Section B (Building Permit Fees) has no distinct 'Electrical' or 'EV charger' line item in either version; electrical work (including EV-charger circuits) is billed under the general valuation-based Building Permit Fee 'per the adopted code,' consistent with the general electrical-permit entry in this same file. This is a confirmed negative (no such fee line exists), not an unpublished gap — reached via the Town's clean, standalone Fee Schedule PDFs (Document Center) rather than the noisier full Board of Trustees agenda-packet PDF used in the 2026-07-20 chase.
Per the adopted code
Re-Inspection Fee
$100.00 per hour, 2-hour minimum

Review timeline

Plan review
Not published — contact the department

How long did your Electric Vehicle (EV) Charger Permit permit actually take in Morrison?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    See the full Morrison inspection guide — scheduling & re-inspection fees →

    Tips

    • There is no Morrison-specific 'EV charger permit' — a new circuit or outlet for EV charging falls under the Town's standard standalone electrical-only permit process.
    • Morrison's population (~430) is far below the 10,000-resident threshold that triggers Colorado HB24-1173's municipal EV-charging-permit mandate, so the Town is not confirmed to be legally required to have adopted EV-specific permitting standards.
    • Confirm scope and fee directly with the Building Department (303-697-8749) before applying; the Town contracts building-code enforcement to Charles Abbott Associates, Inc.

    Frequently asked questions

    Morrison has not published EV-specific guidance, but a new electrical circuit or outlet to serve an EV charger would require the Town's standard standalone electrical-only permit, with the installing electrician's Colorado state license verified against the DORA License Lookup.

    In Morrison, the published Building Permit Fee (electrical work billed under the general adopted-code fee table) is: Per the adopted code. Additional published fees: Re-Inspection Fee — $100.00 per hour, 2-hour minimum. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    Morrison does not publish a plan-review timeline for this permit. Contact Town of Morrison Building Department at 303-697-8749 for current turnaround.

    You'll need: Morrison Building Permit Application (Electrical-Only). See the required-documents checklist on this page for details on each.

    Apply through Town of Morrison Building Department at 321 Highway 8, Morrison, CO 80465 (Town Hall); Building Department contract administration address listed as 4704 Harlan St, Suite 684, Lakeside, CO 80212. Phone: 303-697-8749, email: building@morrisonco.us. Office hours: Monday - Friday, 8:30 AM - 4:30 PM (Town of Morrison general hours, per website footer). Inspection requests must be submitted by 4:00 PM on the business day prior to the requested inspection date via the Town's online scheduling form.. Official information: https://www.morrisonco.us/140/Building-Department.

    Morrison, Colorado has adopted: 2015 International Building Code (IBC), chapters 1-35 inclusive and appendix chapter I — Morrison Municipal Code Section 9-1-2 (Codes Adopted By Reference), current through 2026 S-15 supplement; 2015 International Residential Code (IRC), chapters 1-44 inclusive and appendix chapter H — Section 9-1-2; 2015 International Mechanical Code (IMC), chapters 1-15 inclusive — Section 9-1-2; 2015 International Fuel Gas Code (IFGC), chapters 1-8 inclusive — Section 9-1-2; 2015 International Plumbing Code (IPC), chapters 1-15 inclusive — Section 9-1-2; 2015 International Fire Code (IFC), chapters 1-80 inclusive — Section 9-1-2; 2015 International Energy Conservation Code (IECC), Residential and Commercial chapters 1-6 — Section 9-1-2; 2015 International Existing Building Code (IEBC), chapters 1-16 inclusive with all appendices — Section 9-1-2; 2015 International Swimming Pool and Spa Code, chapters 1-11 inclusive with all appendices — Section 9-1-2; 2015 International Property Maintenance Code, chapters 1-8 inclusive with all appendices — Section 9-1-2; National Electrical Code (NEC), 'the most current edition adopted by the Colorado State Electrical Board, Department of Regulatory Agencies' — Morrison's own code text ties its NEC edition to whichever edition the Colorado State Electrical Board (DORA) currently has in force, rather than fixing a specific year itself; as of this review the Colorado State Electrical Board's currently adopted edition is the 2023 NEC (per DORA Division of Professions and Occupations rules), so 2023 NEC is the effective edition in Morrison, subject to change automatically if DORA updates its adopted edition; Colorado Wildfire Resiliency Code, 2025 edition, adopted and published by the Wildfire Resiliency Code Board within the Division of Fire Prevention and Control, Colorado Department of Public Safety — adopted by reference as the Town of Morrison wildfire resiliency code (Section 9-1-2, subsection M); HB22-1362 (Colorado statewide building greenhouse-gas-emissions / energy code law) note: HB22-1362 only obligates a municipality or county to adopt an equivalent-or-better energy code WHEN it next updates one or more of its building codes — it does not retroactively force an update on jurisdictions that haven't touched their codes. Morrison's adopted energy code is still the 2015 IECC (per Section 9-1-2, unchanged since original codification), so the HB22-1362 floor (2021 IECC-equivalent performance from 7/1/2023-6/30/2026; Model Low Energy and Carbon Code-equivalent performance from 7/1/2026 onward) has NOT yet been triggered for Morrison because the Town has not updated its building code since adopting the 2015 cycle. This is a genuine, current compliance gap/lag relative to HB22-1362's intent, not an omission by this file — confirmed against the Colorado Energy Office's published HB22-1362 timeline.. Local amendments apply — see the Morrison overview page for the full list.

    Sources & verification

    Verified against official sources. Last reviewed 2026-07-23.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morrison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.