Required for uncovered decks, patio covers/carports, and enclosing existing patios in Holyoke. The city publishes three distinct Colorado Chapter ICC 'Building Guide' fill-in-the-blank worksheets for these scopes (Uncovered Decks, Patio Covers & Carports, Enclosing a Patio), used alongside the general Building Permit Application. The governing code is IRC 2018 (Holyoke Municipal Code §15.08.010), whose locally modified §105.2 exempt list directly covers small uncovered decks — see requirements.

Verified 2026-07-23 · Source

When you need this permit

  • Completed City of Holyoke Building Permit Application with Class of Work marked appropriately (typically 'New' or 'Addition')
  • For uncovered decks: guardrail height, baluster spacing, footing depth/size, and beam/joist sizing per the city's Uncovered Decks Building Guide worksheet
  • For patio covers/carports: post spacing, beam and rafter sizing, and attachment-to-existing-structure details per the Patio Covers & Carport Building Guide worksheet
  • For enclosing an existing patio: window/door egress and safety glazing requirements, insulation values, and structural connection details per the Enclosing a Patio Building Guide worksheet
  • Two sets of scaled site plans and two sets of scaled construction plans, per the general instructions printed on each Building Guide worksheet
  • CONFIRMED 2026-07-23 (Holyoke Municipal Code §15.08.020, IRC 2018 local modification): an UNCOVERED DECK is exempt from a building permit if it does not exceed 120 sq ft in area, is not more than 18 inches above grade at any point, is not attached to a dwelling, and does not serve a required exit door (IRC §R311.4) — decks exceeding any of those thresholds, or patio covers/carports/enclosures generally, DO require a permit. Retaining walls over 4 feet and fences over 7 feet also require a permit per the same section.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit FeeHolyoke Municipal Code § 17.44.050 — permit fees are set by a standalone city council resolution, the consolidated fee schedule, which the City does not publish online. Fees are calculated by city staff at issuance.
Not published — contact the department

Review timeline

Plan review
Not published — contact the department

How long did your Deck / Patio Cover / Enclosed Patio Permit permit actually take in Holyoke?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    For decks and patio covers with new footings, before concrete pour

  2. 2

    Framing

    Structural framing/posts/beams before decking or roofing installation

  3. 3

    Final Inspection

    Completed structure verified, including guardrail/baluster compliance for decks

See the full Holyoke inspection guide — scheduling & re-inspection fees →

Tips

  • Holyoke publishes three separate scope-specific Building Guide worksheets for this permit category (Uncovered Decks, Patio Covers & Carports, Enclosing a Patio) rather than one combined form — use the worksheet matching your exact project scope to avoid missing scope-specific details like guardrail height or egress glazing.
  • These worksheets are generic 2003-era Colorado Chapter ICC statewide templates, not confirmation of Holyoke's currently enforced code edition — treat them as a submittal aid only; the actual currently-enforced code is IRC 2018 (confirmed 2026-07-23, Holyoke Municipal Code §15.08.010).
  • A small uncovered deck can be exempt from a permit entirely — under 120 sq ft, 18 inches or less above grade, not attached to the dwelling, and not serving a required exit door (Holyoke Municipal Code §15.08.020). Patio covers, carports, and patio enclosures do not get this exemption and always require a permit.

Frequently asked questions

It depends on size. The city publishes a dedicated 'Uncovered Decks' Building Guide worksheet as part of its Building Department document center, and decks are generally a permitted scope requiring the general Building Permit Application plus this worksheet — BUT per Holyoke Municipal Code §15.08.020, a deck under 120 sq ft, no more than 18 inches above grade, not attached to the dwelling, and not serving a required exit door is exempt from a permit.

Holyoke does not publish a plan-review timeline for this permit. Contact City of Holyoke Building Department at 970-854-2266 for current turnaround.

You'll need: City of Holyoke Building Permit Application. Depending on your project, Holyoke may also ask for: Uncovered Decks / Patio Covers & Carport / Enclosing a Patio Building Guide worksheet. See the required-documents checklist on this page for details on each.

Holyoke requires 3 inspection(s) for a deck / patio cover / enclosed patio permit, in order: Footing/Foundation, Framing, Final Inspection. Schedule each through City of Holyoke Building Department (970-854-2266).

Apply through City of Holyoke Building Department at 407 E. Denver Street, Holyoke, CO 80734. Phone: 970-854-2266, email: contactus@cityofholyoke-co.gov. Office hours: City offices Monday-Friday 8:00 AM to 5:00 PM (closed weekends), per the City of Holyoke Forms & Documents page. No separate Building Department-specific hours or direct phone/email distinct from the main city line (970-854-2266 / contactus@cityofholyoke-co.gov) were found published anywhere on the city's site as of the last verification; the Building Department does not have its own dedicated staff-listing or contact page distinct from the city's general Forms & Documents / Business Office pages.. Official information: https://www.cityofholyoke-co.gov/departments/forms_documents.php.

Holyoke, Colorado has adopted: Watch for a same-name collision when searching: https://www.holyoke.org/departments/building/ is the City of Holyoke, MASSACHUSETTS Building Department (413-322-5600, City Hall Annex Room 300, buildcon@holyoke.org), a completely different municipality. The City of Holyoke, COLORADO -- Phillips County, 407 E. Denver Street, 970-854-2266 -- publishes at https://www.cityofholyoke-co.gov. Everything in this record comes from cityofholyoke-co.gov and its linked documents, plus Colorado statewide electrical and plumbing jurisdiction rules; nothing comes from the Massachusetts site.; The Holyoke Municipal Code is published on Municode (library.municode.com/co/holyoke). Title 15 - BUILDINGS AND CONSTRUCTION is codified as Supplement 2, 'Online content updated on December 13, 2024,' 'Codified through Ordinance No. 1-2024, enacted September 17, 2024.' Holyoke has adopted, by reference, as its own local code (each chapter states a certified copy is on file with the city clerk): International Building Code, 2018 edition, incl. appendices C/E/I/J (Sec. 15.04.010); International Residential Code, 2018 edition (Sec. 15.08.010); International Mechanical Code, 2018 edition, incl. appendix A (Sec. 15.12.010); International Fire Code, 2018 edition, incl. appendices B/C/D/I (Sec. 15.16.010); International Energy Conservation Code, 2018 edition (Sec. 15.20.010); International Existing Building Code, 2018 edition (Sec. 15.22.010); 'the most recent edition of the Colorado Plumbing Code as adopted by the state plumbing board' as the city's own Plumbing Code, no fixed year — it floats to whatever edition the state plumbing board currently has in effect (Sec. 15.24.010); and the National Electrical Code, 2017 edition, 'as adopted by the state' (Sec. 15.26.010). Quoted directly from the Municode text.; Local modifications on file: IBC 2018 Sec. 101.1 retitled 'Building Code of the City of Holyoke'; Sec. 103 deleted; Sec. 105.2 (Work Exempt from Permit) amended so 'fences not over six feet, three inches high' and 'retaining walls...not over four feet' are REMOVED from the exempt list (i.e., these now DO require a permit; see chapter 17.28 for fencing). IRC 2018 Sec. 101.1 retitled 'Residential Code of the City of Holyoke'; Sec. 104.10.1 (Flood Hazard Areas) deleted; Sec. 105.2 amended — exempt from permit: one-story detached accessory structures ≤120 sq ft; and 'decks not exceeding 120 square feet in area, that are not more than 18 inches above grade at any point, are not attached to a dwelling and do not serve the exit door required by section R311.4'; also exempt: like-for-like window/door replacement with no framing change; Sec. R313 (Automatic Fire Sprinkler Systems) deleted; Sec. N1102.4.1.2 (Testing) deleted. IMC 2018 Sec. 106.2 amended to exempt like-for-like category-one furnace/water-heater and A/C replacement (R-3 occupancies, prior install permitted/inspected/approved) from a new permit, and adds 'Sec. 106.5.2 Fee schedule. Fees for any permit, plan review or inspection required by this code shall be established from time to time by resolution of the city council' (confirms the fee-setting mechanism — a standalone council resolution, not a codified table — while the dollar figures themselves remain unpublished online; see the fee-schedule note below). IFC 2018 and IECC 2018 each retitled to the City of Holyoke's name in Sec. 101.1/C101.1 with no other substantive local modification noted.; HB22-1362 (Colorado's statewide low-energy/carbon code requirement) and its predecessor HB19-1260 both operate on a 'when a jurisdiction updates its building code, the energy code update must accompany it' trigger — neither is a blanket mandate independent of a local update, and neither contains a population-based exemption threshold. The IECC edition currently on Holyoke's books is 2018 (not a newer low-energy cycle), but exactly when Title 15's ICC chapters were last substantively enacted or updated cannot be established from the published code: none of the Sec. 15.04.010 through 15.26.010 adoption sections carries an inline '(Ord. No. ___, ____)' legislative-history citation in the Municode text (unlike, e.g., the Mobile Home chapter at Sec. 15.28.010, which cites 'Ord. No. 5-1975'), and the code's front-matter 'codified through Ordinance No. 1-2024' banner reflects the single most-recent ordinance affecting ANY part of the whole Municipal Code, not necessarily Title 15 specifically. Whether HB22-1362 currently binds Holyoke therefore remains genuinely unresolved — recorded as such, not assumed either way — though whatever cycle IS in force is the 2018 ICC family.; Holyoke Municipal Code Title 15 contains the City's OWN codified Electrical Code chapter (Sec. 15.26.010, adopting NEC 2017 'as adopted by the state,' expressly 'to provide for the issuance of permits and collection of fees therefor') and Plumbing Code chapter (Sec. 15.24.010, adopting by reference the state plumbing board's current Colorado Plumbing Code 'as the plumbing code of the CITY... providing for the issuance of permits and collection of fees therefor'). Both are codified as the City's own local ordinances under Title 15 - Buildings and Construction (footnoted to C.R.S. § 31-15-601 et seq., municipal building/fire-regulation power, and C.R.S. § 31-16-202, authority to adopt codes by reference) — not merely descriptive cross-references to a separate state process. This corroborates, on a primary legal source, the City's own Forms & Documents page listing 'wiring' and 'plumbing' among its administered Building Department permit types, and as a home-rule municipality Holyoke has independent authority to run its own electrical/plumbing permitting program regardless of whether DORA's 'no state inspections in these counties' list includes Phillips County — that DORA list concerns default authority over unincorporated county land, not an incorporated home-rule city's own adopted code. Electrical and plumbing permits in Holyoke are therefore City-issued (City of Holyoke Building Department), under Secs. 15.26.010 and 15.24.010 respectively — not State of Colorado (DORA) issued. The ordinance text does not address whether the City's own staff performs the physical inspections in-house or engages a state-certified/contract inspector — that operational detail remains unconfirmed.; The fee-setting mechanism is confirmed by primary ordinance text even though the dollar figures are unpublished online: IMC Sec. 106.5.2 ('Fees...shall be established from time to time by resolution of the city council'); Zoning Sec. 17.44.050, Building permit—Fee ('A fee for the examination and administration of a building permit shall be payable to the city upon receipt of the application. The fee shall be as set from time to time by action of the city council and set out in the fee schedule.'); and the Mobile Home Regulations chapter, which repeatedly references applicants paying 'a fee in an amount set out in the consolidated fee schedule' (Secs. 15.28.040, 15.28.090). All three confirm Holyoke fees are set by a standalone CITY COUNCIL RESOLUTION establishing a 'consolidated fee schedule' — a document that is NOT part of the codified ordinances Municode publishes and is not located anywhere online: the city's city_council.php and city_clerk.php pages post no agendas, minutes or resolutions; the only fee document on the cityofholyoke-co.gov domain is an unrelated 'Records Request Fees Schedule.pdf' (a CORA records-request fee document, not a building-permit fee schedule); and a web search for 'City of Holyoke Colorado fee schedule resolution building permit' returns only the wrong-jurisdiction holyoke.org Massachusetts site plus unrelated other-Colorado-jurisdiction fee schedules. The consolidated fee schedule exists as a real governing document adopted by council resolution, but its actual dollar figures are not recoverable from public online sources.. Local amendments apply — see the Holyoke overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Holyoke building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Property Access

Holyoke's permit history is searchable by address

1,605 permits on record for Holyoke, 2015–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.

96% of Holyoke's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.

Start your 7-day free trial7 days free for new customers, then $79/mo · the guide above stays free