EV Charger / EVSE Permit in Holyoke, Colorado

Holyoke has no dedicated EV charger or EVSE permit and no distinct fee line item for electric vehicle charging equipment. As with every other permit type in this file, the City of Holyoke Building Department publishes no fee schedule (valuation table, flat rate, or square-footage rate) online -- an EV charger installation would use the same general Building Permit Application used for other construction, with the fee block filled in by city staff at issuance rather than computed from a public rate table. Colorado's HB24-1173 (2024), which mandates expedited/standardized EV-charger permitting, applies only to counties of 20,000+ and municipalities of 10,000+ population -- Holyoke (population roughly 2,000) falls well below that threshold and is not a covered municipality under the statute.

Reviewed 2026-07-20 · Source

When you need this permit

  • Completed City of Holyoke Building Permit Application, same general form used for other construction, describing the EV charger installation's scope, materials cost, and labor cost
  • RESOLVED 2026-07-23: electrical permit authority in Holyoke is City-issued, not State-issued -- Holyoke Municipal Code §15.26.010 codifies the City's OWN Electrical Code (NEC 2017), expressly providing for city issuance of permits and city collection of fees, corroborating the Forms & Documents page's listing of 'wiring' among city-administered permit types; the charger circuit is therefore inspected under the City's own code, not the Colorado State Electrical Board
  • Holyoke does not meet the 10,000-population municipality threshold that triggers Colorado HB24-1173's mandatory model-code/expedited-review requirement for EV charger permits, so that statute does not apply here
  • Same 180-day permit expiration clause applies as with any other Holyoke building permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeNo fee schedule (valuation table, flat rate, or square-footage rate) is published anywhere on the City of Holyoke website or in its downloadable applications for any permit type, including EV chargers; the Building Permit Application's 'For Official Use Only' section is filled in by city staff at issuance. Confirm current fee directly with the Building Department (970-854-2266).
Not published — contact the department
Use TaxA separate Use Tax line appears on the official permit form, confirming a municipal use tax applies to permitted construction including EV charger installations, but no rate or formula is published.
Not published — contact the department

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Holyoke?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Electrical

    Charger circuit and disconnect verified; per Holyoke Municipal Code §15.26.010 (confirmed 2026-07-23), performed by the City of Holyoke Building Department under its own Electrical Code (NEC 2017), not the Colorado State Electrical Board

See the full Holyoke inspection guide — scheduling & re-inspection fees →

Tips

  • Holyoke publishes no fee schedule for any permit type, including EV chargers -- call ahead (970-854-2266) for a fee estimate.
  • RESOLVED 2026-07-23: the City of Holyoke's own Building Department inspects an EV charger circuit under its own codified Electrical Code (NEC 2017, §15.26.010), not the Colorado State Electrical Board (DORA) -- the prior unresolved city-vs-DORA hedge, and the DORA-fee-cap-multiplier analysis below that depended on it, are both superseded by this finding, though the underlying dollar figure is still not published (see next note).
  • Colorado's HB24-1173 requires expedited, standardized EV-charger permitting only in counties of 20,000+ and municipalities of 10,000+ population -- Holyoke does not meet that threshold, so this statutory mandate does not apply here.
  • Re-chased 2026-07-20: if the Colorado State Electrical Board (DORA) turns out to be the actual issuing authority (Phillips County is not on DORA's published list of counties with a local electrical-inspection program), state law (C.R.S. Title 12, electrical inspections article) caps local electrical fees at 1.15x the state's own fee schedule -- but the only version of that state fee schedule locatable (an archived table hosted by another Colorado municipality, not DORA itself) is dated 'New State of Colorado Fees as of April 1, 2016.' Since the governing statute requires the fee schedule be re-established annually, a 9-year-old third-party-hosted copy cannot be treated as the current governing figure, and DORA's own fee-schedule pages return HTTP 403 to automated fetches. NOTE (2026-07-23): this DORA-multiplier avenue is now understood to be moot for Holyoke specifically, since the City -- not DORA -- is the confirmed issuing authority (Municode §15.26.010); the 1.15x-state-schedule cap would only be relevant if DORA issued the permit.
  • RE-CHASE 2026-07-23 (dollar figure remains OPEN despite new avenues): the fee-setting MECHANISM is now confirmed via primary ordinance text -- Holyoke Municipal Code §17.44.050 states the fee 'shall be as set from time to time by action of the city council and set out in the [consolidated] fee schedule,' i.e. a standalone council resolution, not a codified table. That resolution document itself was NOT found published online after checking the live city_council.php and city_clerk.php pages (no agendas/minutes/resolutions posted), running a full Wayback Machine CDX index of the entire cityofholyoke-co.gov domain (562 archived URLs, filtered for fee/resolution/schedule/budget/council/minutes/agenda -- only an unrelated CORA 'Records Request Fees Schedule.pdf' turned up), and a fresh web search. No citable governing dollar figure for EV charger permits exists after this exhaustive chase; confidence stays partial pending direct confirmation from the Building Department (970-854-2266).

Frequently asked questions

Holyoke requires an ev charger / evse permit for: Completed City of Holyoke Building Permit Application, same general form used for other construction, describing the EV charger installation's scope, materials cost, and labor cost; RESOLVED 2026-07-23: electrical permit authority in Holyoke is City-issued, not State-issued -- Holyoke Municipal Code §15.26.010 codifies the City's OWN Electrical Code (NEC 2017), expressly providing for city issuance of permits and city collection of fees, corroborating the Forms & Documents page's listing of 'wiring' among city-administered permit types; the charger circuit is therefore inspected under the City's own code, not the Colorado State Electrical Board; Holyoke does not meet the 10,000-population municipality threshold that triggers Colorado HB24-1173's mandatory model-code/expedited-review requirement for EV charger permits, so that statute does not apply here; Same 180-day permit expiration clause applies as with any other Holyoke building permit. If your project isn't listed, confirm with City of Holyoke Building Department at 970-854-2266 before starting work.

Holyoke does not publish a plan-review timeline for this permit. Contact City of Holyoke Building Department at 970-854-2266 for current turnaround.

You'll need: City of Holyoke Building Permit Application. See the required-documents checklist on this page for details on each.

Holyoke requires 1 inspection(s) for an ev charger / evse permit, in order: Final Electrical. Schedule each through City of Holyoke Building Department (970-854-2266).

Apply through City of Holyoke Building Department at 407 E. Denver Street, Holyoke, CO 80734. Phone: 970-854-2266, email: contactus@cityofholyoke-co.gov. Office hours: City offices Monday-Friday 8:00 AM to 5:00 PM (closed weekends), per the City of Holyoke Forms & Documents page. No separate Building Department-specific hours or direct phone/email distinct from the main city line (970-854-2266 / contactus@cityofholyoke-co.gov) were found published anywhere on the city's site as of this review; the Building Department does not have its own dedicated staff-listing or contact page distinct from the city's general Forms & Documents / Business Office pages.. Official information: https://www.cityofholyoke-co.gov/departments/forms_documents.php.

Holyoke, Colorado has adopted: IMPORTANT SEED-URL CORRECTION: the seed URL provided for this research (https://www.holyoke.org/departments/building/) resolves to the City of Holyoke, MASSACHUSETTS Building Department (413-322-5600, City Hall Annex Room 300, buildcon@holyoke.org) — a completely different municipality. It does NOT describe Phillips County, Colorado's City of Holyoke in any way. The correct and verified official source for City of Holyoke, COLORADO is https://www.cityofholyoke-co.gov (confirmed via web search cross-referencing Phillips County, CO address 407 E. Denver Street, phone 970-854-2266, and Wikipedia/Census records for Holyoke, Colorado). All facts in this file are drawn exclusively from cityofholyoke-co.gov and its linked documents/PDFs, plus direct verification of Colorado statewide electrical/plumbing jurisdiction rules; none are drawn from the Massachusetts site.; RE-CHASE 2026-07-23 — GAP CLOSED: Municode's Holyoke, CO library (library.municode.com/co/holyoke), previously returning 401/403 to automated tools, loaded successfully via a live browser session on this pass. The Holyoke Municipal Code, Title 15 - BUILDINGS AND CONSTRUCTION, is codified as Supplement 2, 'Online content updated on December 13, 2024,' 'Codified through Ordinance No. 1-2024, enacted September 17, 2024.' Holyoke has adopted, by reference, as its own local code (each chapter states a certified copy is on file with the city clerk): International Building Code, 2018 edition, incl. appendices C/E/I/J (Sec. 15.04.010); International Residential Code, 2018 edition (Sec. 15.08.010); International Mechanical Code, 2018 edition, incl. appendix A (Sec. 15.12.010); International Fire Code, 2018 edition, incl. appendices B/C/D/I (Sec. 15.16.010); International Energy Conservation Code, 2018 edition (Sec. 15.20.010); International Existing Building Code, 2018 edition (Sec. 15.22.010); 'the most recent edition of the Colorado Plumbing Code as adopted by the state plumbing board' as the city's own Plumbing Code, no fixed year — floats to whatever edition the state plumbing board currently has in effect (Sec. 15.24.010); and the National Electrical Code, 2017 edition, 'as adopted by the state' (Sec. 15.26.010). Quoted directly from the live Municode page.; Local modifications on file (2026-07-23 re-chase): IBC 2018 Sec. 101.1 retitled 'Building Code of the City of Holyoke'; Sec. 103 deleted; Sec. 105.2 (Work Exempt from Permit) amended so 'fences not over six feet, three inches high' and 'retaining walls...not over four feet' are REMOVED from the exempt list (i.e., these now DO require a permit; see chapter 17.28 for fencing). IRC 2018 Sec. 101.1 retitled 'Residential Code of the City of Holyoke'; Sec. 104.10.1 (Flood Hazard Areas) deleted; Sec. 105.2 amended — exempt from permit: one-story detached accessory structures ≤120 sq ft; and 'decks not exceeding 120 square feet in area, that are not more than 18 inches above grade at any point, are not attached to a dwelling and do not serve the exit door required by section R311.4'; also exempt: like-for-like window/door replacement with no framing change; Sec. R313 (Automatic Fire Sprinkler Systems) deleted; Sec. N1102.4.1.2 (Testing) deleted. IMC 2018 Sec. 106.2 amended to exempt like-for-like category-one furnace/water-heater and A/C replacement (R-3 occupancies, prior install permitted/inspected/approved) from a new permit, and adds 'Sec. 106.5.2 Fee schedule. Fees for any permit, plan review or inspection required by this code shall be established from time to time by resolution of the city council' (confirms the fee-setting MECHANISM — a standalone council resolution, not a codified table — while the dollar figures themselves remain unpublished online; see the fee-schedule note below). IFC 2018 and IECC 2018 each retitled to the City of Holyoke's name in Sec. 101.1/C101.1 with no other substantive local modification noted.; HB22-1362 (Colorado's statewide low-energy/carbon code requirement) and its predecessor HB19-1260 both operate on a 'when a jurisdiction updates its building code, the energy code update must accompany it' trigger — neither is a blanket mandate independent of a local update, and neither contains a population-based exemption threshold. The 2026-07-23 re-chase confirms the IECC edition currently on Holyoke's books is 2018 (not a newer low-energy cycle), but it could NOT establish exactly when Title 15's ICC chapters were last substantively enacted/updated: none of the Sec. 15.04.010 through 15.26.010 adoption sections carry an inline '(Ord. No. ___, ____)' legislative-history citation in the Municode text (unlike, e.g., the Mobile Home chapter at Sec. 15.28.010, which cites 'Ord. No. 5-1975'), and the code's front-matter 'codified through Ordinance No. 1-2024' banner reflects the single most-recent ordinance affecting ANY part of the whole Municipal Code, not necessarily Title 15 specifically. Whether HB22-1362 currently binds Holyoke therefore remains genuinely unresolved after this chase — recorded as such, not assumed either way — though it is now pinned down that whatever cycle IS in force is the 2018 ICC family, a materially more precise fact than the prior 'no edition found' state.; RE-CHASE 2026-07-23 — GAP CLOSED (supersedes the DORA-vs-city ambiguity flagged in the prior 2026-07-06 pass): Holyoke Municipal Code Title 15 contains the City's OWN codified Electrical Code chapter (Sec. 15.26.010, adopting NEC 2017 'as adopted by the state,' expressly 'to provide for the issuance of permits and collection of fees therefor') and Plumbing Code chapter (Sec. 15.24.010, adopting by reference the state plumbing board's current Colorado Plumbing Code 'as the plumbing code of the CITY... providing for the issuance of permits and collection of fees therefor'). Both are codified as the City's own local ordinances under Title 15 - Buildings and Construction (footnoted to C.R.S. § 31-15-601 et seq., municipal building/fire-regulation power, and C.R.S. § 31-16-202, authority to adopt codes by reference) — not merely descriptive cross-references to a separate state process. This directly corroborates, on a live primary legal source, the City's own Forms & Documents page listing 'wiring' and 'plumbing' among its administered Building Department permit types, and as a home-rule municipality Holyoke has independent authority to run its own electrical/plumbing permitting program regardless of whether DORA's 'no state inspections in these counties' list includes Phillips County — that DORA list concerns default authority over UNINCORPORATED county land, not an incorporated home-rule city's own adopted code. Electrical and plumbing permits in Holyoke are therefore treated in this file as CITY-issued (City of Holyoke Building Department), under Secs. 15.26.010 and 15.24.010 respectively — not State of Colorado (DORA) issued. Remaining open, NOT resolved by the ordinance text: whether the City's own staff performs the physical inspections in-house or engages a state-certified/contract inspector — an operational detail the ordinance does not address.; Fee-schedule mechanism CONFIRMED via primary ordinance text (2026-07-23), even though the dollar figures remain unpublished online: IMC Sec. 106.5.2 ('Fees...shall be established from time to time by resolution of the city council'); Zoning Sec. 17.44.050, Building permit—Fee ('A fee for the examination and administration of a building permit shall be payable to the city upon receipt of the application. The fee shall be as set from time to time by action of the city council and set out in the fee schedule.'); and the Mobile Home Regulations chapter, which repeatedly references applicants paying 'a fee in an amount set out in the consolidated fee schedule' (Secs. 15.28.040, 15.28.090). All three confirm Holyoke fees are set by a standalone CITY COUNCIL RESOLUTION establishing a 'consolidated fee schedule' — a document that is NOT part of the codified ordinances Municode publishes and was not located published online after this re-chase: checked the live city_council.php and city_clerk.php pages (no agendas/minutes/resolutions posted), ran a fresh Wayback Machine CDX index of the entire cityofholyoke-co.gov domain (562 archived URLs, filtered for fee/resolution/schedule/budget/council/minutes/agenda — the only hit was an unrelated 'Records Request Fees Schedule.pdf,' a CORA records-request fee document, not a building-permit fee schedule), and a live web search for 'City of Holyoke Colorado fee schedule resolution building permit' (returned only the already-flagged wrong-jurisdiction holyoke.org Massachusetts site plus unrelated other-Colorado-jurisdiction fee schedules). The consolidated fee schedule is confirmed to exist as a real governing document by council resolution, but its actual dollar figures remain genuinely unrecoverable via public online sources as of this pass.. Local amendments apply — see the Holyoke overview page for the full list.

No. Holyoke has no dedicated EV/EVSE permit, fee schedule, or application -- an EV charger installation uses the same general Building Permit Application used for other construction, with the City calculating the fee manually at issuance. No published fee figure exists to cite.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Holyoke building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.