Required for re-roofing, re-siding, and soffit replacement work in Holyoke, using the city's own dedicated 2020 Re-siding/Re-roofing/Soffit Permit Application — a distinct standalone form from the general Building Permit Application, unlike many peer jurisdictions in this corpus that fold re-roofs into the general building-permit process.

Verified 2026-07-06 · Source

When you need this permit

  • Completed Re-siding/Re-roofing/Soffit Permit Application specifying roof type (shingles, shakes, built-up, metal, tile, other) and/or siding type (wood, vinyl, metal, soffit, brick, other)
  • Contractor license Class, Number, and Expiration date must be disclosed on the application Contractor
  • Number of layers must be disclosed if roofing material is being overlaid rather than fully torn off
  • Material Cost, Labor Cost, and Total Cost disclosed for permit fee and use tax calculation
  • Permit becomes null and void if work is not commenced within 180 days or is suspended/abandoned for 180 days after commencement

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Re-roof/Re-siding Permit FeeNo published fee schedule; the application's 'For Official Use Only' block (Permit Fee, Use Tax, Total) is completed by city staff at issuance rather than computed from a public rate table
Not published — contact the department
Use TaxSeparate line item on the official application form; no published rate
Not published — contact the department

Review timeline

Plan review
Not published — contact the department

How long did your Re-siding / Re-roofing / Soffit Permit permit actually take in Holyoke?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection (roof/siding)

    Completed re-roof or re-siding work verified against the permit application

See the full Holyoke inspection guide — scheduling & re-inspection fees →

Tips

  • Holyoke uses a dedicated Re-siding/Re-roofing/Soffit Permit Application distinct from its general Building Permit Application — use the correct form for this scope rather than the general building-permit form.
  • If overlaying rather than fully tearing off existing roofing, the application requires you to disclose the number of layers — confirm with the Building Department whether a maximum layer count applies before assuming an overlay is permitted.

Frequently asked questions

Holyoke requires a re-siding / re-roofing / soffit permit for: Completed Re-siding/Re-roofing/Soffit Permit Application specifying roof type (shingles, shakes, built-up, metal, tile, other) and/or siding type (wood, vinyl, metal, soffit, brick, other); Contractor license Class, Number, and Expiration date must be disclosed on the application; Number of layers must be disclosed if roofing material is being overlaid rather than fully torn off; Material Cost, Labor Cost, and Total Cost disclosed for permit fee and use tax calculation; Permit becomes null and void if work is not commenced within 180 days or is suspended/abandoned for 180 days after commencement. If your project isn't listed, confirm with City of Holyoke Building Department at 970-854-2266 before starting work.

Holyoke does not publish a plan-review timeline for this permit. Contact City of Holyoke Building Department at 970-854-2266 for current turnaround.

You'll need: City of Holyoke Re-siding/Re-roofing/Soffit Permit Application. See the required-documents checklist on this page for details on each.

Holyoke requires 1 inspection(s) for a re-siding / re-roofing / soffit permit, in order: Final Inspection (roof/siding). Schedule each through City of Holyoke Building Department (970-854-2266).

Apply through City of Holyoke Building Department at 407 E. Denver Street, Holyoke, CO 80734. Phone: 970-854-2266, email: contactus@cityofholyoke-co.gov. Office hours: City offices Monday-Friday 8:00 AM to 5:00 PM (closed weekends), per the City of Holyoke Forms & Documents page. No separate Building Department-specific hours or direct phone/email distinct from the main city line (970-854-2266 / contactus@cityofholyoke-co.gov) were found published anywhere on the city's site as of this review; the Building Department does not have its own dedicated staff-listing or contact page distinct from the city's general Forms & Documents / Business Office pages.. Official information: https://www.cityofholyoke-co.gov/departments/forms_documents.php.

Holyoke, Colorado has adopted: IMPORTANT SEED-URL CORRECTION: the seed URL provided for this research (https://www.holyoke.org/departments/building/) resolves to the City of Holyoke, MASSACHUSETTS Building Department (413-322-5600, City Hall Annex Room 300, buildcon@holyoke.org) — a completely different municipality. It does NOT describe Phillips County, Colorado's City of Holyoke in any way. The correct and verified official source for City of Holyoke, COLORADO is https://www.cityofholyoke-co.gov (confirmed via web search cross-referencing Phillips County, CO address 407 E. Denver Street, phone 970-854-2266, and Wikipedia/Census records for Holyoke, Colorado). All facts in this file are drawn exclusively from cityofholyoke-co.gov and its linked documents/PDFs, plus direct verification of Colorado statewide electrical/plumbing jurisdiction rules; none are drawn from the Massachusetts site.; RE-CHASE 2026-07-23 — GAP CLOSED: Municode's Holyoke, CO library (library.municode.com/co/holyoke), previously returning 401/403 to automated tools, loaded successfully via a live browser session on this pass. The Holyoke Municipal Code, Title 15 - BUILDINGS AND CONSTRUCTION, is codified as Supplement 2, 'Online content updated on December 13, 2024,' 'Codified through Ordinance No. 1-2024, enacted September 17, 2024.' Holyoke has adopted, by reference, as its own local code (each chapter states a certified copy is on file with the city clerk): International Building Code, 2018 edition, incl. appendices C/E/I/J (Sec. 15.04.010); International Residential Code, 2018 edition (Sec. 15.08.010); International Mechanical Code, 2018 edition, incl. appendix A (Sec. 15.12.010); International Fire Code, 2018 edition, incl. appendices B/C/D/I (Sec. 15.16.010); International Energy Conservation Code, 2018 edition (Sec. 15.20.010); International Existing Building Code, 2018 edition (Sec. 15.22.010); 'the most recent edition of the Colorado Plumbing Code as adopted by the state plumbing board' as the city's own Plumbing Code, no fixed year — floats to whatever edition the state plumbing board currently has in effect (Sec. 15.24.010); and the National Electrical Code, 2017 edition, 'as adopted by the state' (Sec. 15.26.010). Quoted directly from the live Municode page.; Local modifications on file (2026-07-23 re-chase): IBC 2018 Sec. 101.1 retitled 'Building Code of the City of Holyoke'; Sec. 103 deleted; Sec. 105.2 (Work Exempt from Permit) amended so 'fences not over six feet, three inches high' and 'retaining walls...not over four feet' are REMOVED from the exempt list (i.e., these now DO require a permit; see chapter 17.28 for fencing). IRC 2018 Sec. 101.1 retitled 'Residential Code of the City of Holyoke'; Sec. 104.10.1 (Flood Hazard Areas) deleted; Sec. 105.2 amended — exempt from permit: one-story detached accessory structures ≤120 sq ft; and 'decks not exceeding 120 square feet in area, that are not more than 18 inches above grade at any point, are not attached to a dwelling and do not serve the exit door required by section R311.4'; also exempt: like-for-like window/door replacement with no framing change; Sec. R313 (Automatic Fire Sprinkler Systems) deleted; Sec. N1102.4.1.2 (Testing) deleted. IMC 2018 Sec. 106.2 amended to exempt like-for-like category-one furnace/water-heater and A/C replacement (R-3 occupancies, prior install permitted/inspected/approved) from a new permit, and adds 'Sec. 106.5.2 Fee schedule. Fees for any permit, plan review or inspection required by this code shall be established from time to time by resolution of the city council' (confirms the fee-setting MECHANISM — a standalone council resolution, not a codified table — while the dollar figures themselves remain unpublished online; see the fee-schedule note below). IFC 2018 and IECC 2018 each retitled to the City of Holyoke's name in Sec. 101.1/C101.1 with no other substantive local modification noted.; HB22-1362 (Colorado's statewide low-energy/carbon code requirement) and its predecessor HB19-1260 both operate on a 'when a jurisdiction updates its building code, the energy code update must accompany it' trigger — neither is a blanket mandate independent of a local update, and neither contains a population-based exemption threshold. The 2026-07-23 re-chase confirms the IECC edition currently on Holyoke's books is 2018 (not a newer low-energy cycle), but it could NOT establish exactly when Title 15's ICC chapters were last substantively enacted/updated: none of the Sec. 15.04.010 through 15.26.010 adoption sections carry an inline '(Ord. No. ___, ____)' legislative-history citation in the Municode text (unlike, e.g., the Mobile Home chapter at Sec. 15.28.010, which cites 'Ord. No. 5-1975'), and the code's front-matter 'codified through Ordinance No. 1-2024' banner reflects the single most-recent ordinance affecting ANY part of the whole Municipal Code, not necessarily Title 15 specifically. Whether HB22-1362 currently binds Holyoke therefore remains genuinely unresolved after this chase — recorded as such, not assumed either way — though it is now pinned down that whatever cycle IS in force is the 2018 ICC family, a materially more precise fact than the prior 'no edition found' state.; RE-CHASE 2026-07-23 — GAP CLOSED (supersedes the DORA-vs-city ambiguity flagged in the prior 2026-07-06 pass): Holyoke Municipal Code Title 15 contains the City's OWN codified Electrical Code chapter (Sec. 15.26.010, adopting NEC 2017 'as adopted by the state,' expressly 'to provide for the issuance of permits and collection of fees therefor') and Plumbing Code chapter (Sec. 15.24.010, adopting by reference the state plumbing board's current Colorado Plumbing Code 'as the plumbing code of the CITY... providing for the issuance of permits and collection of fees therefor'). Both are codified as the City's own local ordinances under Title 15 - Buildings and Construction (footnoted to C.R.S. § 31-15-601 et seq., municipal building/fire-regulation power, and C.R.S. § 31-16-202, authority to adopt codes by reference) — not merely descriptive cross-references to a separate state process. This directly corroborates, on a live primary legal source, the City's own Forms & Documents page listing 'wiring' and 'plumbing' among its administered Building Department permit types, and as a home-rule municipality Holyoke has independent authority to run its own electrical/plumbing permitting program regardless of whether DORA's 'no state inspections in these counties' list includes Phillips County — that DORA list concerns default authority over UNINCORPORATED county land, not an incorporated home-rule city's own adopted code. Electrical and plumbing permits in Holyoke are therefore treated in this file as CITY-issued (City of Holyoke Building Department), under Secs. 15.26.010 and 15.24.010 respectively — not State of Colorado (DORA) issued. Remaining open, NOT resolved by the ordinance text: whether the City's own staff performs the physical inspections in-house or engages a state-certified/contract inspector — an operational detail the ordinance does not address.; Fee-schedule mechanism CONFIRMED via primary ordinance text (2026-07-23), even though the dollar figures remain unpublished online: IMC Sec. 106.5.2 ('Fees...shall be established from time to time by resolution of the city council'); Zoning Sec. 17.44.050, Building permit—Fee ('A fee for the examination and administration of a building permit shall be payable to the city upon receipt of the application. The fee shall be as set from time to time by action of the city council and set out in the fee schedule.'); and the Mobile Home Regulations chapter, which repeatedly references applicants paying 'a fee in an amount set out in the consolidated fee schedule' (Secs. 15.28.040, 15.28.090). All three confirm Holyoke fees are set by a standalone CITY COUNCIL RESOLUTION establishing a 'consolidated fee schedule' — a document that is NOT part of the codified ordinances Municode publishes and was not located published online after this re-chase: checked the live city_council.php and city_clerk.php pages (no agendas/minutes/resolutions posted), ran a fresh Wayback Machine CDX index of the entire cityofholyoke-co.gov domain (562 archived URLs, filtered for fee/resolution/schedule/budget/council/minutes/agenda — the only hit was an unrelated 'Records Request Fees Schedule.pdf,' a CORA records-request fee document, not a building-permit fee schedule), and a live web search for 'City of Holyoke Colorado fee schedule resolution building permit' (returned only the already-flagged wrong-jurisdiction holyoke.org Massachusetts site plus unrelated other-Colorado-jurisdiction fee schedules). The consolidated fee schedule is confirmed to exist as a real governing document by council resolution, but its actual dollar figures remain genuinely unrecoverable via public online sources as of this pass.. Local amendments apply — see the Holyoke overview page for the full list.

Yes. The City of Holyoke publishes a dedicated Re-siding/Re-roofing/Soffit Permit Application (2020 version), separate from its general Building Permit Application.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Holyoke building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.