Commercial Building Permit in Holyoke, Colorado

Required for new commercial construction, commercial additions, alterations, repairs, moves, and demolitions within Holyoke city limits. Holyoke has NO separate commercial permit application, commercial submittal checklist, or commercial fee track: commercial work uses the exact same general Building Permit Application as residential work, distinguished only by checking 'Commercial' in the form's 'Type of Work: Residential ___ Commercial ___' field, per the application PDF itself. The Forms & Documents page lists only these Building Department applications — Building Permit Application (General), Excavation Permit (2 pages), Fence Permit, and Re-siding/Re-roof/Soffit — plus 12 guides, all residential-scoped (addition, basement, garage, patio, roof, decks); nothing commercial-specific is posted. Plan review is against the International Building Code, 2018 edition, adopted by reference as the city's own code (Holyoke Municipal Code §15.04.010), with IEBC 2018 (§15.22.010) and IFC 2018 (§15.16.010) also on the books for existing-building and fire-code scopes.

Reviewed 2026-08-02 · Source

When you need this permit

  • Completed City of Holyoke Building Permit Application (General) — the same form used for residential work — with 'Commercial' checked under Type of Work and the appropriate Class of Work marked (New / Addition / Alteration / Repair / Move / Demo); verified from the live application PDF 2026-08-02
  • 'Use of Building' field completed, and 'Change of Use From' / 'Change of Use To' fields completed if the project changes the building's use (these fields exist on the standard form and are the only occupancy-change mechanism published)
  • Building dimensions (W x L, total square feet), number of stories, Plans Available (Yes/No), and Flood Plain Area (Yes/No) disclosed on the application
  • Material Cost, Labor Cost, and Total Cost disclosed for staff calculation of the permit fee and municipal use tax at issuance
  • Separate electrical, plumbing, and mechanical/HVAC permits are ALWAYS required for commercial work: the application's notice text exempts only construction 'for a new residence' (page 1 wording: 'a new home') from standalone trade permits, so no commercial project of any class qualifies for the umbrella exception (verified from the live application PDF 2026-08-02)
  • Permit becomes null and void if work is not commenced within 180 days of issuance, or if work is suspended or abandoned for 180 days at any time after commencement (notice text on the application)
  • Governing code: IBC 2018 as locally modified — §101.1 retitled 'Building Code of the City of Holyoke,' §103 deleted, §105.2 amended so fences over 6'3" and retaining walls over 4' require a permit (Holyoke Municipal Code §§15.04.010/15.04.020); IFC 2018 (§15.16.010, incl. appendices B/C/D/I) and IECC 2018 (§15.20.010) also apply

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Commercial Building Permit Fee
The City of Holyoke publishes no fee schedule — commercial or otherwise — anywhere on its website or in any downloadable application. Show full citationThe City of Holyoke publishes no fee schedule — commercial or otherwise — anywhere on its website or in any downloadable application. Per Holyoke Municipal Code §17.44.050, fees are set by standalone city council resolution ('consolidated fee schedule'), not a codified table, and that resolution is not published online. The city's Forms & Documents page carries eight document categories (Council Meeting Agenda and Minutes, Housing Authority Application, Water Department Annual Reports, City of Holyoke Employment, City Office, Building Department Guides, Building Department Applications, Volunteer Fireman Application, Police Department Documents and Forms) — no Budget, Resolutions, or Fee Schedule category exists, and only the five most recent Council agendas/minutes are kept online at a time, with no archive. There is no evidence Holyoke contracts building or plan-review services to a third party (SAFEbuilt, Colorado Code Consulting, or similar, as is common for small Colorado towns), and the regional council of governments (Northeast Colorado Association of Local Governments, serving Phillips County) provides aging and case-management services only, not building inspection. One concrete primary-source data point exists: the City Council's May 19, 2026 meeting minutes record that City Clerk Brown presented a permit fee waiver request from the Heginbotham Library for a porch project, and Council voted to approve 'the building permit fee waiver request from the Library in the amount of $942.50' — a real, staff-calculated, non-residential building-permit fee the City actually assessed in practice (then separately voted to waive for this applicant). The minutes do not state the underlying construction cost that produced the $942.50 figure, so it cannot be generalized into a rate schedule. Confirm the current fee directly with the Building Department (970-854-2266).
Not published — contact the department
Use TaxMunicipal use tax applies to permitted construction and is calculated by city staff at issuance from the Material/Labor/Total Cost figures disclosed on the application; no rate or formula is published.
Not published — contact the department

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Holyoke?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Prior to concrete pour; no commercial-specific inspection checklist is published by the city — sequence below is the standard IBC-based progression, to be confirmed with the Building Department at permit issuance

  2. 2

    Framing / Rough-in

    Structural framing and trade rough-ins (under separately issued electrical/plumbing/mechanical permits) before concealment

  3. 3

    Final Inspection

    Completed work verified against the approved application before occupancy/use

See the full Holyoke inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate commercial application, checklist, plan-review track, or fee schedule in Holyoke — commercial projects check the 'Commercial' box on the same general Building Permit Application residential projects use. Everything scope-specific (plan-set count, stamped-drawing requirements, review expectations) is handled by conversation with the Building Department (970-854-2266), not published documents.
  • Unlike a new house, commercial work NEVER qualifies for the umbrella trade-permit exception: the application's notice text exempts only 'a new residence' from separate electrical/plumbing/HVAC permits, so budget for standalone trade permits on every commercial job, including new commercial buildings.
  • The 'Change of Use From/To' fields on the general application are the city's only published mechanism for occupancy/use changes — if your project converts a space to a different use, complete these fields and expect review against IBC 2018 and IEBC 2018 (both adopted, Holyoke Municipal Code §§15.04.010/15.22.010).
  • Do not trust search results from holyoke.org (including its published commercial fee tables) — that is Holyoke, MASSACHUSETTS. The only official source for this jurisdiction is cityofholyoke-co.gov.
  • REAL-WORLD FEE ANCHOR (found 2026-08-02): while no fee schedule is published, the City Council's May 19, 2026 minutes document an actual $942.50 building permit fee the City calculated for a porch project at the Heginbotham Library (a non-residential structure), which Council then voted to waive for that applicant. Treat this as a rough real-world data point on the scale of Holyoke's staff-calculated fees for a modest non-residential scope — not a rate table, and not necessarily representative of a full new commercial building's fee — but it is the only actual dollar figure for a non-residential Holyoke permit located in the research to date.

Frequently asked questions

Holyoke requires a commercial building permit for: Completed City of Holyoke Building Permit Application (General) — the same form used for residential work — with 'Commercial' checked under Type of Work and the appropriate Class of Work marked (New / Addition / Alteration / Repair / Move / Demo); verified from the live application PDF 2026-08-02; 'Use of Building' field completed, and 'Change of Use From' / 'Change of Use To' fields completed if the project changes the building's use (these fields exist on the standard form and are the only occupancy-change mechanism published); Building dimensions (W x L, total square feet), number of stories, Plans Available (Yes/No), and Flood Plain Area (Yes/No) disclosed on the application; Material Cost, Labor Cost, and Total Cost disclosed for staff calculation of the permit fee and municipal use tax at issuance; Separate electrical, plumbing, and mechanical/HVAC permits are ALWAYS required for commercial work: the application's notice text exempts only construction 'for a new residence' (page 1 wording: 'a new home') from standalone trade permits, so no commercial project of any class qualifies for the umbrella exception (verified from the live application PDF 2026-08-02); Permit becomes null and void if work is not commenced within 180 days of issuance, or if work is suspended or abandoned for 180 days at any time after commencement (notice text on the application); Governing code: IBC 2018 as locally modified — §101.1 retitled 'Building Code of the City of Holyoke,' §103 deleted, §105.2 amended so fences over 6'3" and retaining walls over 4' require a permit (Holyoke Municipal Code §§15.04.010/15.04.020); IFC 2018 (§15.16.010, incl. appendices B/C/D/I) and IECC 2018 (§15.20.010) also apply. If your project isn't listed, confirm with City of Holyoke Building Department at 970-854-2266 before starting work.

Holyoke does not publish a plan-review timeline for this permit. Contact City of Holyoke Building Department at 970-854-2266 for current turnaround.

You'll need: City of Holyoke Building Permit Application (General); Construction plans. See the required-documents checklist on this page for details on each.

Holyoke requires 3 inspection(s) for a commercial building permit, in order: Foundation, Framing / Rough-in, Final Inspection. Schedule each through City of Holyoke Building Department (970-854-2266).

Apply through City of Holyoke Building Department at 407 E. Denver Street, Holyoke, CO 80734. Phone: 970-854-2266, email: contactus@cityofholyoke-co.gov. Office hours: City offices Monday-Friday 8:00 AM to 5:00 PM (closed weekends), per the City of Holyoke Forms & Documents page. No separate Building Department-specific hours or direct phone/email distinct from the main city line (970-854-2266 / contactus@cityofholyoke-co.gov) were found published anywhere on the city's site as of the last verification; the Building Department does not have its own dedicated staff-listing or contact page distinct from the city's general Forms & Documents / Business Office pages.. Official information: https://www.cityofholyoke-co.gov/departments/forms_documents.php.

Holyoke, Colorado has adopted: Watch for a same-name collision when searching: https://www.holyoke.org/departments/building/ is the City of Holyoke, MASSACHUSETTS Building Department (413-322-5600, City Hall Annex Room 300, buildcon@holyoke.org), a completely different municipality. The City of Holyoke, COLORADO -- Phillips County, 407 E. Denver Street, 970-854-2266 -- publishes at https://www.cityofholyoke-co.gov. Everything in this record comes from cityofholyoke-co.gov and its linked documents, plus Colorado statewide electrical and plumbing jurisdiction rules; nothing comes from the Massachusetts site.; The Holyoke Municipal Code is published on Municode (library.municode.com/co/holyoke). Title 15 - BUILDINGS AND CONSTRUCTION is codified as Supplement 2, 'Online content updated on December 13, 2024,' 'Codified through Ordinance No. 1-2024, enacted September 17, 2024.' Holyoke has adopted, by reference, as its own local code (each chapter states a certified copy is on file with the city clerk): International Building Code, 2018 edition, incl. appendices C/E/I/J (Sec. 15.04.010); International Residential Code, 2018 edition (Sec. 15.08.010); International Mechanical Code, 2018 edition, incl. appendix A (Sec. 15.12.010); International Fire Code, 2018 edition, incl. appendices B/C/D/I (Sec. 15.16.010); International Energy Conservation Code, 2018 edition (Sec. 15.20.010); International Existing Building Code, 2018 edition (Sec. 15.22.010); 'the most recent edition of the Colorado Plumbing Code as adopted by the state plumbing board' as the city's own Plumbing Code, no fixed year — it floats to whatever edition the state plumbing board currently has in effect (Sec. 15.24.010); and the National Electrical Code, 2017 edition, 'as adopted by the state' (Sec. 15.26.010). Quoted directly from the Municode text.; Local modifications on file: IBC 2018 Sec. 101.1 retitled 'Building Code of the City of Holyoke'; Sec. 103 deleted; Sec. 105.2 (Work Exempt from Permit) amended so 'fences not over six feet, three inches high' and 'retaining walls...not over four feet' are REMOVED from the exempt list (i.e., these now DO require a permit; see chapter 17.28 for fencing). IRC 2018 Sec. 101.1 retitled 'Residential Code of the City of Holyoke'; Sec. 104.10.1 (Flood Hazard Areas) deleted; Sec. 105.2 amended — exempt from permit: one-story detached accessory structures ≤120 sq ft; and 'decks not exceeding 120 square feet in area, that are not more than 18 inches above grade at any point, are not attached to a dwelling and do not serve the exit door required by section R311.4'; also exempt: like-for-like window/door replacement with no framing change; Sec. R313 (Automatic Fire Sprinkler Systems) deleted; Sec. N1102.4.1.2 (Testing) deleted. IMC 2018 Sec. 106.2 amended to exempt like-for-like category-one furnace/water-heater and A/C replacement (R-3 occupancies, prior install permitted/inspected/approved) from a new permit, and adds 'Sec. 106.5.2 Fee schedule. Fees for any permit, plan review or inspection required by this code shall be established from time to time by resolution of the city council' (confirms the fee-setting mechanism — a standalone council resolution, not a codified table — while the dollar figures themselves remain unpublished online; see the fee-schedule note below). IFC 2018 and IECC 2018 each retitled to the City of Holyoke's name in Sec. 101.1/C101.1 with no other substantive local modification noted.; HB22-1362 (Colorado's statewide low-energy/carbon code requirement) and its predecessor HB19-1260 both operate on a 'when a jurisdiction updates its building code, the energy code update must accompany it' trigger — neither is a blanket mandate independent of a local update, and neither contains a population-based exemption threshold. The IECC edition currently on Holyoke's books is 2018 (not a newer low-energy cycle), but exactly when Title 15's ICC chapters were last substantively enacted or updated cannot be established from the published code: none of the Sec. 15.04.010 through 15.26.010 adoption sections carries an inline '(Ord. No. ___, ____)' legislative-history citation in the Municode text (unlike, e.g., the Mobile Home chapter at Sec. 15.28.010, which cites 'Ord. No. 5-1975'), and the code's front-matter 'codified through Ordinance No. 1-2024' banner reflects the single most-recent ordinance affecting ANY part of the whole Municipal Code, not necessarily Title 15 specifically. Whether HB22-1362 currently binds Holyoke therefore remains genuinely unresolved — recorded as such, not assumed either way — though whatever cycle IS in force is the 2018 ICC family.; Holyoke Municipal Code Title 15 contains the City's OWN codified Electrical Code chapter (Sec. 15.26.010, adopting NEC 2017 'as adopted by the state,' expressly 'to provide for the issuance of permits and collection of fees therefor') and Plumbing Code chapter (Sec. 15.24.010, adopting by reference the state plumbing board's current Colorado Plumbing Code 'as the plumbing code of the CITY... providing for the issuance of permits and collection of fees therefor'). Both are codified as the City's own local ordinances under Title 15 - Buildings and Construction (footnoted to C.R.S. § 31-15-601 et seq., municipal building/fire-regulation power, and C.R.S. § 31-16-202, authority to adopt codes by reference) — not merely descriptive cross-references to a separate state process. This corroborates, on a primary legal source, the City's own Forms & Documents page listing 'wiring' and 'plumbing' among its administered Building Department permit types, and as a home-rule municipality Holyoke has independent authority to run its own electrical/plumbing permitting program regardless of whether DORA's 'no state inspections in these counties' list includes Phillips County — that DORA list concerns default authority over unincorporated county land, not an incorporated home-rule city's own adopted code. Electrical and plumbing permits in Holyoke are therefore City-issued (City of Holyoke Building Department), under Secs. 15.26.010 and 15.24.010 respectively — not State of Colorado (DORA) issued. The ordinance text does not address whether the City's own staff performs the physical inspections in-house or engages a state-certified/contract inspector — that operational detail remains unconfirmed.; The fee-setting mechanism is confirmed by primary ordinance text even though the dollar figures are unpublished online: IMC Sec. 106.5.2 ('Fees...shall be established from time to time by resolution of the city council'); Zoning Sec. 17.44.050, Building permit—Fee ('A fee for the examination and administration of a building permit shall be payable to the city upon receipt of the application. The fee shall be as set from time to time by action of the city council and set out in the fee schedule.'); and the Mobile Home Regulations chapter, which repeatedly references applicants paying 'a fee in an amount set out in the consolidated fee schedule' (Secs. 15.28.040, 15.28.090). All three confirm Holyoke fees are set by a standalone CITY COUNCIL RESOLUTION establishing a 'consolidated fee schedule' — a document that is NOT part of the codified ordinances Municode publishes and is not located anywhere online: the city's city_council.php and city_clerk.php pages post no agendas, minutes or resolutions; the only fee document on the cityofholyoke-co.gov domain is an unrelated 'Records Request Fees Schedule.pdf' (a CORA records-request fee document, not a building-permit fee schedule); and a web search for 'City of Holyoke Colorado fee schedule resolution building permit' returns only the wrong-jurisdiction holyoke.org Massachusetts site plus unrelated other-Colorado-jurisdiction fee schedules. The consolidated fee schedule exists as a real governing document adopted by council resolution, but its actual dollar figures are not recoverable from public online sources.. Local amendments apply — see the Holyoke overview page for the full list.

No. Commercial construction uses the same general Building Permit Application as residential work — the form has a 'Type of Work: Residential / Commercial' checkbox (verified from the live application PDF, 2026-08-02). The city publishes no commercial-specific application, submittal checklist, fee schedule, or review-timeline commitment. Review is against the IBC 2018 as adopted by Holyoke Municipal Code §15.04.010.

No — Holyoke publishes no tenant improvement, tenant finish, or commercial remodel permit type, form, fee line, or process anywhere on its website or in its Forms & Documents center. A TI project is simply a commercial building permit: check 'Commercial' under Type of Work and 'Alteration' (or 'Repair') under Class of Work on the general Building Permit Application, complete the 'Change of Use From/To' fields if the tenancy changes the use, and pull standalone electrical/plumbing/mechanical permits for any trade work (the new-residence umbrella exception never applies to commercial scopes).

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Holyoke.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Property Access

Holyoke's permit history is searchable by address

1,605 permits in our copy of Holyoke's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything Holyoke has issued.

1,526 of these 1,607 permits — 95% — carry an issued date, and those run from 2015 to 2026. The remaining 81 have no date at all.

96% of Holyoke's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.