Required for construction of decks, covered patios, garages, and storage sheds in the Town of Center, billed under the same fee line by the Town's own Fee Schedule document.

Verified 2026-07-06 · Source

When you need this permit

  • Filed on the combined Building Permit Application, 'Deck or Patio' or 'Shed' checkbox under Project Information/Type
  • Sketch plan required per standard attachment requirements, including setback dimensions

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Garage, Storage Shed, Deck or Patio FeeTown of Center Building Permit Application / Fee Schedule document
$0.10 per sq. ft. of floor space or area to be constructed, $50.00 minimum
Application Fee
$50.00 flat, non-refundable

Review timeline

Plan reviewCenter’s published plan-review target
1–2 business days

How long did your Deck / Patio Permit permit actually take in Center?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

See the full Center inspection guide — scheduling & re-inspection fees →

Tips

  • Decks, patios, garages, and storage sheds all share the same $0.10/sq ft (min $50) fee line in Center's Fee Schedule — a simpler flat structure than jurisdictions with separate accessory-structure fee tables.

Frequently asked questions

Center requires a deck / patio permit for: Filed on the combined Building Permit Application, 'Deck or Patio' or 'Shed' checkbox under Project Information/Type; Sketch plan required per standard attachment requirements, including setback dimensions. If your project isn't listed, confirm with Town of Center Public Works Department at (719) 754-3497 before starting work.

In Center, the published Garage, Storage Shed, Deck or Patio Fee is: $0.10 per sq. ft. of floor space or area to be constructed, $50.00 minimum. Additional published fees: Application Fee — $50.00 flat, non-refundable. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Center's published plan-review target for a deck / patio permit is 1–2 business days.

You'll need: Building Permit Application (combined form); Sketch Plan. See the required-documents checklist on this page for details on each.

Center requires 1 inspection(s) for a deck / patio permit, in order: Final Inspection. Schedule each through Town of Center Public Works Department ((719) 754-3497).

Apply through Town of Center Public Works Department at 294 S. Worth Street, Center, CO 81125. Phone: (719) 754-3497, email: cwebb@centerco.gov. Office hours: Monday-Thursday 7:00 AM - 5:00 PM; Friday 8:00 AM - 1:00 PM; Saturday-Sunday Closed. Fax (719) 754-3379.. Official information: https://www.centerco.gov/documents.

Center, Colorado has adopted: 2018 International Building Code (IBC) and International Residential Code (IRC) — per the Town of Center's own Building Permit Application / Fee Schedule document ('CURRENT (2018 Codes)', referencing https://codes.iccsafe.org/codes/colorado); 2018 International Plumbing Code (IPC); 2018 International Mechanical Code (IMC); 2018 International Fire Code (IFC); 2018 International Energy Conservation Code (IECC) (listed on the Town's document as 'International Energy Commission Code'); 2018 International Fuel Gas Code (IFGC); ICC/ANSI A117.1 Accessibility Code (ADA); ASME Boiler and Pressure Vessel Code; Note on currency: the Town's Building Permit Application/Fee Schedule packet (the only currently-published code-adoption source found) explicitly labels these as the '2018 Codes' with no revision date visible on the document itself. No newer code-adoption ordinance, resolution, or updated fee-schedule packet was found anywhere on the Town's current website (centerco.gov) or its Documents/Building Department listing as of this review (2026-07-06). The prior townofcenter.colorado.gov CivicPlus-style site (which hosted the original seed URL, .../departments/public-works-department/building-department, and an alternate .../departments/building-department path) now 301-redirects at the domain root to www.centerco.gov — the entire old site has been retired and its content was not recoverable via Wayback Machine chase within this review; the Town's own current-generation site (a minimal TownCloud/SvelteKit site launched circa 2025-2026) is treated as authoritative and does not itself carry a separate 'Adopted Codes' page distinct from the Building Permit Application document.. Local amendments apply — see the Center overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Center building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.