Center building permits
Department contacts, adopted codes, permit types, fees, and gotchas for Center, Colorado.
Last verified 2026-07-06 · Source · Embed this page’s badge · Version history
Building department
- Address
- 294 S. Worth Street, Center, CO 81125
- Phone
- (719) 754-3497
- cwebb@centerco.gov
- Office hours
- Monday-Thursday 7:00 AM - 5:00 PM; Friday 8:00 AM - 1:00 PM; Saturday-Sunday Closed. Fax (719) 754-3379.
- Website
- Official site
Inspection guide
See how inspections work in Center — sequence, scheduling & re-inspection fees.
Codes adopted
Colorado has no statewide-mandated building code edition. Under the Colorado Constitution's home-rule provisions (art. XX, home rule for municipalities since 1902; home rule for counties since 1970), building codes and zoning are an enumerated home-rule charter power, so cities and counties adopt and amend their own construction codes independently — predominantly the I-Codes, with editions and local amendments varying by jurisdiction. The one statewide floor is for energy: HB22-1362 (2022) created the Energy Code Board (jointly appointed by the Colorado Energy Office and the Department of Local Affairs) and requires that, on or after July 1, 2023 and before July 1, 2026, any municipality or county that adopts or updates a building code must adopt and enforce an energy code achieving performance equivalent to or better than the 2021 IECC together with the board's Model Electric Ready and Solar Ready Code (which includes electric-ready, EV-ready, and solar-ready provisions); from July 1, 2026 onward the floor shifts to the board's Model Low Energy and Carbon Code or an equivalent. Electrical and plumbing permitting defaults to the Colorado State Electrical Board and State Plumbing Board (within DORA's Division of Professions and Occupations) — the state issues permits and inspects statewide except in counties/jurisdictions that operate their own certified Electrical or Plumbing Inspection Program, in which case the local program has authority instead. Always confirm the currently adopted code edition, local amendments, and inspection authority (state board vs. local program) with the specific jurisdiction before submitting plans.
- 2018 International Building Code (IBC) and International Residential Code (IRC) — per the Town of Center's own Building Permit Application / Fee Schedule document ('CURRENT (2018 Codes)', referencing https://codes.iccsafe.org/codes/colorado)
- 2018 International Plumbing Code (IPC)
- 2018 International Mechanical Code (IMC)
- 2018 International Fire Code (IFC)
- 2018 International Energy Conservation Code (IECC) (listed on the Town's document as 'International Energy Commission Code')
- 2018 International Fuel Gas Code (IFGC)
- ICC/ANSI A117.1 Accessibility Code (ADA)
- ASME Boiler and Pressure Vessel Code
Note on currency: the Town's Building Permit Application/Fee Schedule packet (the only currently-published code-adoption source) explicitly labels these as the '2018 Codes' with no revision date visible on the document itself. Show full textShow less
Note on currency: the Town's Building Permit Application/Fee Schedule packet (the only currently-published code-adoption source) explicitly labels these as the '2018 Codes' with no revision date visible on the document itself. No newer code-adoption ordinance, resolution, or updated fee-schedule packet appears anywhere on the Town's current website (centerco.gov) or its Documents/Building Department listing. The prior townofcenter.colorado.gov CivicPlus-style site (which hosted the original.../departments/public-works-department/building-department page and an alternate.../departments/building-department path) now 301-redirects at the domain root to www.centerco.gov — the entire old site has been retired and its content is not archived. The Town's current-generation site (a minimal TownCloud/SvelteKit site launched circa 2025-2026) is authoritative and does not itself carry a separate 'Adopted Codes' page distinct from the Building Permit Application document.
Permit types & fees
Residential Building Permit (New Construction)
Required for new residential construction in the Town of Center, issued by the Public Works Department on the Town's combined Building Permit Application. Reviewed under the 2018 IBC/IRC as adopted per the Town's own Fee Schedule document.
From$0.10Residential Addition / Remodeling Permit
Required for additions and remodeling of existing residential structures, issued on the same combined Building Permit Application as new construction, under the 2018 IRC as adopted.
From$0.10Electrical Permit
Electrical work in the Town of Center is permitted and inspected directly by the State of Colorado, Division of Professions and Occupations (DORA/DPO) Electrical Board — NOT by the Town. The Town of Center runs no local certified electrical inspection program; its own Building Permit Application/Fee Schedule document directs applicants to the state program.
See fee schedulePlumbing Permit
Plumbing work in the Town of Center is permitted and inspected directly by the State of Colorado, Division of Professions and Occupations (DORA/DPO) Plumbing Board — NOT by the Town. The Town of Center runs no local certified plumbing inspection program; its own Building Permit Application/Fee Schedule document directs applicants to the state program.
See fee scheduleMechanical / HVAC Permit
Required for mechanical/HVAC installation or replacement work in the Town of Center, issued on the Town's combined Building Permit Application under the 2018 IMC and 2018 IFGC as adopted. Unlike electrical and plumbing, mechanical work is NOT carved out of Ordinance 339's Town contractor-license definition, and is not routed to a State board by the Town's own Fee Schedule document.
From$0.10Re-Roofing Permit
Required for re-roofing work in the Town of Center; billed as a flat fee distinct from the Town's general square-footage-based schedule, per the Town's own Fee Schedule document.
From$50.00Rooftop Solar PV Permit
The Town of Center's own Building Permit Application/Fee Schedule document and its 'Other Inspections and Fees' section do not name or price a distinct solar/photovoltaic permit category, and no rooftop solar program appears on the Town's current website, its Documents page, or any of the Building Department PDFs.
From$0.10Accessory Dwelling Unit (ADU) Permit
The Town of Center has a genuine, detailed ADU zoning-approval program under Municipal Code Section 44-73 and 44-73.1, administered via a dedicated ADU Application form. ADUs in Residential (R) or PUDR zone districts meeting all objective standards qualify for administrative approval (no public hearing); ADUs in Commercial Business (CB) or Commercial Highway (CH) districts require an additional Commercial ADU addendum and Special Review by the Planning Commission or Town Board. ADU zoning approval is a prerequisite to, but distinct from, the separate building permit required to actually construct the unit.
Fee not publishedDemolition Permit
Required for demolition of structures in the Town of Center, using a dedicated Demolition Application form (revised 7/01/2024) distinct from the general Building Permit Application.
$50.00Commercial Building Permit (New Construction / Remodeling)
Required for commercial new construction or remodeling in the Town of Center, filed on the same combined Building Permit Application as residential work but billed under the Town's commercial fee rate.
From$0.20Deck / Patio Permit
Required for construction of decks, covered patios, garages, and storage sheds in the Town of Center, billed under the same fee line by the Town's own Fee Schedule document.
From$0.10EV Charger / EVSE Permit
Center has no separate EV-charger permit. Installing charging equipment — for example a dedicated 240V Level 2 circuit — is electrical work, and all electrical work in Center is permitted and inspected by the State of Colorado Division of Professions and Occupations (DORA/DPO) Electrical Board. The Town runs no local certified electrical inspection program, and its own Building Permit Application/Fee Schedule directs applicants to the state program for any electrical scope, including an EV charger circuit. Under the state electrical fee schedule (set by CRS 12-23-117(3), effective statewide April 1, 2016), an EV charger circuit outside living area is priced under Chart B, Commercial and Other Installations, on the total contract cost of labor and materials: $100 base for a contract cost up to $2,000, plus $10 for each additional $1,000, rounded up. Colorado's HB24-1173 (Electric Vehicle Charging System Permits Act, effective August 7, 2024) sets a December 31, 2025 deadline for standardized EV-charging land-use permitting, but only for municipalities of 10,000 or more. Center's population was 1,929 at the 2020 Census, so the Town is not required to adopt a separate EV-charging land-use process.
From$100Sign Permit
The Town of Center's Zoning Code (Chapter 44 of the Town's Code of Ordinances, codified through Ordinance No. 571, enacted April 23, 2024, republished May 5, 2025) defines the term 'Sign' and two subtypes ('Sign, Advertising' and 'Sign, Animated') in its Article 44-XI Definitions (Sec. 44-221) — but across all eleven articles of Chapter 44 there is no dedicated Sign Regulations article, no dimensional, height or illumination standard, and no standalone sign-permit fee, and Chapter 10 (Buildings and Building Regulations, including the Town's adopted International Building Code) contains no sign-specific provision either. A sign is still captured by the general Building Permit requirement: it meets the Zoning Code's own definition of 'Structure' (Sec. 44-221: 'Anything constructed, the use of which requires permanent location on the ground or attachment to something having a permanent location on the ground'), and Sec. 44-211(a) requires a Building Permit application for the erection of any 'structure'. It is simply not its own permit type or fee line anywhere in the Town's Building Permit Application and Fee Schedule document, which lists only New Construction, Addition(s), Mobile Home, Fence-New/Replace, Deck or Patio, Reroof, Shed, Siding or Stucco, New Water/Gas/Sewer Tap, and an open 'Other' line, with no 'Sign' checkbox. Note that the Town's code on centerco.gov and the vanity center.municipalcodeonline.com domain both return an unrendered shell to simple tools and misroute to an unrelated default state page — open library.municode.com/co/center in an ordinary web browser to read the chapter text.
From$0.10Fire Sprinkler and Fire Alarm System Permit
The Town of Center has adopted a fire code: Chapter 20 (Fire Prevention and Protection) of the Town's Code of Ordinances, Sec. 20-40, adopts the International Fire Code, 2006 Edition (including Appendices A-D) by reference (Ord. No. 415, § 3, enacted 9-6-2011). That directly contradicts the Town's own Building Permit Application/Fee Schedule PDF, which lists '2018 International Fire Code (IFC)' among its adopted codes. Both are current Town documents and the Town does not reconcile them, so treat the edition as unsettled and confirm before designing to either. Sec. 20-41 amends the adopted IFC by deleting Section 105.6 (Required Operational Permits) in its entirety except for 105.6.30 (Open burning), but does not touch Section 105.7 (Required Construction Permits) — the section that requires a construction permit for installing automatic fire-extinguishing (sprinkler) systems and fire alarm/detection systems. Because only the operational-permit section was deleted, fire sprinkler and fire alarm system installation remains required under the Town's adopted fire code. One anomaly is worth knowing: Sec. 20-41(a) amends IFC Section 103.1 to place the 'department of fire prevention... under the direction of the Pagosa Fire Protection District' and defines the 'fire code official' as the Pagosa Fire Protection District Fire Chief. Pagosa Springs is roughly 100 miles away in Archuleta County with no jurisdictional connection to Center, so this reads as uncorrected boilerplate from a template ordinance rather than an actual arrangement — which makes the codified text's own designation of the local fire code official unreliable on its face. Center's actual local fire agency is the Center Fire Protection District (P.O. Box 845, Center, CO 81125; contact Kimberlee Schuett, 970-396-5396, Centerfire1941@gmail.com; serving Saguache, Rio Grande and Alamosa Counties; board meets at 360 East 8th Street/Hwy 112, Center, CO), but that district publishes no fire-code, permit, plan-review or inspection-fee information of any kind. The Town's own Building Permit Application/Fee Schedule has no fire-sprinkler or fire-alarm line item, checkbox or fee anywhere on it.
See fee scheduleChange of Use / Change of Occupancy Permit
The Town of Center has a directly codified change-of-use requirement. Town of Center Municipal Code Sec. 44-211(a), in Article 44-X (Administration and Enforcement) of Chapter 44 Zoning, current through Ord. No. 571 enacted 4-23-2024, states that 'every application for a Building Permit for construction, moving, alteration, or changes in the type of use or type of occupancy shall be accompanied by' a written statement and scaled plans showing, among other things, 'the existing and intended use of the plot and all structures upon it.' That requires a Building Permit for a change in the type of use or occupancy independent of whether any physical construction accompanies it. Note that the Town's combined Building Permit Application has no dedicated 'Change of Use' checkbox among its listed project types (New Construction, Additions, Mobile Home, Fence New/Replace, Deck or Patio, Reroof, Shed, Siding or Stucco, New Water/Gas/Sewer Tap, Other), so a pure change of use is filed under 'Other' even though the legal obligation is codified in Sec. 44-211(a) itself.
From$0.10
Center's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Center yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Center lands. Privacy.
New residential construction activity
New privately-owned residential construction onlyHousing units authorized by building permits for new privately-owned residential construction — this is not total permit volume (no commercial permits or remodels).
- Latest month (2026-07)
- No data reported
- Trailing 12 months
- No data reported
- Year to date (2026 YTD)
- No data reported
- Full year 2025
- No data reported
Source: U.S. Census Bureau, Building Permits Survey (BPS), 2026-07 vintage. Census survey data — separate from the permit-requirements verification above. All Colorado building activity
Tips & gotchas
- The seed URL (townofcenter.colorado.gov/departments/public-works-department/building-department) and its sibling path (.../departments/building-department) both now 301-redirect at the domain root to a completely new Town website, www.centerco.gov — the entire prior CivicPlus-style site has been retired. The new site is a minimal TownCloud/SvelteKit build (Documents/News/Agendas only, no dedicated department subpages), so all permitting information in this record was sourced from the Town's Documents page (Building Department category) and a dated Public Works Department news notice, not from a page matching the seed URL's original structure.
- The Town's Public Works Department (not a separately named 'Building Department' division) administers permitting directly — a June 23, 2026 dated public notice from the Town explicitly frames all building-permit requirements as Public Works Department functions.
- A flat, non-refundable $50.00 application fee applies to every permit type in Center, in addition to any valuation-based permit fee — this doubles the effective minimum cost of a small project (e.g., a $50 minimum reroof fee plus the $50 application fee = $100 total).
- Center charges flat per-square-foot building permit rates rather than a tiered valuation table: residential $0.10/sq ft, commercial $0.20/sq ft, and mobile homes $0.20/sq ft, with a $50 minimum.
- Electrical AND plumbing permits are NOT issued by the Town of Center at all — both are handled entirely by the State of Colorado DORA/DPO Electrical and Plumbing Boards, per the Town's own Fee Schedule document and corroborated by Ordinance 339's explicit exclusion of those trades from the Town's contractor-licensing definition. This is a materially different structure from jurisdictions that run their own certified electrical/plumbing inspection programs.
- Any contractor (other than electrical/plumbing) working on a job valued at $1,500 or more must hold a Town of Center Contractor's Registration (Ordinance 339, $50/yr General or $25/one-time Limited, plus a one-time $10 background-check fee) — carrying minimum $50,000 bodily injury / $100,000 property damage liability insurance.
- Building permits in Center are valid for only 180 days (6 months) — a materially shorter window than many jurisdictions' 1-year permit validity — and require an end-of-permit inspection before any reissue (flat $50 reissue fee regardless of project size).
- Center genuinely has a real, actively-maintained ADU program (Municipal Code Section 44-73/44-73.1) with objective administrative-approval standards (750 sq ft detached cap, 30% attached cap, 90-day minimum rental period) — a materially more developed ADU framework than one might expect for a town of this size. ADU zoning approval is a prerequisite to, but distinct from, the building permit needed to actually construct it.
- HB22-1362, Colorado's building energy-code/GHG statute, requires municipalities that update their building code on or after July 1, 2026 to adopt an equivalent-or-better energy code. It carries a rural-county carve-out tied to a state grant application and a full exclusion for municipalities with no building code at all, but no population-based exemption. Center currently operates on the 2018 IECC per its own Fee Schedule document, and no updated code-adoption action is published on its website - so the town's position under HB22-1362 is unresolved either way. Confirm with the Town before assuming which energy code applies.
- The Town of Center straddles Saguache County (majority of the town and its population) and Rio Grande County; several Town forms (e.g., the Demolition Application's landfill-notification checklist) explicitly branch by county — always confirm which county applies to your specific parcel/disposal site.
- The Town's current website publishes no adopted Climatic and Geographic Design Criteria chart, no separate trade-specific (non-electrical/plumbing) permit applications, and no dedicated 'Adopted Codes' page. The single Building Permit Application/Fee Schedule PDF — dated revised 09/2025 and issued by Public Works — is the Town's most complete currently-published source for code editions and fees; work from it, and confirm design criteria with Public Works directly.
- Two genuine gaps and one verified requirement, all read from the Town's own codified Code of Ordinances (Chapters 10, 20 and 44). First, no dedicated Sign Regulations article exists anywhere in Chapter 44 (Zoning) despite 'Sign' being a defined term (Sec. 44-221) — no dimensional, height or illumination standard is published, so a sign is filed as a generic structure under the Town's general Building Permit process. Second, the adopted fire code is the 2006 IFC (Sec. 20-40, per Ordinance No. 415 of 2011), not the 2018 edition the Town's own Building Permit Application and Fee Schedule PDF claims — a real discrepancy. That code was amended in 2011 to name the 'Pagosa Fire Protection District Fire Chief' as the local fire code official (Sec. 20-41(a)), but Pagosa Springs is an unrelated town roughly 100 miles away, so this reads as uncorrected boilerplate rather than a real arrangement. The result is that the enforcing authority for fire-sprinkler and alarm construction permits is genuinely unclear, even though Section 105.7 of the adopted IFC was never deleted and the Center Fire Protection District publishes no permit process of its own. By contrast, the change-of-use requirement is real and directly codified: Sec. 44-211(a) requires a Building Permit for 'changes in the type of use or type of occupancy' independent of whether construction accompanies the change, even though the Town's intake form has no dedicated Change of Use checkbox.