Change of Use Permit (Development Permit) in Breckenridge, Colorado

Breckenridge has no standalone 'change of use permit' by that name. A change of use is instead one of the enumerated triggers under the Planning Division's Development Permit classification system (Town Code Title 9): the Town's own Development Permits page explicitly lists 'Change of use within a residential district' as a Class B Minor Development Permit (typically a 7-week process with a preliminary and final Planning Commission hearing) and 'Change of use not in a residential district' as a Class C Minor Development Permit (typically a 3-week consent-calendar process). This is genuinely distinct from the Building Division's building-permit/Certificate of Occupancy process documented elsewhere in this file, and this file's own commercial-tenant-improvement-permit entry already cross-references the non-residential case — a retail-to-restaurant conversion is the Town's own worked example — as also triggering Upper Blue Sanitation District and Summit County Environmental Health review.

Verified 2026-08-13 · Source

When you need this permit

  • No standalone 'change of use permit' application exists; change of use is one of the enumerated triggers under the Town's Development Permit classification system (Town Code Title 9), administered by the Planning Division, and requires an approved Development Permit (with a Plan Case Number) that may run separately from, or as a precondition to, any Building Division construction permit for the same project
  • 'Change of use within a residential district' is expressly classified as a Class B Minor Development Permit, per the Town's own Development Permits page — typically a 7-week process with both a preliminary and final hearing before the Planning Commission
  • 'Change of use not in a residential district' is expressly classified as a Class C Minor Development Permit — typically a 3-week process as a consent-calendar item on the Planning Commission agenda
  • Class A, B, C, and D Major permits all require a mandatory pre-application meeting before submittal; submittals without one are returned and not processed
  • A retail-to-restaurant conversion is the Town's own worked example of a change of use (already cited in this file's commercial-tenant-improvement-permit entry) — it separately triggers Upper Blue Sanitation District review (use-change sign-off) and Summit County Environmental Health review (food establishment) alongside the Class C Minor Development Permit
  • Development Permit applications can be submitted in person at Town Hall (2nd floor) or via email to websitecommdev@townofbreckenridge.com; new structures require a physical set of plans dropped off at the Planning offices prior to Building Permit submittal
  • No static dollar fee is published for a Class B Minor or Class C Minor Development Permit specifically; the Town's own Development Permits page states that 'changes of use and new commercial development can incur employee generation fees, water Plant Investment Fees, and parking fees' and directs applicants to a Planner for a preliminary fee calculation — Development Permits generally are invoiced individually once entered into the Town's system rather than billed off a static published table (tree-removal permits and permits for deed-restricted properties are the only two categories the Town states carry no fee at all)
  • A genuine change of use with no accompanying construction can require only the Development Permit, without a parallel Building Division permit; where construction IS involved, the separate Certificate of Occupancy sign-off documented under this file's residential- and commercial-building-permit entries still applies

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Development Permit Fee (Class B Minor or Class C Minor, change of use)Billed individually once the Development Permit is entered into the Town's system, payable by check or card in person or online after invoicing, per the Development Permits page. No Class-specific dollar figure is published.
Not published as a static dollar figure
Change-of-use / added-square-footage exposurePer the Development Permits page, changes of use and new commercial development can incur employee generation fees, water Plant Investment Fees, and parking fees — contact a Planner (970-453-3160) for preliminary calculations. This mirrors the identical fee-exposure language already documented in this file's commercial-tenant-improvement-permit entry.
Varies

Review timeline

Plan reviewBreckenridge’s published plan-review target
21–49 business days

How long did your Change of Use Permit (Development Permit) permit actually take in Breckenridge?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Zoning/Land Use Compliance Review

    Planning Commission review (consent calendar for Class C Minor; preliminary and final hearing for Class B Minor), plus applicable referral departments (e.g., Upper Blue Sanitation District, Summit County Environmental Health) depending on scope

See the full Breckenridge inspection guide — scheduling & re-inspection fees →

Tips

  • Whether your change of use is 'Class B Minor' (7-week, residential district) or 'Class C Minor' (3-week consent-calendar, everywhere else) hinges entirely on the underlying zoning district — confirm classification with Planning (970-453-3160) before assuming which timeline governs.
  • A retail-to-restaurant conversion — the Town's own example — pulls in Upper Blue Sanitation District and Summit County Environmental Health review on top of the Development Permit itself, per this file's commercial-tenant-improvement-permit entry; budget for those parallel reviews, not just the Planning Commission's own clock.
  • No static fee table exists for a change-of-use Development Permit — new commercial development and changes of use can carry employee generation fees, water Plant Investment Fees, and parking fees, all calculated case-by-case; get a preliminary estimate from a Planner before committing to a budget.

Frequently asked questions

Breckenridge requires a change of use permit (development permit) for: No standalone 'change of use permit' application exists; change of use is one of the enumerated triggers under the Town's Development Permit classification system (Town Code Title 9), administered by the Planning Division, and requires an approved Development Permit (with a Plan Case Number) that may run separately from, or as a precondition to, any Building Division construction permit for the same project; 'Change of use within a residential district' is expressly classified as a Class B Minor Development Permit, per the Town's own Development Permits page — typically a 7-week process with both a preliminary and final hearing before the Planning Commission; 'Change of use not in a residential district' is expressly classified as a Class C Minor Development Permit — typically a 3-week process as a consent-calendar item on the Planning Commission agenda; Class A, B, C, and D Major permits all require a mandatory pre-application meeting before submittal; submittals without one are returned and not processed; A retail-to-restaurant conversion is the Town's own worked example of a change of use (already cited in this file's commercial-tenant-improvement-permit entry) — it separately triggers Upper Blue Sanitation District review (use-change sign-off) and Summit County Environmental Health review (food establishment) alongside the Class C Minor Development Permit; Development Permit applications can be submitted in person at Town Hall (2nd floor) or via email to websitecommdev@townofbreckenridge.com; new structures require a physical set of plans dropped off at the Planning offices prior to Building Permit submittal; No static dollar fee is published for a Class B Minor or Class C Minor Development Permit specifically; the Town's own Development Permits page states that 'changes of use and new commercial development can incur employee generation fees, water Plant Investment Fees, and parking fees' and directs applicants to a Planner for a preliminary fee calculation — Development Permits generally are invoiced individually once entered into the Town's system rather than billed off a static published table (tree-removal permits and permits for deed-restricted properties are the only two categories the Town states carry no fee at all); A genuine change of use with no accompanying construction can require only the Development Permit, without a parallel Building Division permit; where construction IS involved, the separate Certificate of Occupancy sign-off documented under this file's residential- and commercial-building-permit entries still applies. If your project isn't listed, confirm with Town of Breckenridge Community Development Department — Building Division at (970) 453-3180 before starting work.

In Breckenridge, the published Development Permit Fee (Class B Minor or Class C Minor, change of use) is: Not published as a static dollar figure. Additional published fees: Change-of-use / added-square-footage exposure — Varies. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the Town's own Development Permits page: about 7 weeks (with a preliminary and final Planning Commission hearing) for a change of use within a residential district (Class B Minor), or about 3 weeks (a consent-calendar item) for a change of use outside a residential district (Class C Minor).

You'll need: Pre-Application Meeting Confirmation. Depending on your project, Breckenridge may also ask for: Class B Minor Permit Form; Class C Minor Permit Form; Upper Blue Sanitation District sign-off or self-affidavit; Summit County Environmental Health sign-off or self-affidavit. See the required-documents checklist on this page for details on each.

Breckenridge requires 1 inspection(s) for a change of use permit (development permit), in order: Zoning/Land Use Compliance Review. Schedule each through Town of Breckenridge Community Development Department — Building Division ((970) 453-3180).

Apply through Town of Breckenridge Community Development Department — Building Division at 150 Ski Hill Road, 2nd Floor, PO Box 168, Breckenridge, CO 80424. Phone: (970) 453-3180, email: building@townofbreckenridge.com. Office hours: Monday-Thursday 8:00am-5:00pm, Friday 8:00am-12:00pm; closed major holidays. Official information: https://www.townofbreckenridge.com/departments/community-development/building.

No — change of use is one of the enumerated triggers under the Planning Division's Development Permit system (Town Code Title 9), not a standalone permit type. It is classified as a Class B Minor Development Permit if the change is within a residential district, or a Class C Minor Development Permit otherwise.

Yes. Per this file's own commercial-tenant-improvement-permit entry, a retail-to-restaurant conversion also triggers Upper Blue Sanitation District review and Summit County Environmental Health review (food establishment), in addition to whichever Development Permit class applies.

Sources & verification

Verified against official sources. Last reviewed 2026-08-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Breckenridge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.