Required for re-roofing work in Breckenridge. Governed by the 2025 Colorado Wildfire Resiliency Code Class A roofing requirements (applied town-wide, not just in a mapped WUI zone) plus IRC/IBC underlayment, valley-flashing, and ventilation standards, per the Town's own Re-Roof Requirements bulletin.

Verified 2026-07-06 · Source

When you need this permit

  • All roof coverings on new construction, additions, and re-roofs must be Class A, tested per ASTM E108 or UL 790 (CWRC Section 403.2 / 1505.1/R902.1)
  • If more than 25% of existing roof surface area is affected by reconstruction/replacement/alteration/repair, the work must meet the new-construction roof-covering standard (CWRC Section 101.6/403.2)
  • Roofs must be designed with snow-shed barriers to prevent snow from shedding onto balconies, decks, exits, stairways, sidewalks, streets, utility meters, or adjacent properties (Town Code 8-1-4, IBC 1503.6/IRC R903.1.1), except for roof areas with 48 inches or less horizontal dimension that won't shed onto a lower roof
  • Flame/ember protection required at any gap between roof covering profile and roof deck (firestopping, cap sheet per ASTM D3909, or listed Class A assembly) — CWRC 403.2.1
  • Valley flashings: minimum 0.019-inch (No. 26 galvanized) corrosion-resistant metal over a minimum 36-inch-wide underlayment of ASTM D3909 cap sheet running the full valley length — CWRC 403.2.2
  • Gutters and downspouts must be noncombustible material — CWRC 403.3
  • Ventilation openings for attics/rafter spaces/underfloor spaces must meet CWRC 403.4 performance (ASTM E2886 tested vents) or prescriptive (noncombustible corrosion-resistant mesh) requirements
  • Roof underlayment (self-adhering polymer-modified bitumen or equivalent, building-official approved) required under all roof coverings, extending from eave to ridge and covering the full deck; new construction requires the underlayment to extend a minimum of 30 inches up adjacent walls (IBC 1507.1.1/IRC R905.1.1)
  • Certain commercial/residential roofing types (EPDM, TPO, built-up, nail-fin, cold roof) may require third-party or manufacturer certification — verify with the Building Department
  • Minimum of two inspections typical: Underlayment and Flashing Inspection, and Final Building Inspection; ladder/access arrangements must be coordinated with the inspector in advance
  • The Building Division may use drone aerial photography for roofing inspections, determined case-by-case

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation-based (same Building, Mechanical & Plumbing Fee Schedule)Effective September 27, 2022
$50.00 minimum, scaling per valuation tiers
Plan Review Fee
65% of the permit fee
Re-inspection Fee
$65.00/hour

Review timeline

Plan review
Not published — contact the department

How long did your Roofing Permit (Re-Roof) permit actually take in Breckenridge?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underlayment and Flashing Inspection

    Underlayment, valley flashing, and ventilation openings verified before roof covering installation is completed

  2. 2

    Final Building Inspection

    Completed roof — Class A covering, snow-shed design, and all CWRC compliance items verified; drone aerial photography may be used

See the full Breckenridge inspection guide — scheduling & re-inspection fees →

Tips

  • Breckenridge requires Class A roof covering on every re-roof town-wide — this is a Colorado Wildfire Resiliency Code requirement that applies regardless of whether the parcel sits in a mapped wildfire hazard zone, unlike jurisdictions that only impose Class A roofing inside a WUI overlay.
  • If your re-roof project affects more than 25% of the existing roof surface, code treats it as new-construction-grade work — budget for full CWRC compliance, not a like-for-like patch.
  • Coordinate ladder/roof access with the inspector ahead of time; the Building Division may also fly a drone for the final inspection, so leave the roof accessible and complete (painted vent penetrations, debris cleared) before requesting it.

Frequently asked questions

Breckenridge requires a roofing permit (re-roof) for: All roof coverings on new construction, additions, and re-roofs must be Class A, tested per ASTM E108 or UL 790 (CWRC Section 403.2 / 1505.1/R902.1); If more than 25% of existing roof surface area is affected by reconstruction/replacement/alteration/repair, the work must meet the new-construction roof-covering standard (CWRC Section 101.6/403.2); Roofs must be designed with snow-shed barriers to prevent snow from shedding onto balconies, decks, exits, stairways, sidewalks, streets, utility meters, or adjacent properties (Town Code 8-1-4, IBC 1503.6/IRC R903.1.1), except for roof areas with 48 inches or less horizontal dimension that won't shed onto a lower roof; Flame/ember protection required at any gap between roof covering profile and roof deck (firestopping, cap sheet per ASTM D3909, or listed Class A assembly) — CWRC 403.2.1; Valley flashings: minimum 0.019-inch (No. 26 galvanized) corrosion-resistant metal over a minimum 36-inch-wide underlayment of ASTM D3909 cap sheet running the full valley length — CWRC 403.2.2; Gutters and downspouts must be noncombustible material — CWRC 403.3; Ventilation openings for attics/rafter spaces/underfloor spaces must meet CWRC 403.4 performance (ASTM E2886 tested vents) or prescriptive (noncombustible corrosion-resistant mesh) requirements; Roof underlayment (self-adhering polymer-modified bitumen or equivalent, building-official approved) required under all roof coverings, extending from eave to ridge and covering the full deck; new construction requires the underlayment to extend a minimum of 30 inches up adjacent walls (IBC 1507.1.1/IRC R905.1.1); Certain commercial/residential roofing types (EPDM, TPO, built-up, nail-fin, cold roof) may require third-party or manufacturer certification — verify with the Building Department; Minimum of two inspections typical: Underlayment and Flashing Inspection, and Final Building Inspection; ladder/access arrangements must be coordinated with the inspector in advance; The Building Division may use drone aerial photography for roofing inspections, determined case-by-case. If your project isn't listed, confirm with Town of Breckenridge Community Development Department — Building Division at (970) 453-3180 before starting work.

In Breckenridge, the published Building Permit Fee — valuation-based (same Building, Mechanical & Plumbing Fee Schedule) is: $50.00 minimum, scaling per valuation tiers. Additional published fees: Plan Review Fee — 65% of the permit fee; Re-inspection Fee — $65.00/hour. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Breckenridge does not publish a plan-review timeline for this permit. Contact Town of Breckenridge Community Development Department — Building Division at (970) 453-3180 for current turnaround.

You'll need: Roofing Permit Application (Access Portal); Re-Roof Requirements document. See the required-documents checklist on this page for details on each.

Breckenridge requires 2 inspection(s) for a roofing permit (re-roof), in order: Underlayment and Flashing Inspection, Final Building Inspection. Schedule each through Town of Breckenridge Community Development Department — Building Division ((970) 453-3180).

Apply through Town of Breckenridge Community Development Department — Building Division at 150 Ski Hill Road, 2nd Floor, PO Box 168, Breckenridge, CO 80424. Phone: (970) 453-3180, email: building@townofbreckenridge.com. Office hours: Monday-Thursday 8:00am-5:00pm, Friday 8:00am-12:00pm; closed major holidays. Official information: https://www.townofbreckenridge.com/departments/community-development/building.

Breckenridge, Colorado has adopted: 2024 International Building Code (IBC), including Appendix P, with Town-specific amendments codified at Breckenridge Town Code Title 8, Chapter 1, Section 8-1-4 — effective as of January 13, 2026 per the Town's Adopted Building Codes page; 2024 International Residential Code (IRC), including Appendices BE and BG, with local amendments at Town Code 8-1-5; 2024 International Plumbing Code (IPC), including Appendix C; 2024 International Mechanical Code (IMC), including Appendix A; 2024 International Fuel Gas Code (IFGC), including Appendices A and B; 2024 International Energy Conservation Code (IECC); 2024 International Existing Building Code (IEBC); 2024 International Pool and Spa Code (ISPSC); 2023 National Electrical Code (NEC); 2006 ICC Electrical Code — Administrative Provisions; 1997 Uniform Code for the Abatement of Dangerous Buildings; 2025 Colorado Wildfire Resiliency Code (CWRC) — adopted town-wide, NOT limited to a mapped Wildland-Urban Interface overlay; governs defensible-space site plans, Structure Ignition Zones 1-3, Class 1/Class 2 structure hardening, exterior roof coverings and wall materials on renovations affecting more than 25% of existing surface area, and additions increasing footprint by more than 500 sq ft; 2023 Colorado Model Electric Ready and Solar Ready Code — requires plans to show solar-ready zone location/size, roof dead/live load design values, EV-capable/EV-ready/EVSE parking space counts and conduit routing, per the Town's Permit Submittal Checklist; 2024 International Fire Code (IFC), including Appendices B through Q, adopted by reference without amendments; ICC A117.1-2017 Standard for Accessible and Usable Buildings and Facilities; Full adopted code text (Town Code Title 8, Chapter 1) hosted at breckenridge.town.codes/Code/8. Local amendments apply — see the Breckenridge overview page for the full list.

Class A roof covering is required town-wide on all new construction, additions, and re-roofs under the 2025 Colorado Wildfire Resiliency Code as adopted by Breckenridge — it is not limited to a mapped Wildland-Urban Interface zone.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Breckenridge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.