Required for electrical installation, alteration, or repair in Breckenridge. Governed by the 2023 NEC plus the 2006 ICC Electrical Code Administrative Provisions. Electrical work must be performed by a Colorado state-licensed Master Electrician/Electrical Contractor holding a Town of Breckenridge Business License.

Verified 2026-07-06 · Source

When you need this permit

  • Electrical work must be performed by a Colorado Licensed Electrician; contractor must provide a valid State of Colorado Electrical Contractor's License AND State of Colorado Master Electrician's License to apply Contractor
  • Contractor must hold a Town of Breckenridge Business License (the Town does not license general contractors separately)
  • Homeowner permits do NOT allow the owner to self-perform electrical work — it must be done by a Colorado state-licensed electrician even on an owner/builder permit Owner-builderContractor
  • Contemporaneous review of electrician licenses (per CRS 12-115) may be performed on job sites during inspections or randomly
  • Governed by the 2023 NEC and 2006 ICC Electrical Code Administrative Provisions as locally adopted

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit Fee — not more than 1,000 sq ftElectrical Permit Fees table, effective September 27, 2022 — Town of Breckenridge Building Department Fee Schedules page
$120.00
Electrical Permit Fee — over 1,000 sq ft and not more than 1,500 sq ft
$168.00
Electrical Permit Fee — over 1,500 sq ft and not more than 2,000 sq ft
$216.00
Electrical Permit Fee — over 2,000 sq ft
$216.00 plus $9.60 per 100 sq ft or fraction thereof over 2,000 sq ft
All other electrical work (valuation-based) — not more than $2,000.00
$120.00
All other electrical work (valuation-based) — more than $2,000.00
$9.60 per thousand or fraction thereof, plus $120.00
Mobile homes and travel parks, per space
$120.00
Temporary Power Permit
$65.00
Plan Review Fee (if required)
65% of the electrical permit fee
Re-inspection Fee
$65.00

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Breckenridge?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring and panel installed, before concealment

  2. 2

    Final Electrical

    System energized and verified; for solar/hot tub work, Final Electrical and Final Building inspections typically occur the same day

See the full Breckenridge inspection guide — scheduling & re-inspection fees →

Tips

  • Both a State of Colorado Electrical Contractor's License and a separate Master Electrician's License are required to apply — a business-only registration is not sufficient. Contractor
  • Breckenridge inspectors may conduct contemporaneous, on-site license verification (per CRS 12-115) — have current license documentation available on site, not just on file with the Town.

Frequently asked questions

Breckenridge requires an electrical permit for: Electrical work must be performed by a Colorado Licensed Electrician; contractor must provide a valid State of Colorado Electrical Contractor's License AND State of Colorado Master Electrician's License to apply; Contractor must hold a Town of Breckenridge Business License (the Town does not license general contractors separately); Homeowner permits do NOT allow the owner to self-perform electrical work — it must be done by a Colorado state-licensed electrician even on an owner/builder permit; Contemporaneous review of electrician licenses (per CRS 12-115) may be performed on job sites during inspections or randomly; Governed by the 2023 NEC and 2006 ICC Electrical Code Administrative Provisions as locally adopted. If your project isn't listed, confirm with Town of Breckenridge Community Development Department — Building Division at (970) 453-3180 before starting work.

In Breckenridge, the published Electrical Permit Fee — not more than 1,000 sq ft is: $120.00. Additional published fees: Electrical Permit Fee — over 1,000 sq ft and not more than 1,500 sq ft — $168.00; Electrical Permit Fee — over 1,500 sq ft and not more than 2,000 sq ft — $216.00; Electrical Permit Fee — over 2,000 sq ft — $216.00 plus $9.60 per 100 sq ft or fraction thereof over 2,000 sq ft; All other electrical work (valuation-based) — not more than $2,000.00 — $120.00; All other electrical work (valuation-based) — more than $2,000.00 — $9.60 per thousand or fraction thereof, plus $120.00; Mobile homes and travel parks, per space — $120.00; Temporary Power Permit — $65.00; Plan Review Fee (if required) — 65% of the electrical permit fee; Re-inspection Fee — $65.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Breckenridge does not publish a plan-review timeline for this permit. Contact Town of Breckenridge Community Development Department — Building Division at (970) 453-3180 for current turnaround.

You'll need: Electrical Permit Application (Access Portal); Colorado Electrical Contractor's License and Master Electrician's License; Town of Breckenridge Business License. See the required-documents checklist on this page for details on each.

Breckenridge requires 2 inspection(s) for an electrical permit, in order: Rough Electrical, Final Electrical. Schedule each through Town of Breckenridge Community Development Department — Building Division ((970) 453-3180).

Apply through Town of Breckenridge Community Development Department — Building Division at 150 Ski Hill Road, 2nd Floor, PO Box 168, Breckenridge, CO 80424. Phone: (970) 453-3180, email: building@townofbreckenridge.com. Office hours: Monday-Thursday 8:00am-5:00pm, Friday 8:00am-12:00pm; closed major holidays. Official information: https://www.townofbreckenridge.com/departments/community-development/building.

Breckenridge, Colorado has adopted: 2024 International Building Code (IBC), including Appendix P, with Town-specific amendments codified at Breckenridge Town Code Title 8, Chapter 1, Section 8-1-4 — effective as of January 13, 2026 per the Town's Adopted Building Codes page; 2024 International Residential Code (IRC), including Appendices BE and BG, with local amendments at Town Code 8-1-5; 2024 International Plumbing Code (IPC), including Appendix C; 2024 International Mechanical Code (IMC), including Appendix A; 2024 International Fuel Gas Code (IFGC), including Appendices A and B; 2024 International Energy Conservation Code (IECC); 2024 International Existing Building Code (IEBC); 2024 International Pool and Spa Code (ISPSC); 2023 National Electrical Code (NEC); 2006 ICC Electrical Code — Administrative Provisions; 1997 Uniform Code for the Abatement of Dangerous Buildings; 2025 Colorado Wildfire Resiliency Code (CWRC) — adopted town-wide, NOT limited to a mapped Wildland-Urban Interface overlay; governs defensible-space site plans, Structure Ignition Zones 1-3, Class 1/Class 2 structure hardening, exterior roof coverings and wall materials on renovations affecting more than 25% of existing surface area, and additions increasing footprint by more than 500 sq ft; 2023 Colorado Model Electric Ready and Solar Ready Code — requires plans to show solar-ready zone location/size, roof dead/live load design values, EV-capable/EV-ready/EVSE parking space counts and conduit routing, per the Town's Permit Submittal Checklist; 2024 International Fire Code (IFC), including Appendices B through Q, adopted by reference without amendments; ICC A117.1-2017 Standard for Accessible and Usable Buildings and Facilities; Full adopted code text (Town Code Title 8, Chapter 1) hosted at breckenridge.town.codes/Code/8. Local amendments apply — see the Breckenridge overview page for the full list.

No. Even on a homeowner (owner/builder) permit, all electrical work must be performed by a Colorado state-licensed electrician — it cannot be self-performed by the property owner.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Breckenridge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.