Frisco building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Frisco, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Frisco Town Hall, 1 East Main Street, P.O. Box 4100, Frisco, CO 80443
- Phone
- 970-668-9128
- Office hours
- Monday-Friday, 8:00 AM - 5:00 PM. Building permit administration is contracted to a third-party firm, Comprehensive Building Code Services, LLC (CBCS), since August 2024, when the Town's in-house Building Division was dissolved. CBCS contacts: Kara Fine, Contracted Permit Technician, 303-910-2966 / TOFPermits@townoffrisco.com; John C. Schumacher, Jr., CBO (CBCS owner), 303-550-2731. Community Development main line 970-668-5276; Planning Division 970-668-9131.
- Website
- Official site
Inspection sequence
Applies to: Residential Addition / Remodel Permit
- 1
Rough Frame
Framing complete before cover, for structural additions
- 2
Rough Plumbing / Mechanical
Trade rough-ins before concealment
- 3
Final Inspection
All work complete per approved plans; request online via CommunityCore before 4:00 PM for next-business-day inspection
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour
- 2
Rough Frame / Rough Mechanical / Rough Plumbing
Framing, plumbing, and mechanical rough-in inspected before concealment; electrical rough-in is inspected separately by Summit County Building Inspection Division
- 3
Final Inspection
All work complete per approved plans; inspections requested online via CommunityCore before 4:00 PM are conducted the next business day
Applies to: Electrical Permit
- 1
Rough Electrical
Conducted by Summit County Building Inspection Division inspectors, not Town of Frisco building inspectors
- 2
Final Inspection
Final electrical sign-off by Summit County
Applies to: EV Charger / EVSE Permit
- 1
Rough Electrical
Conducted by Summit County Building Inspection Division inspectors, not Town of Frisco building inspectors
- 2
Final Inspection
EVSE circuit and connections verified, final electrical sign-off by Summit County
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment connections inspected before concealment
- 2
Final Inspection
Equipment operational, venting and combustion air verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Requested after pipes installed and before concealment; inspector may conduct a contemporaneous licensure check of the plumbing contractor and any apprentices on site per C.R.S. 12-58
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Final inspection only: Demolition Permit, Roofing Permit (Re-Roof), Solar PV Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Frisco building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Frisco building permits
Get alerts for Frisco
We'll email you when Frisco's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.