Commercial Building Permit — Frisco, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.friscogov.com/departments/community-development/building-permits-and-plan-review/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Frisco, Colorado
Required for new commercial construction, additions, alterations/repairs to existing commercial buildings (including re-siding a commercial or multi-family structure), change in use or occupancy, moving, and demolition within Frisco town limits. Reviewed under the 2018 ICC code family (IBC) as locally amended by Frisco Town Code Chapter 65, plus the Summit Sustainable Building Code (SSBC, Ordinance 20-04) energy overlay requiring new commercial construction to demonstrate 25% energy savings above an ASHRAE 90.1 Energy Cost Budget baseline. Administered by the Town's Community Development Department via its contracted provider, Comprehensive Building Code Services, LLC (CBCS) — not Summit County — and submitted through the CommunityCore online portal. Tenant improvements are NOT a separate permit type in Frisco; they run through this same Building Permit track (see tips).
Verified 2026-08-02 · Source
When you need this permit
- Building Permit required for 'New building construction,' 'Additions, alterations, and repairs to existing buildings (including re-roofing a structure, replacing window or door units, and re-siding a commercial or multi-family structure),' and 'Change in use or occupancy of existing buildings' — per the Town's Building Permits page
- Summit Sustainable Building Code (Ordinance 20-04): 'All new commercial construction must demonstrate 25% energy savings above a baseline building energy model developed using ASHRAE 90.1 Energy Cost Budget protocol' — applies to all new commercial building applications since July 1, 2020
- Proof of Registration in LEED, Green Globe, or other program required for new construction or additions (IBC), per the Building Permit Submittal Requirements PDF
- 4 sets of plans to scale, including 1 set of structural plans stamped by a Colorado-licensed architect or engineer, plus a set of plans uploaded on CommunityCore
- Structural Calculations required for commercial projects
- Soils Investigation Report required for new construction and additions
- Signed Construction Management Plan and Standards (erosion control, noise, construction hours 7am-7pm Mon-Sat, fencing, dust/traffic control) required before permit issuance
- Engineer's stamp required on all mechanical and plumbing plans for commercial projects
- Contractor must hold a current Town of Frisco Business License (no town contractor's license required) Contractor
- If Planning Commission/Planning Division approval is required, plans must be submitted to the Planning Division for review PRIOR to Building Permit issuance
- Plan review fees are due at the time of application — CommunityCore requires at least a partial payment of the plan review fee at submission; only complete applications are accepted
- Electrical permit for the project is issued separately by Summit County Building Inspection Division, not the Town
- A separate Summit Fire & EMS permit (its own fee, submitted at summitfire.org) is independently required for new construction, tenant finish/remodels, occupancy/owner changes, and fire detection/suppression systems
- Valuation of work set per Frisco Town Code Section 65-12 A(3) — the Building Official has final authority on permit valuation
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 7 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour
- 2
Rough Frame / Rough Mechanical / Rough Plumbing
Framing, plumbing, and mechanical rough-in inspected before concealment; electrical rough-in is inspected separately by Summit County Building Inspection Division
- 3
Final Inspection
All work complete per approved plans; inspections requested online via CommunityCore before 4:00 PM are conducted the next business day. Summit Fire & EMS conducts its own inspections under its separate permit
See the full Frisco inspection guide — scheduling & re-inspection fees →
Tips
- Tenant improvement is NOT a separate permit type in Frisco — tenant finish, interior alterations, and change-of-occupancy projects all run through this same Building Permit track via CommunityCore. The practical distinction is in review speed: CBCS's published first-comments schedule splits 'Small/Minor Commercial' (11 business days) from 'Large Commercial' (21 business days), and a typical downtown Main Street tenant finish will fall in the small/minor commercial queue.
- Budget for the Summit Sustainable Building Code early: new commercial construction must demonstrate 25% energy savings above an ASHRAE 90.1 Energy Cost Budget baseline model, and the submittal checklist requires proof of registration in LEED, Green Globe, or another program for new construction or additions — this is genuinely above-code and affects design cost, not just paperwork.
- Plan for TWO parallel permit tracks on tenant finishes and new commercial construction: the Town/CBCS building permit AND a separate Summit Fire & EMS permit (own fee, submitted at summitfire.org) — SFE review covers tenant finish/remodels, occupancy/owner changes, and fire detection/suppression systems and is not bundled into the Town permit.
- Frisco's in-house Building Division was dissolved in August 2024 — commercial plan review and permit administration run through Comprehensive Building Code Services, LLC (Kara Fine, 303-910-2966, info@cbcscode.com), not town staff. Electrical permits for the project still go separately to Summit County Building Inspection Division (County Commons, 0037 Peak One Drive).
- If your project needs Planning Commission or Planning Division approval (common for new commercial buildings and exterior changes in the downtown core), that approval must be secured BEFORE the building permit can be issued — sequence it first.
- Commercial re-roofs and commercial/multi-family re-siding qualify for the faster Rapid Review Joint Application track (3-business-day target) rather than this full commercial building-permit process — check that list before assuming the slower track applies.
- The Comprehensive Fee Schedule publishes the exact plan-review percentage only for mechanical and plumbing permits (65% each) — the building-permit plan-review fee is confirmed to exist and be due at application, but its percentage is not published; confirm with CBCS before budgeting.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Frisco building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Frisco.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Frisco
Commercial Building Permit in other cities
Compare commercial building permit fees across Colorado →
Look up this fee in a different city →