Skip to main content
PermitBase

Solar PV Permit in Frisco, Colorado

Required for installation of residential or commercial solar photovoltaic systems in Frisco. Administered through Summit County (in collaboration with Summit Fire & EMS), not the Town's own Building Division — a one-stop process capped at $500 total fee per the Town's own page, though the Town's own Comprehensive Fee Schedule separately lists a state-allowable residential PV fee figure.

Verified 2026-07-06 · Source

When you need this permit

  • Solar/Photovoltaic permits are administered through Summit County in collaboration with Summit Fire & EMS, per the Town of Frisco Building Division page — not submitted through the Town's own CommunityCore building-permit track
  • A Summit Fire & EMS permit (separate, its own fee via summitfire.org) is also required for solar installations, per the SFE Permit Process for Applicant letter
  • Town of Frisco Building Division page states solar permits are capped at a $500.00 maximum total fee for the one-stop process

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Photovoltaic PermitTown of Frisco Comprehensive Fee Schedule (Dec 9, 2025) — two figures listed without further breakdown in the source; likely correspond to different system-size or plan-review-inclusive/exclusive tiers under the state fee cap, but the schedule does not clarify which applies when. Reported verbatim rather than guessing which figure governs a given project.
$303.05 / $196.95 (State allowable fees)
Solar one-stop process capTown of Frisco Building Division page
$500.00 maximum total

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Frisco?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Racking, roof penetrations, and electrical connections verified; electrical aspects inspected by Summit County

See the full Frisco inspection guide — scheduling & re-inspection fees →

Tips

  • Solar permits in Frisco route through Summit County (with Summit Fire & EMS), not the Town's own CommunityCore portal used for building/plumbing/mechanical — don't apply in the wrong system.
  • Budget for TWO separate fee tracks: the County-processed PV permit itself (capped at $500 total per the Town's page) and a separate Summit Fire & EMS permit fee.
  • The Fee Schedule's two dollar figures ($303.05 / $196.95) for Residential Photovoltaic Permit are not further explained on the schedule itself — confirm directly with Summit County or CBCS which applies to your system size/type before budgeting.

Frequently asked questions

Frisco requires a solar pv permit for: Solar/Photovoltaic permits are administered through Summit County in collaboration with Summit Fire & EMS, per the Town of Frisco Building Division page — not submitted through the Town's own CommunityCore building-permit track; A Summit Fire & EMS permit (separate, its own fee via summitfire.org) is also required for solar installations, per the SFE Permit Process for Applicant letter; Town of Frisco Building Division page states solar permits are capped at a $500.00 maximum total fee for the one-stop process. If your project isn't listed, confirm with Town of Frisco Community Development Department, Building Division at 970-668-9128 before starting work.

In Frisco, the published Residential Photovoltaic Permit is: $303.05 / $196.95 (State allowable fees). Additional published fees: Solar one-stop process cap — $500.00 maximum total. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Frisco does not publish a plan-review timeline for this permit. Contact Town of Frisco Community Development Department, Building Division at 970-668-9128 for current turnaround.

You'll need: Solar PV Permit Application (Summit County process, in collaboration with Summit Fire & EMS); Summit Fire & EMS Permit Application. See the required-documents checklist on this page for details on each.

Frisco requires 1 inspection(s) for a solar pv permit, in order: Final Inspection. Schedule each through Town of Frisco Community Development Department, Building Division (970-668-9128).

Apply through Town of Frisco Community Development Department, Building Division at Frisco Town Hall, 1 East Main Street, P.O. Box 4100, Frisco, CO 80443. Phone: 970-668-9128, email: TOFPermits@townoffrisco.com. Office hours: Monday-Friday, 8:00 AM - 5:00 PM. Building permit administration is contracted to a third-party firm, Comprehensive Building Code Services, LLC (CBCS), since August 2024, when the Town's in-house Building Division was dissolved. CBCS contacts: Kara Fine, Contracted Permit Technician, 303-910-2966 / TOFPermits@townoffrisco.com; John C. Schumacher, Jr., CBO (CBCS owner), 303-550-2731. Community Development main line 970-668-5276; Planning Division 970-668-9131.. Official information: https://www.friscogov.com/departments/community-development/building-division/.

Frisco, Colorado has adopted: The Town of Frisco currently uses the 2018 International Code Council (ICC) code family — Town of Frisco Building Permits & Plan Review page states verbatim: 'The Town of Frisco currently uses the 2018 International Code Council codes.' (International Building Code, International Residential Code, and related I-Codes; specific IECC/IMC/IPC/IFC edition years beyond '2018 ICC family' are not individually broken out on the Town's public pages — local amendments live in Frisco Town Code Chapter 65, Building Construction and Housing Standards, which is hosted on Municode (library.municode.com/co/frisco) but renders as a JavaScript single-page app that could not be retrieved as readable text via direct fetch, browser-header curl, or the Wayback Machine snapshot (which mirrors the same JS shell) during this research session — flagged as an open item below rather than guessed at.); Summit Sustainable Building Code (SSBC) — adopted by Town Council Ordinance 20-04 on April 14, 2020, as an 'above-code' energy standard layered on top of the 2018 ICC base codes. Source: Town of Frisco Building Permits & Plan Review page.; National Electrical Code (NEC) — electrical permits and their governing NEC edition are administered entirely by Summit County Building Inspection Division, not the Town; edition not independently confirmed on the Town's own pages (see localAmendments).. Local amendments apply — see the Frisco overview page for the full list.

Solar/photovoltaic permits are processed through Summit County in collaboration with Summit Fire & EMS, not through the Town of Frisco's own Building Division — described by the Town as a 'one-stop' process capped at a $500 maximum total fee.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Frisco building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.