Required for furnaces, boilers, fireplaces, and other heating/mechanical equipment installation or replacement in Frisco. Issued by the Town's Building Division (CBCS-administered). Many like-for-like mechanical replacements qualify for the faster Rapid Review Joint Application rather than the standard Building Permit track.

Verified 2026-07-06 · Source

When you need this permit

  • Permit required for furnace, boiler, and fireplace installation or replacement; hot tubs on existing decks/slabs also route through Rapid Review
  • Product specification sheets required for all replacement equipment except direct-vent fireplaces; not required for equipment installed as part of a new commercial construction project (already covered by that permit's plan set)
  • Engineer's stamp required on mechanical plans for commercial projects
  • If Mechanical and Plumbing permits are both required for the same scope of work under Rapid Review, the fee is charged at 2x the base valuation-based rate per the Rapid Review chart

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Mechanical Permit FeeTown of Frisco Comprehensive Fee Schedule (Dec 9, 2025), citing Frisco Town Code Section 65-13 C(1)
Determined by applying the project valuation to the corresponding Building Permit Valuation fee tiers
Mechanical Permit Plan Review FeeSeparate from and in addition to the permit fee
65% of the mechanical permit fee
Rapid Review — Furnace/Boiler/Fireplace replacementRapid Review Joint Submittal Online Requirements PDF (April 2024)
Based on valuation of work (building fee); doubled if both Mechanical and Plumbing permits required for the same project

Review timeline

Plan review
Not published — contact the department

How long did your Mechanical / HVAC Permit permit actually take in Frisco?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment connections inspected before concealment

  2. 2

    Final Inspection

    Equipment operational, venting and combustion air verified

See the full Frisco inspection guide — scheduling & re-inspection fees →

Tips

  • Furnace, boiler, and fireplace replacements usually qualify for the Rapid Review Joint Application (target 3-business-day turnaround) rather than the slower standard Building Permit track — confirm eligibility before assuming the longer CBCS review timeline applies.
  • Direct-vent fireplaces are specifically exempted from the product-spec-sheet submittal requirement under Rapid Review — a small but real paperwork savings if you're installing one.

Frequently asked questions

Yes, but it typically qualifies for the Town's Rapid Review Joint Application, which targets a 3-business-day turnaround once a complete application and fees are submitted online via CommunityCore, rather than the longer standard building-permit review track.

In Frisco, the published Mechanical Permit Fee is: Determined by applying the project valuation to the corresponding Building Permit Valuation fee tiers. Additional published fees: Mechanical Permit Plan Review Fee — 65% of the mechanical permit fee; Rapid Review — Furnace/Boiler/Fireplace replacement — Based on valuation of work (building fee); doubled if both Mechanical and Plumbing permits required for the same project. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Frisco does not publish a plan-review timeline for this permit. Contact Town of Frisco Community Development Department, Building Division at 970-668-9128 for current turnaround.

You'll need: Rapid Review Joint Application or standard Building Permit Application (CommunityCore); Product spec sheets. See the required-documents checklist on this page for details on each.

Frisco requires 2 inspection(s) for a mechanical / hvac permit, in order: Rough Mechanical, Final Inspection. Schedule each through Town of Frisco Community Development Department, Building Division (970-668-9128).

Apply through Town of Frisco Community Development Department, Building Division at Frisco Town Hall, 1 East Main Street, P.O. Box 4100, Frisco, CO 80443. Phone: 970-668-9128, email: TOFPermits@townoffrisco.com. Office hours: Monday-Friday, 8:00 AM - 5:00 PM. Building permit administration is contracted to a third-party firm, Comprehensive Building Code Services, LLC (CBCS), since August 2024, when the Town's in-house Building Division was dissolved. CBCS contacts: Kara Fine, Contracted Permit Technician, 303-910-2966 / TOFPermits@townoffrisco.com; John C. Schumacher, Jr., CBO (CBCS owner), 303-550-2731. Community Development main line 970-668-5276; Planning Division 970-668-9131.. Official information: https://www.friscogov.com/departments/community-development/building-division/.

Frisco, Colorado has adopted: The Town of Frisco currently uses the 2018 International Code Council (ICC) code family — Town of Frisco Building Permits & Plan Review page states verbatim: 'The Town of Frisco currently uses the 2018 International Code Council codes.' (International Building Code, International Residential Code, and related I-Codes; specific IECC/IMC/IPC/IFC edition years beyond '2018 ICC family' are not individually broken out on the Town's public pages — local amendments live in Frisco Town Code Chapter 65, Building Construction and Housing Standards, which is hosted on Municode (library.municode.com/co/frisco) but renders as a JavaScript single-page app that could not be retrieved as readable text via direct fetch, browser-header curl, or the Wayback Machine snapshot (which mirrors the same JS shell) during this research session — flagged as an open item below rather than guessed at.); Summit Sustainable Building Code (SSBC) — adopted by Town Council Ordinance 20-04 on April 14, 2020, as an 'above-code' energy standard layered on top of the 2018 ICC base codes. Source: Town of Frisco Building Permits & Plan Review page.; National Electrical Code (NEC) — electrical permits and their governing NEC edition are administered entirely by Summit County Building Inspection Division, not the Town; edition not independently confirmed on the Town's own pages (see localAmendments).. Local amendments apply — see the Frisco overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Frisco building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.