EV Charger / EVSE Permit in Frisco, Colorado

Required for installation of a residential or commercial electric vehicle charging station (EVSE) on any property within Frisco town limits. As with all electrical work in Frisco, the permit is issued entirely by the Summit County Building Inspection Division, not the Town of Frisco's own Building Division — the Town's own Building Permits & Plan Review page states verbatim that 'all electrical permits for the Town of Frisco are issued by the Summit County Building Inspection Division.' The Town's Comprehensive Fee Schedule has no distinct EV-charger/EVSE line item; a standalone EVSE circuit is billed under the same general Electrical Permit fee tiers listed for other standalone electrical work (e.g., the same flat-rate treatment as a Hot Tub electrical hookup).

Verified 2026-07-20 · Source

When you need this permit

  • New dedicated 120V or 240V circuit installation for EVSE equipment requires an electrical permit issued by Summit County Building Inspection Division, not the Town of Frisco
  • Applicants must apply directly to Summit County Building Inspection Division (County Commons, 0037 Peak One Drive, Frisco, CO 80443), not through the Town's CommunityCore portal used for building/plumbing/mechanical permits
  • If the EVSE installation requires a panel or service upgrade, that additional scope is billed under the same Electrical Permit valuation-based tiers

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit — Other, valuation <$2,000.00Town of Frisco Comprehensive Fee Schedule, Adoption Date December 9, 2025. No EV-specific line item is published; a standalone EVSE circuit installation (typically under $2,000 in electrical valuation) is billed under this general 'Other' electrical tier, the same category used for e.g. a Hot Tub hookup ($120 flat).
$120.00
Electrical Permit — Other, valuation ≥$2,000.00Applies if the EVSE circuit (or a combined EVSE-plus-panel-upgrade scope) exceeds $2,000 in electrical valuation.
$9.60 per $1,000.00 or fraction thereof, plus $120.00
Electrical Permit — Additional Plan Review
$65.00
Electrical Permit — Reinspection
$65.00

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Frisco?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conducted by Summit County Building Inspection Division inspectors, not Town of Frisco building inspectors

  2. 2

    Final Inspection

    EVSE circuit and connections verified, final electrical sign-off by Summit County

See the full Frisco inspection guide — scheduling & re-inspection fees →

Tips

  • Do not submit your EV charger electrical permit through the Town's CommunityCore portal — it will not be processed there. Apply directly to Summit County Building Inspection Division, the same rule that applies to all electrical work in Frisco.
  • Frisco has no distinct EV charger fee line item — a standalone EVSE circuit is billed under the general Electrical Permit 'Other' valuation tiers on the Town's Comprehensive Fee Schedule, typically the flat $120 rate for scope under $2,000 in valuation.
  • Summit County's building-department office is physically located inside Frisco town limits at County Commons, 0037 Peak One Drive, despite being a distinct county authority rather than a Town of Frisco department.

Frequently asked questions

Frisco requires an ev charger / evse permit for: New dedicated 120V or 240V circuit installation for EVSE equipment requires an electrical permit issued by Summit County Building Inspection Division, not the Town of Frisco; Applicants must apply directly to Summit County Building Inspection Division (County Commons, 0037 Peak One Drive, Frisco, CO 80443), not through the Town's CommunityCore portal used for building/plumbing/mechanical permits; If the EVSE installation requires a panel or service upgrade, that additional scope is billed under the same Electrical Permit valuation-based tiers. If your project isn't listed, confirm with Town of Frisco Community Development Department, Building Division at 970-668-9128 before starting work.

In Frisco, the published Electrical Permit — Other, valuation <$2,000.00 is: $120.00. Additional published fees: Electrical Permit — Other, valuation ≥$2,000.00 — $9.60 per $1,000.00 or fraction thereof, plus $120.00; Electrical Permit — Additional Plan Review — $65.00; Electrical Permit — Reinspection — $65.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Frisco does not publish a plan-review timeline for this permit. Contact Town of Frisco Community Development Department, Building Division at 970-668-9128 for current turnaround.

You'll need: Electrical Permit Application (Summit County Building Inspection Division). See the required-documents checklist on this page for details on each.

Frisco requires 2 inspection(s) for an ev charger / evse permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of Frisco Community Development Department, Building Division (970-668-9128).

Apply through Town of Frisco Community Development Department, Building Division at Frisco Town Hall, 1 East Main Street, P.O. Box 4100, Frisco, CO 80443. Phone: 970-668-9128, email: TOFPermits@townoffrisco.com. Office hours: Monday-Friday, 8:00 AM - 5:00 PM. Building permit administration is contracted to a third-party firm, Comprehensive Building Code Services, LLC (CBCS), since August 2024, when the Town's in-house Building Division was dissolved. CBCS contacts: Kara Fine, Contracted Permit Technician, 303-910-2966 / TOFPermits@townoffrisco.com; John C. Schumacher, Jr., CBO (CBCS owner), 303-550-2731. Community Development main line 970-668-5276; Planning Division 970-668-9131.. Official information: https://www.friscogov.com/departments/community-development/building-division/.

Frisco, Colorado has adopted: The Town of Frisco currently uses the 2018 International Code Council (ICC) code family — Town of Frisco Building Permits & Plan Review page states verbatim: 'The Town of Frisco currently uses the 2018 International Code Council codes.' (International Building Code, International Residential Code, and related I-Codes; specific IECC/IMC/IPC/IFC edition years beyond '2018 ICC family' are not individually broken out on the Town's public pages — local amendments live in Frisco Town Code Chapter 65, Building Construction and Housing Standards, which is hosted on Municode (library.municode.com/co/frisco) but renders as a JavaScript single-page app that could not be retrieved as readable text via direct fetch, browser-header curl, or the Wayback Machine snapshot (which mirrors the same JS shell) during this research session — flagged as an open item below rather than guessed at.); Summit Sustainable Building Code (SSBC) — adopted by Town Council Ordinance 20-04 on April 14, 2020, as an 'above-code' energy standard layered on top of the 2018 ICC base codes. Source: Town of Frisco Building Permits & Plan Review page.; National Electrical Code (NEC) — electrical permits and their governing NEC edition are administered entirely by Summit County Building Inspection Division, not the Town; edition not independently confirmed on the Town's own pages (see localAmendments).. Local amendments apply — see the Frisco overview page for the full list.

No. As with all electrical work in Frisco, EV charger/EVSE permits are issued by the Summit County Building Inspection Division, not the Town of Frisco's own Building Division. The Town's Comprehensive Fee Schedule lists the fee (typically the $120 flat 'Other, valuation <$2,000' electrical tier), but Summit County administers the permit itself.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Frisco building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.