Skip to main content
PermitBase

Fire Sprinkler / Fire Alarm System Permit in Fort Lupton, Colorado

Fire protection and fire prevention plan review in Fort Lupton is provided by the Fort Lupton Fire Protection District's Fire Prevention Division (303-857-4603), operating under the 2018 editions of the International Fire Code (IFC) and International Building Code (IBC), plus applicable NFPA standards, per the District's own Directions for Plan Review Submittals and Fire Alarm/Sprinkler Requirements pages. Sprinkler and alarm shop drawings are submitted electronically along with the original City building permit application directly to the District's Fire Prevention Division, which reviews all plans in-house with a published 7-10 day turnaround.

Verified 2026-08-13 · Source

When you need this permit

  • Sprinkler and fire alarm shop drawings must be electronically submitted directly to the Fort Lupton Fire Prevention Division along with (or referencing) the original City building permit application
  • Required submittal package: three complete sets of scaled shop drawings, battery and voltage-drop calculations, manufacturers' equipment cut sheets, and a copy of the contractor's Colorado state license
  • Fire alarm and fire sprinkler drawings must bear the stamp of a NICET Level III (or higher) technician in the appropriate field of engineering
  • Published review turnaround is 7-10 days; all plans are reviewed in-house by the Fire Prevention Division
  • After approval, the applicant receives two stamped sets of drawings; one stamped set must remain on-site throughout construction
  • All buildings with fire sprinklers and fire alarms must have interior horn/strobe units, exterior strobes, and manual pull stations
  • Current codes enforced: 2018 IFC, 2018 IBC, and applicable NFPA codes (e.g., NFPA 13 for sprinklers, NFPA 72 for alarms), per the District's Directions for Plan Review Submittals page

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Sprinkler PlansIncludes plan review, 1 rough-in/hydro test, and 1 final/acceptance test, per the District's Fee Schedule
$40.00
Commercial Sprinkler System Inspection (tiered by site square footage)Fee schedule includes plan review, field inspections, and test witnessing bundled into the tiered amount, per the District's Fee Schedule
$50.00 (0-2,500 sq ft) up to $1,750.00 (1,000,001+ sq ft)
Fire Alarm System Inspection (tiered by site square footage)Additional inspections beyond those included are billed at hourly rates
$50.00 to $1,750.00, same tier structure as sprinkler inspections

Review timeline

Plan reviewFort Lupton’s published plan-review target
7–10 business days

How long did your Fire Sprinkler / Fire Alarm System Permit permit actually take in Fort Lupton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underground Supply Flush Test

    Fire Prevention Division witnesses the flush test of the underground supply for the suppression system

  2. 2

    Sprinkler Hydrostatic Test

    200 PSI automatic fire sprinkler hydrostatic test witnessed by the Fire Prevention Division

  3. 3

    Fire Alarm Acceptance Test

    Verifies system installation matches approved drawings, all alarm devices function, wiring is correct (including dispatch trouble-signal verification), water flow transmits between 45-60 seconds of the inspector's test valve opening, and required labeling/signage is present

  4. 4

    Kitchen Hood Suppression Test

    Required where a commercial kitchen hood suppression system is installed

See the full Fort Lupton inspection guide — scheduling & re-inspection fees →

Tips

  • Submit sprinkler and alarm shop drawings directly to the Fort Lupton Fire Prevention Division electronically, alongside the City building permit application — the District, not the City Building Department, performs this in-house review.
  • Drawings must be stamped by a NICET Level III or higher technician — plans without this stamp will not be accepted for review.
  • Keep one stamped, approved set of drawings on-site throughout construction; the Fire Prevention Division checks for it during inspections.

Frequently asked questions

Fort Lupton requires a fire sprinkler / fire alarm system permit for: Sprinkler and fire alarm shop drawings must be electronically submitted directly to the Fort Lupton Fire Prevention Division along with (or referencing) the original City building permit application; Required submittal package: three complete sets of scaled shop drawings, battery and voltage-drop calculations, manufacturers' equipment cut sheets, and a copy of the contractor's Colorado state license; Fire alarm and fire sprinkler drawings must bear the stamp of a NICET Level III (or higher) technician in the appropriate field of engineering; Published review turnaround is 7-10 days; all plans are reviewed in-house by the Fire Prevention Division; After approval, the applicant receives two stamped sets of drawings; one stamped set must remain on-site throughout construction; All buildings with fire sprinklers and fire alarms must have interior horn/strobe units, exterior strobes, and manual pull stations; Current codes enforced: 2018 IFC, 2018 IBC, and applicable NFPA codes (e.g., NFPA 13 for sprinklers, NFPA 72 for alarms), per the District's Directions for Plan Review Submittals page. If your project isn't listed, confirm with City of Fort Lupton Planning & Building Department (Building Division) at 720-928-4003 before starting work.

$40.00, which includes plan review, one rough-in/hydro test, and one final/acceptance test, per the Fort Lupton Fire Protection District's Fee Schedule.

Fort Lupton's published plan-review target for a fire sprinkler / fire alarm system permit is 7–10 business days.

You'll need: Scaled Shop Drawings (3 sets); Battery and Voltage Drop Calculations; Manufacturer's Equipment Cut Sheets; Contractor's State License (copy). See the required-documents checklist on this page for details on each.

Fort Lupton requires 4 inspection(s) for a fire sprinkler / fire alarm system permit, in order: Underground Supply Flush Test, Sprinkler Hydrostatic Test, Fire Alarm Acceptance Test, Kitchen Hood Suppression Test. Schedule each through City of Fort Lupton Planning & Building Department (Building Division) (720-928-4003).

Apply through City of Fort Lupton Planning & Building Department (Building Division) at 1200 Dexter Street, Unit W13, Fort Lupton, CO 80621 (mailing: 130 S McKinley Ave, Fort Lupton, CO 80621). Phone: 720-928-4003, email: buildingdept@fortluptonco.gov. Office hours: Not published on the Building Department page as of this review. Key staff direct lines: Jonathan Gesick (Building Official, SAFEbuilt contract) 970-518-5269 jgesick@safebuilt.com; Jose Gonzalez (Building Official II, ProCode Inc. contract) 970-305-3161 jgonzalez@procodeinc.net (also reachable at coemail@safebuilt.com per the New Construction Requirements page); Shannon DeVries (Permit Technician I) 720-466-6104 buildingdept@fortluptonco.gov; Todd Hodges (Planning Director) 720-466-6106 thodges@fortluptonco.gov.. Official information: https://www.fortluptonco.gov/208/Building.

Fort Lupton, Colorado has adopted: 2024 International Building Code (IBC) — City of Fort Lupton, Current Adopted Codes & Additional Resources page, adopted by Ordinance No. 2026-1198 (approved by City Council January 20, 2026, effective after publication March 28, 2026), replacing the prior 2018 code cycle; 2024 International Residential Code (IRC); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC); 2024 International Fuel Gas Code (IFGC); 2024 International Fire Code (IFC); 2024 International Existing Building Code (IEBC); 2024 International Energy Conservation Code (IECC); 2024 International Property Maintenance Code; 2024 International Swimming Pool and Spa Code; 2023 National Electrical Code (NEC) — state-mandated edition per Colorado statute, referenced on the same Current Adopted Codes page; Colorado Model Electric Ready and Solar Ready Code, 2023 Edition — adopted by reference in the same Ordinance No. 2026-1198 (per Resolution No. 2026R020 recitals), enacting new municipal code sections rather than amending the I-Codes directly; Colorado Wildfire Resiliency Code, 2025 Edition — likewise adopted by reference in Ordinance No. 2026-1198, effective March 28, 2026; Note on prior-cycle residue: a ProCode Inc.-branded 'Residential Energy Compliance Certificate' template still in departmental circulation references the superseded '2012/2018 IECC (Res) as amended' baseline for duct-leakage (R403.3.3) and building-envelope (R402.1.2) testing language; the live Current Adopted Codes webpage and Resolution No. 2026R020 recitals (Ordinance 2026-1198, 2024 I-Codes) are treated as the current, governing adoption for this file since they are the actively maintained code-adoption authority, not a legacy form that has not yet been reprinted.. Local amendments apply — see the Fort Lupton overview page for the full list.

The Fort Lupton Fire Protection District's Fire Prevention Division (303-857-4603) reviews all sprinkler and alarm shop drawings in-house, with a published 7-10 day turnaround, submitted alongside the original City building permit application.

Sources & verification

Verified against official sources. Last reviewed 2026-08-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fort Lupton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.