Accessory Dwelling Units are listed among the project types requiring a building permit in Fort Lupton, and are permitted through the general residential building-permit submittal process (no distinct 'ADU permit' application or fee line), but ARE governed by a detailed, codified ADU-specific zoning standard: Fort Lupton Municipal Code Sec. 16-4.03(2) (Chapter 16, Development Code, Article IV — Zoning District and Uses, 'Accessory Uses'), adopted by Ord. No. 2022-1143 (6-7-2022) and amended by Ord. No. 2023-1159 (9-5-2023) and Ord. No. 2025-1197 (12-2-2025), confirmed live on Municode (Supp. No. 29, online content updated June 4, 2026).

Verified 2026-07-23 · Source

When you need this permit

  • Listed explicitly as requiring a building permit on the Permit Information page
  • Processed under the general Single-Family/accessory-structure New Construction Requirements submittal set (plot plan, engineered foundation where applicable, energy code compliance)
  • Pre-Application Meeting with Planning staff required before submitting an ADU building-permit application, unless waived by the Director (Municipal Code Sec. 16-4.03(2)a.1)
  • One ADU permitted per lot, only when associated with either a proposed or existing detached house or duplex/multi-unit house (Sec. 16-4.03(2)a.2)
  • ADU may be a detached accessory building, attached accessory building, or located within the principal building (attic, basement, garage, or rear apartment) (Sec. 16-4.03(2)a.3); a garage required to meet the principal dwelling's minimum parking cannot be converted into an ADU (Sec. 16-4.03(2)a.4)
  • Size cap: for lots under 40,000 sq ft or between 40,000 sq ft and 5 acres, the ADU may not exceed 100% of the principal dwelling's livable square footage (minimum 750 sq ft allowance if the principal dwelling is under 750 sq ft); no size limit for lots 5 acres or larger (Sec. 16-4.03(2)a.5-7)
  • Height capped at 35'; setbacks: front meets/exceeds the principal dwelling's Table 5-1 (or Table 6-1 for RO-zone ADUs) front minimum, side 5', side corner meets/exceeds Table 5-1/6-1 corner-side minimum, rear 5' (0' above an alley-loaded garage absent an easement conflict) (Sec. 16-4.03(2)b.1-2)
  • Design compatibility: the ADU must visually match the principal dwelling in at least 3 of 6 ways (color palette, roof pitch, roof material, façade materials, height not exceeding principal dwelling, window dimensions/height) (Sec. 16-4.03(2)b.3)
  • Access/addressing: minimum 3' delineated pedestrian connection from the ADU entrance to the public sidewalk/alley (or to the principal building's public access point if none exists); both units must have individual, visible, city-assigned addresses; no additional off-street parking is required (up to 2 on-street spots may be identified if not already required for the principal dwelling); no new access/curb-cut permit is issued for an ADU (Sec. 16-4.03(2)c.1-7)
  • Zoning compliance (lot coverage, general district standards) otherwise governed by the Fort Lupton Municipal Code (Municode Chapter 16, Development Code), not a Building Division-specific ADU page

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (general valuation-based schedule)No ADU-specific fee line item is published; billed under the general Building Permit Fee schedule based on the ADU's construction valuation
$24.00 minimum, scaling per the valuation tiers in Resolution No. 2026R020
Plan Review Fee
65% of Building Permit Fee

Review timeline

Plan reviewFort Lupton’s published plan-review target
7–10 business days

How long did your Accessory Dwelling Unit (ADU) Permit permit actually take in Fort Lupton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Prior to concrete pour (new-construction ADU)

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans

See the full Fort Lupton inspection guide — scheduling & re-inspection fees →

Tips

  • Fort Lupton has no dedicated ADU permit application or fee line distinct from a standard residential building permit, but it DOES have a detailed codified ADU zoning standard (Municipal Code Sec. 16-4.03(2)) — review the size cap (100% of principal dwelling's livable sq ft, or 750 sq ft minimum allowance), 35' height limit, and the 3-of-6 design-compatibility requirement before finalizing plans.
  • A Pre-Application Meeting with Planning staff is required before submitting an ADU building-permit application, unless waived by the Director — confirm zoning eligibility (lot size, use-by-district, setbacks) with the Planning Director (Todd Hodges, 720-466-6106) at that meeting.
  • Because no ADU-specific fee exists, expect your ADU to be billed exactly like a small new-construction residential building permit under the general valuation-based schedule.
  • No new access/curb-cut permit is issued for an ADU — off-street parking construction must use an existing driveway or alley access unless the Public Works Director deems the lot's width/spacing/orientation sufficient for a new one.

Frequently asked questions

Fort Lupton requires an accessory dwelling unit (adu) permit for: Listed explicitly as requiring a building permit on the Permit Information page; Processed under the general Single-Family/accessory-structure New Construction Requirements submittal set (plot plan, engineered foundation where applicable, energy code compliance); Pre-Application Meeting with Planning staff required before submitting an ADU building-permit application, unless waived by the Director (Municipal Code Sec. 16-4.03(2)a.1); One ADU permitted per lot, only when associated with either a proposed or existing detached house or duplex/multi-unit house (Sec. 16-4.03(2)a.2); ADU may be a detached accessory building, attached accessory building, or located within the principal building (attic, basement, garage, or rear apartment) (Sec. 16-4.03(2)a.3); a garage required to meet the principal dwelling's minimum parking cannot be converted into an ADU (Sec. 16-4.03(2)a.4); Size cap: for lots under 40,000 sq ft or between 40,000 sq ft and 5 acres, the ADU may not exceed 100% of the principal dwelling's livable square footage (minimum 750 sq ft allowance if the principal dwelling is under 750 sq ft); no size limit for lots 5 acres or larger (Sec. 16-4.03(2)a.5-7); Height capped at 35'; setbacks: front meets/exceeds the principal dwelling's Table 5-1 (or Table 6-1 for RO-zone ADUs) front minimum, side 5', side corner meets/exceeds Table 5-1/6-1 corner-side minimum, rear 5' (0' above an alley-loaded garage absent an easement conflict) (Sec. 16-4.03(2)b.1-2); Design compatibility: the ADU must visually match the principal dwelling in at least 3 of 6 ways (color palette, roof pitch, roof material, façade materials, height not exceeding principal dwelling, window dimensions/height) (Sec. 16-4.03(2)b.3); Access/addressing: minimum 3' delineated pedestrian connection from the ADU entrance to the public sidewalk/alley (or to the principal building's public access point if none exists); both units must have individual, visible, city-assigned addresses; no additional off-street parking is required (up to 2 on-street spots may be identified if not already required for the principal dwelling); no new access/curb-cut permit is issued for an ADU (Sec. 16-4.03(2)c.1-7); Zoning compliance (lot coverage, general district standards) otherwise governed by the Fort Lupton Municipal Code (Municode Chapter 16, Development Code), not a Building Division-specific ADU page. If your project isn't listed, confirm with City of Fort Lupton Planning & Building Department (Building Division) at 720-928-4003 before starting work.

In Fort Lupton, the published Building Permit Fee (general valuation-based schedule) is: $24.00 minimum, scaling per the valuation tiers in Resolution No. 2026R020. Additional published fees: Plan Review Fee — 65% of Building Permit Fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Fort Lupton's published plan-review target for an accessory dwelling unit (adu) permit is 7–10 business days.

You'll need: Residential Building Permit Application — ADU scope; Plot Plan / Site Plan. See the required-documents checklist on this page for details on each.

Fort Lupton requires 4 inspection(s) for an accessory dwelling unit (adu) permit, in order: Foundation, Framing, Rough Electrical / Plumbing / Mechanical, Final Inspection. Schedule each through City of Fort Lupton Planning & Building Department (Building Division) (720-928-4003).

Apply through City of Fort Lupton Planning & Building Department (Building Division) at 1200 Dexter Street, Unit W13, Fort Lupton, CO 80621 (mailing: 130 S McKinley Ave, Fort Lupton, CO 80621). Phone: 720-928-4003, email: buildingdept@fortluptonco.gov. Office hours: Not published on the Building Department page as of this review. Key staff direct lines: Jonathan Gesick (Building Official, SAFEbuilt contract) 970-518-5269 jgesick@safebuilt.com; Jose Gonzalez (Building Official II, ProCode Inc. contract) 970-305-3161 jgonzalez@procodeinc.net (also reachable at coemail@safebuilt.com per the New Construction Requirements page); Shannon DeVries (Permit Technician I) 720-466-6104 buildingdept@fortluptonco.gov; Todd Hodges (Planning Director) 720-466-6106 thodges@fortluptonco.gov.. Official information: https://www.fortluptonco.gov/208/Building.

Fort Lupton, Colorado has adopted: 2024 International Building Code (IBC) — City of Fort Lupton, Current Adopted Codes & Additional Resources page, adopted by Ordinance No. 2026-1198 (approved by City Council January 20, 2026, effective after publication March 28, 2026), replacing the prior 2018 code cycle; 2024 International Residential Code (IRC); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC); 2024 International Fuel Gas Code (IFGC); 2024 International Fire Code (IFC); 2024 International Existing Building Code (IEBC); 2024 International Energy Conservation Code (IECC); 2024 International Property Maintenance Code; 2024 International Swimming Pool and Spa Code; 2023 National Electrical Code (NEC) — state-mandated edition per Colorado statute, referenced on the same Current Adopted Codes page; Colorado Model Electric Ready and Solar Ready Code, 2023 Edition — adopted by reference in the same Ordinance No. 2026-1198 (per Resolution No. 2026R020 recitals), enacting new municipal code sections rather than amending the I-Codes directly; Colorado Wildfire Resiliency Code, 2025 Edition — likewise adopted by reference in Ordinance No. 2026-1198, effective March 28, 2026; Note on prior-cycle residue: a ProCode Inc.-branded 'Residential Energy Compliance Certificate' template still in departmental circulation references the superseded '2012/2018 IECC (Res) as amended' baseline for duct-leakage (R403.3.3) and building-envelope (R402.1.2) testing language; the live Current Adopted Codes webpage and Resolution No. 2026R020 recitals (Ordinance 2026-1198, 2024 I-Codes) are treated as the current, governing adoption for this file since they are the actively maintained code-adoption authority, not a legacy form that has not yet been reprinted.. Local amendments apply — see the Fort Lupton overview page for the full list.

There is no distinct ADU permit application or fee line — ADUs are processed under the general residential building-permit submittal requirements. However, Fort Lupton DOES have a detailed, codified ADU-specific zoning standard (Municipal Code Sec. 16-4.03(2)), covering a required Pre-Application Meeting, a one-ADU-per-lot limit tied to a detached house or duplex/multi-unit house, size caps by lot size, a 35' height limit, setbacks, design-compatibility rules, and access/addressing requirements.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fort Lupton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.