Solar Photovoltaic (PV) Permit in Plummer, Idaho
Required for rooftop or ground-mounted solar photovoltaic installation within Plummer city limits. The City of Plummer follows Benewah County's building fee schedule (the County currently provides the City's building inspector), plus the City's own 25% surcharge on top of the County's amounts. The Plummer Rate Book (March 2026) has no dedicated solar/PV fee line, so the array/mounting/structural scope is billed under the general 1997 Uniform Building Code valuation table. The full March 2026 Rate Book (15 pages, re-checked in full 2026-07-20) has no electrical PERMIT fee section anywhere — only municipal electric UTILITY service rates (kWh usage, connection fees) appear, and there is no building-inspection-bundled electrical line item either. Consistent with the pattern documented at other small Idaho cities in this corpus with no local electrical-permitting program (e.g., Kellogg, Rathdrum), electrical interconnection work for a Plummer solar PV project is understood to fall under the statewide Idaho DOPL Electrical Board framework (IDAPA 24.39.10), which does publish a current, citable fee schedule.
Verified 2026-07-20 · Source
When you need this permit
- Building Permit required from the City of Plummer Planning, Zoning & Building Department for the array mounting/structural scope, priced per Benewah County's building valuation table plus the City's 25% surcharge
- Electrical permit for the PV wiring/interconnection scope: confirmed 2026-07-20 that the City of Plummer's full Rate Book has no electrical PERMIT fee line (only municipal electric utility service rates), consistent with no local electrical-permitting program — the electrical scope falls under the statewide Idaho DOPL Electrical Board framework (IDAPA 24.39.10); confirm directly with City Hall (208-686-1641) since this was not stated in writing by the City itself
- No dedicated Solar Permit Application or expedited solar-specific review track is published by the City of Plummer as of 2026-07-19
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Plummer inspection guide — scheduling & re-inspection fees →
Tips
- Plummer's Rate Book has no dedicated solar/PV fee line — the array/structural scope is billed under the same 1997 Uniform Building Code valuation table (plus the City's 25% surcharge) used for any other construction, since Benewah County currently provides the City's building inspector.
- Unlike the Building Permits section, the Rate Book has no electrical permit fee line item at all anywhere in its 15 pages (only municipal electric utility service rates) — the electrical interconnection scope for a Plummer solar project is understood to fall under Idaho DOPL's statewide fee schedule (IDAPA 24.39.10, Rule 500.02.b: $60 plus 2% of wiring cost up to $10,000), consistent with the pattern at other small Idaho cities with no local electrical program; confirm directly with City Hall.
- The City of Plummer operates its own municipal electric UTILITY (distinct from building/electrical PERMITTING) — a $150.00 estimate fee and connection-fee-at-cost-plus-12% apply to new electric SERVICE connections, but this is a utility hookup process, not a code-compliance permit, and should not be confused with the PV interconnection permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Plummer building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Plummer
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Idaho →