Installing an EV charger in Shelley is electrical work, and since the City of Shelley does not issue its own electrical permits (electrical, plumbing, and HVAC permits are obtained separately through the State of Idaho Division of Occupational and Professional Licenses (DOPL) / Division of Building Safety, not the City -- the same routing already documented on this file's solar-pv-permit entry), the EV charging circuit is permitted directly by DOPL. DOPL's Electrical Permit Worksheet (Fee Schedule) has no dedicated 'EV charger' or 'EVSE' line item (unlike its explicit Solar/Renewable Energy formula); a new EV charger branch circuit added to an existing residence falls under the worksheet's general 'Existing Residence' fee category. A City of Shelley Building Permit is required in addition only if the installation includes new structural work (e.g., a carport or garage built to house the charger), billed under the City's general valuation-based Building Permit Fee Schedule, the same mechanism documented for solar's structural/roof-mount scope.

Verified 2026-07-20 · Source

When you need this permit

  • The EV charger circuit itself must be permitted through the State of Idaho DOPL (purchased online at dbs.idaho.gov, redirecting to dopl.idaho.gov) -- not through the City of Shelley Building & Safety Department, which does not issue electrical permits
  • On the DOPL Electrical Permit Worksheet, a new EV charger branch circuit at an existing residence falls under the 'Existing Residence / Modular, Manufactured or Mobile Homes / Detached Shop' category: $65 base fee plus $10 per additional branch circuit beyond the first (one circuit is included in the $65 base)
  • Homeowner permits are limited to work personally performed by the property owner on a primary or secondary residence not rented or used commercially; contractor-installed work uses the standard DOPL contractor electrical permit process instead
  • A City of Shelley Building Permit is required only if new structural work (e.g., a carport or garage) is built to house the charger, per the City's general valuation-based Building Permit Fee Schedule

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

State of Idaho DOPL Electrical Permit — Existing Residence (new branch circuit)DOPL Electrical Permit Worksheet (Fee Schedule) -- applies to a new EV charger circuit added to an existing residence; the worksheet has no dedicated EV-charger or EVSE line item, so this general 'Existing Residence' new-branch-circuit category is the applicable fee bucket, consistent with the worksheet's own instruction that its 'Other Installations' catch-all applies only to work 'not specifically mentioned elsewhere on this form' -- a new circuit at an existing home IS specifically covered by this Existing Residence line
$65.00 base fee (includes 1 circuit), plus $10.00 per additional branch circuit
City Building Permit — valuation $1.00 to $500.00 (only if new structure, e.g. carport/garage, is built to house the charger)City of Shelley Building Permit Fee Schedule -- applies only when new structural work is involved; a standalone wall/pedestal charger with no new structure does not require this
$21.00

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / Electric Vehicle Charging Station Permit permit actually take in Shelley?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    DOPL Electrical Inspection

    New circuit wiring, breaker, and disconnect verified, performed under the state-issued Electrical Permit

See the full Shelley inspection guide — scheduling & re-inspection fees →

Tips

  • Do not contact the City of Shelley Building & Safety Department to obtain the EV charger electrical permit -- electrical work anywhere in Shelley is permitted directly by DOPL, purchased online at dbs.idaho.gov.
  • A single new EV charger circuit at an existing home fits DOPL's 'Existing Residence' category: $65 base fee (which includes the first branch circuit), so a straightforward single-circuit EV charger install is typically just the $65 base fee.
  • Unlike solar (which gets an explicit percentage-of-cost formula on the DOPL worksheet), EV chargers have no dedicated line item -- they're billed as an ordinary new branch circuit under the Existing Residence category.

Frequently asked questions

Shelley requires an ev charger / electric vehicle charging station permit for: The EV charger circuit itself must be permitted through the State of Idaho DOPL (purchased online at dbs.idaho.gov, redirecting to dopl.idaho.gov) -- not through the City of Shelley Building & Safety Department, which does not issue electrical permits; On the DOPL Electrical Permit Worksheet, a new EV charger branch circuit at an existing residence falls under the 'Existing Residence / Modular, Manufactured or Mobile Homes / Detached Shop' category: $65 base fee plus $10 per additional branch circuit beyond the first (one circuit is included in the $65 base); Homeowner permits are limited to work personally performed by the property owner on a primary or secondary residence not rented or used commercially; contractor-installed work uses the standard DOPL contractor electrical permit process instead; A City of Shelley Building Permit is required only if new structural work (e.g., a carport or garage) is built to house the charger, per the City's general valuation-based Building Permit Fee Schedule. If your project isn't listed, confirm with City of Shelley Building & Safety Department at (208) 681-3391 before starting work.

No. Unlike its explicit percentage-of-cost formula for Solar/Renewable Energy installations, the DOPL Electrical Permit Worksheet has no dedicated EV-charger or EVSE line item. A new EV charger circuit added to an existing residence is billed under the general 'Existing Residence' category: $65 base fee (includes one branch circuit) plus $10 per additional circuit.

Shelley does not publish a plan-review timeline for this permit. Contact City of Shelley Building & Safety Department at (208) 681-3391 for current turnaround.

You'll need: DOPL Homeowner or Contractor Electrical Permit Application and Worksheet. Depending on your project, Shelley may also ask for: City of Shelley Building Permit Application (only if new structure is built). See the required-documents checklist on this page for details on each.

Shelley requires 1 inspection(s) for an ev charger / electric vehicle charging station permit, in order: DOPL Electrical Inspection. Schedule each through City of Shelley Building & Safety Department ((208) 681-3391).

Apply through City of Shelley Building & Safety Department at 155 E. Pine Street, Shelley, ID 83274. Phone: (208) 681-3391. Office hours: Building Inspector's Office: Monday–Thursday 7:00 a.m. – 5:30 p.m. (City Hall administrative offices: Mon–Thu 8:00 a.m.–5:30 p.m., Fri 8:00 a.m.–noon). Official information: https://cityofshelley.org/city-departments/building-safety-department/.

Shelley, Idaho has adopted: City Code Title 7, Chapter 1 (Uniform Building Code) still codifies the Uniform Building Code, 1991 Edition, published by the International Conference of Building Officials, 'and such later supplements and additions as may hereafter be published' (Title 7-1-1) — this is the codified text on file with the City Clerk; The City of Shelley Building & Safety Department's official department webpage states the department currently administers and enforces the 2018 International Residential Code (IRC) and 2018 International Building Code (IBC), with local amendments; contact the department directly for the specific amendment list, as the department page notes without itemizing each amendment beyond the published Design Loads Table; City of Shelley Design Loads Table R301.2(1) (department-published amendment document) sets Idaho Building Code Board-style climatic/geographic design criteria for the city; City Code Title 7, Chapter 2 — Uniform Code for the Abatement of Dangerous Buildings, Chapters 4 through 7, 1979 Edition (unsafe/dangerous building abatement, separate from routine demolition permits); City Code Title 7, Chapter 4 — Uniform Fire Code (enforcement excluded from the Planning and Building Division's duties per Title 3-8-2(A); administered separately); City Code Title 7, Chapter 5 — Uniform Sign Code; City Code Title 7, Chapter 6 — Electrical Code (administered by the State of Idaho, not the City, per the Building & Safety Department page); City Code Title 7, Chapter 7 — Plumbing Code (administered by the State of Idaho, not the City); City Code Title 7, Chapter 8 — Uniform Mechanical Code (HVAC administered by the State of Idaho, not the City); City Code Title 7, Chapter 9 — Americans with Disabilities Act provisions; Electrical, plumbing, and HVAC permits and inspections in Shelley are obtained through the State of Idaho Division of Occupational and Professional Licenses (DOPL) / Division of Building Safety, not the City — confirmed on both the Building & Safety Department webpage and the New Construction Packet (DOPL contact: 208-334-3233). Local amendments apply — see the Shelley overview page for the full list.

The electrical work itself is permitted directly through the State of Idaho DOPL (dbs.idaho.gov), not the City of Shelley, since the City does not issue electrical permits. A City building permit is only needed in addition if new structural work (like a carport or garage) is built to house the charger.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Shelley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Compare ev charger / electric vehicle charging station permit fees across Idaho

Look up this fee in a different city →

Embed this data card →

Related guides

Now live

Build your Shelley project checklist

Describe your project once and get every permit, document, and fee it triggers in Shelley — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.

Get started →