Required for installation of rooftop or ground-mounted solar photovoltaic systems within Melba city limits. The structural/racking scope is permitted by the City of Melba's own Building Department under Melba City Code §9-2-1 (the same unpublished Exhibit A fee-schedule process used for other construction); the electrical interconnection is separately permitted and inspected by the State of Idaho Division of Occupational and Professional Licenses (DOPL), since Melba's own self-administered permitting program covers Building and Mechanical work but no electrical-permit application or fee schedule is published by the City.

Verified 2026-07-20 · Source

When you need this permit

  • Structural/racking mounting work requires a City of Melba Building Permit Application under City Code §9-2-1(A), including two plot plans and two complete sets of plans/specifications
  • Electrical interconnection (wiring, inverter, grid tie-in) requires a separate State of Idaho electrical permit issued by DOPL, not the City — Melba publishes no electrical-permit application or fee schedule of its own, unlike its published Building and Mechanical permit forms
  • Grid-connected renewable energy systems require a State plan-check permit number prior to purchasing the State electrical installation permit, per DOPL's own homeowner electrical permit process
  • Contractor Registration Number required on the City Building Permit Application Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

City Building Permit Fee (structural/racking scope)Unpublished — the Building Permit Application itself leaves the 'Permit Fee' line blank/hand-filled, and Melba City Code §9-2-1(B) states the fee schedule is on file with the City as Exhibit A, not published online, consistent with the general residential-building-permit entry in this file. Contact City Hall at (208) 495-2722 for the current Exhibit A valuation table.
Not published — contact the department
State of Idaho Electrical Permit — grid-connected renewable energy (electrical/interconnection scope)Idaho DOPL Electrical Permit Worksheet (Homeowner), 'Other Installations including Solar/Renewable Energy' table, revised 8/17/2022 — the same statewide fee formula documented for other Idaho jurisdictions in this corpus (e.g., Ketchum, Malad) that publish no electrical-permit fee schedule of their own. Grid-connected systems additionally require a State plan-check permit number before the installation permit can be purchased.
Up to $10,000 system cost: (cost x 0.02) + $60. $10,001-$100,000: ((cost - $10,000) x 0.01) + $260. Over $100,001: ((cost - $100,000) x 0.005) + $1,160

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Melba?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footings (if new foundation/racking piers)

    Before concrete pour, consistent with the City's general Footings inspection practice

  2. 2

    Framing/Structural

    Racking and roof-penetration/structural attachment inspection

  3. 3

    Electrical Inspection (State of Idaho)

    Wiring, inverter, and interconnection inspected by DOPL's assigned state trade inspector

  4. 4

    Final

    Final City inspection of the completed structural/racking work

See the full Melba inspection guide — scheduling & re-inspection fees →

Tips

  • Two separate permits and two separate agencies are involved: the City of Melba handles the structural/racking mounting permit under City Code §9-2-1 (fee unpublished, call 208-495-2722 for a quote); the State of Idaho DOPL handles the electrical interconnection permit (cost-based formula).
  • Grid-connected renewable energy systems must obtain a State plan-check permit number before purchasing the state electrical installation permit — contact DOPL at 1-800-955-3044.
  • As with all other Melba building permits, plan on two plot plans and two complete sets of plans/specifications for the structural/racking permit application.

Frequently asked questions

Melba requires a solar pv permit for: Structural/racking mounting work requires a City of Melba Building Permit Application under City Code §9-2-1(A), including two plot plans and two complete sets of plans/specifications; Electrical interconnection (wiring, inverter, grid tie-in) requires a separate State of Idaho electrical permit issued by DOPL, not the City — Melba publishes no electrical-permit application or fee schedule of its own, unlike its published Building and Mechanical permit forms; Grid-connected renewable energy systems require a State plan-check permit number prior to purchasing the State electrical installation permit, per DOPL's own homeowner electrical permit process; Contractor Registration Number required on the City Building Permit Application. If your project isn't listed, confirm with City of Melba — Building Department (Development Services) at (208) 495-2722 before starting work.

Melba does not publish a plan-review timeline for this permit. Contact City of Melba — Building Department (Development Services) at (208) 495-2722 for current turnaround.

You'll need: Melba Building Permit Application; Plot Plans (2 copies, drawn to scale); State of Idaho Electrical Permit Application (Homeowner or Contractor). See the required-documents checklist on this page for details on each.

Melba requires 4 inspection(s) for a solar pv permit, in order: Footings (if new foundation/racking piers), Framing/Structural, Electrical Inspection (State of Idaho), Final. Schedule each through City of Melba — Building Department (Development Services) ((208) 495-2722).

Apply through City of Melba — Building Department (Development Services) at 401 Carrie Rex Ave, PO Box 209, Melba, ID 83641. Phone: (208) 495-2722, email: cityclerk@cityofmelba.org. Office hours: Monday – Friday 8:00 AM – 12:00 Noon and 1:00 PM – 3:00 PM. Official information: https://cityofmelba.org/planning-zoning/.

Melba, Idaho has adopted: 2018 International Building Code (IBC), with Idaho amendments — Melba City Code §9-2-1 adopts "the International Building Code" by reference and binds the Building Department to it and State laws pertaining to buildings; Idaho Code §39-4116 requires local building-permit-issuing jurisdictions to enforce the edition currently adopted by the Idaho Building Code Board, which is the 2018 IBC (per DOPL's 2025 Updated Idaho Adopted Codes notice); 2018 International Residential Code (IRC), Parts I, II, III, and IX — Idaho Residential Code (2020 Edition amendments), statewide baseline applicable in Melba absent a more specific local amendment; 2018 International Energy Conservation Code (IECC) — Idaho Energy Conservation Code (2020 Edition amendments); 2018 International Existing Building Code (IEBC); 2018 International Mechanical Code (IMC) and 2018 International Fuel Gas Code (IFGC) — statewide baseline; Melba additionally requires its own separate Mechanical Permit (with published flat fees) per city practice; 2017 Idaho State Plumbing Code (based on the 2015 Uniform Plumbing Code); 2023 National Electrical Code (NEC), with Idaho amendments; Melba City Code Title 9, Chapter 2 ("General Building Regulations"), §9-2-1 (Building Permits and Fees) and §9-2-2 (Fences). Local amendments apply — see the Melba overview page for the full list.

The State of Idaho Division of Occupational and Professional Licenses (DOPL), not the City of Melba — the City publishes no electrical-permit application or fee schedule of its own. The City of Melba separately issues the structural/racking building permit under Melba City Code §9-2-1.

The City's structural/racking building permit fee is unpublished (on file with the City as Exhibit A, not posted online — call 208-495-2722 for a quote). The State electrical permit follows Idaho DOPL's statewide formula for grid-connected renewable energy systems: 2% of system cost up to $10,000 plus a $60 base fee, scaling down to 0.5% above $100,000 plus a $1,160 base fee.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Melba building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.