Residential Building Permit (New Dwelling / Addition / Remodel) in Melba, Idaho

Required for new single-family dwellings, residential additions/remodels, and detached structures within Melba city limits. Issued by the City of Melba's own Building Department under Melba City Code §9-2-1; the City contracts with outside inspection professionals to perform plan review and inspections, but the permit and its legal authority are the City's, not Canyon County's. This same application form and process — not a separate product — is also how Melba permits new commercial construction, commercial additions/remodels, and tenant improvements to existing commercial space; the City has no distinctly-named Commercial Building Permit or Tenant Improvement permit (see localAmendments and tipsAndGotchas for full sourcing on this finding).

Reviewed 2026-08-02 · Source

When you need this permit

  • Building permit required before starting construction, per Melba City Code §9-2-1(A)
  • Two (2) plot plans drawn to scale showing proposed work
  • Two (2) complete sets of plans and specifications (one set is returned to applicant)
  • A copy of the full legal description (recorded) or Subdivision, Lot & Block of property
  • Contractor Registration Number required on the application Contractor
  • Zoning classification must be identified on the application
  • Mechanical permits are required separately through the City of Melba, with a copy of the Manual J calculation kept on site
  • Commercial new construction, commercial additions and remodels, and interior tenant improvements to existing commercial space all use this same Building Permit Application and the same process — Melba publishes no separate commercial application, no commercial fee schedule, and no design-review or site-plan-review step. The Melba City Code bears this out: Title 9 (Building Regulations) contains only Chapter 1 (Building Codes) and Chapter 2 (General Building Regulations, §9-2-1 and §9-2-2), and Title 10 (Zoning Regulations) — General Provisions, Definitions, Residential Zones, Mixed Use Zones, Commercial and Industrial Zones, Planned Unit Developments, Supplementary Regulations, Manufactured Housing, Amendment Procedure, Conditional Use Permit Procedure, Variance Procedure — contains no Design Review or Site Plan Review chapter.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee
Melba does not publish its Exhibit A valuation table online. Show full citationMelba does not publish its Exhibit A valuation table online. City Code §9-2-1(B) says only that 'the building permit fee schedule is on file with the City as exhibit A and made a part hereof' (Ord. 147, 1-19-1994; amd. Ord. 258, 7-9-2018), with no table included. No fee-schedule PDF appears in the City's Historical Documents / Development Services 'Documents & Permits' library, and the City's pre-August-2020 minutes host (gbm.wef.mybluehost.me) is dead (404) with no web-archive captures of those files, so the record of the 7/9/2018 meeting that adopted Ord. 258 is unavailable. A 2021 'Notice of Proposed Fee Increase' PDF is likewise no longer available on the live site. No fee figure is shown here because none is published. Contact City Hall at (208) 495-2722 for the current Exhibit A valuation table.
Unpublished — the Building Permit Application leaves the "Permit Fee" line blank for hand-filling, and Melba City Code §9-2-1(B) states the fee schedule is on file with the City as Exhibit A. That Exhibit A fee schedule does not appear on the City's website, its linked Google Drive document library, Municode or AmLegal codification, or in archived captures of cityofmelba.org.
Plan Review Fee
Not found in any published source as of verification. Show full citationNot found in any published source as of verification. New chase 2026-07-23: same unpublished Exhibit A document as the Building Permit Fee line above — the live ordinance text, City document library, and full 2017-2025 council-minutes archive were all re-checked (pre-2020 minutes host now entirely dead, no Wayback captures); still unrecoverable without a direct call to City Hall.
Unpublished — same as Building Permit Fee; line is blank on the City's own application form
Water Hookup FeePublished directly on the City of Melba Building Permit Application form (fixed amount, not valuation-based)
$1,800.00
Sewer Hookup FeePublished directly on the City of Melba Building Permit Application form (fixed amount, not valuation-based)
$4,500.00

Review timeline

Plan review
Not published — contact the department

How long did your Residential Building Permit (New Dwelling / Addition / Remodel) permit actually take in Melba?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footings

    Before concrete pour

  2. 2

    Floor Framing

  3. 3

    Shear 1 – Nailing

  4. 4

    Shear 2 – House Wrap, Windows, and Flashing

  5. 5

    Framing

  6. 6

    Insulation

  7. 7

    Final

See the full Melba inspection guide — scheduling & re-inspection fees →

Tips

  • Melba is NOT served by Canyon County's Development Services Department for building permits — Melba operates its own Building Department under City Code Title 9. Do not confuse this with unincorporated Canyon County's process.
  • Melba's own Planning & Zoning page states the City "contracts with outside planning, engineering, and building inspection professionals" — this means labor is outsourced to contracted individuals/firms, not that legal authority transfers to the County.
  • All inspections are completed after 5:00 PM or on weekends and require 24-48 hour notice — call the inspection contact listed on the current application (Chuck Pavelka, 208-249-4244, on the Building Permit Application; 208-724-0433 on the Mechanical Permit applications).
  • Water hookup ($1,800) and sewer hookup ($4,500) fees are fixed, published amounts — budget for these in addition to the (unpublished) building permit and plan review fees.
  • Mechanical permits are separate from the building permit and required directly through the City of Melba — bring or reference a Manual J calculation.
  • The exact building-permit valuation fee table (Exhibit A) is not published online; call City Hall to obtain current pricing before budgeting for a project.

Frequently asked questions

Melba requires a residential building permit (new dwelling / addition / remodel) for: Building permit required before starting construction, per Melba City Code §9-2-1(A); Two (2) plot plans drawn to scale showing proposed work; Two (2) complete sets of plans and specifications (one set is returned to applicant); A copy of the full legal description (recorded) or Subdivision, Lot & Block of property; Contractor Registration Number required on the application; Zoning classification must be identified on the application; Mechanical permits are required separately through the City of Melba, with a copy of the Manual J calculation kept on site; Commercial new construction, commercial additions and remodels, and interior tenant improvements to existing commercial space all use this same Building Permit Application and the same process — Melba publishes no separate commercial application, no commercial fee schedule, and no design-review or site-plan-review step. The Melba City Code bears this out: Title 9 (Building Regulations) contains only Chapter 1 (Building Codes) and Chapter 2 (General Building Regulations, §9-2-1 and §9-2-2), and Title 10 (Zoning Regulations) — General Provisions, Definitions, Residential Zones, Mixed Use Zones, Commercial and Industrial Zones, Planned Unit Developments, Supplementary Regulations, Manufactured Housing, Amendment Procedure, Conditional Use Permit Procedure, Variance Procedure — contains no Design Review or Site Plan Review chapter.. If your project isn't listed, confirm with City of Melba — Building Department (Development Services) at (208) 495-2722 before starting work.

The exact building permit fee is set by a fee schedule (Exhibit A) that is on file with the City under Melba City Code §9-2-1(B), but is not published online. The City's own Building Permit Application form leaves the Permit Fee and Plan Review Fee lines blank for staff to fill in. Water and sewer hookup fees are published and fixed at $1,800 and $4,500 respectively. Contact Melba City Hall at (208) 495-2722 for current permit and plan review pricing.

Melba does not publish a plan-review timeline for this permit. Contact City of Melba — Building Department (Development Services) at (208) 495-2722 for current turnaround.

You'll need: Melba Building Permit Application; Plot Plans (2 copies, drawn to scale); Construction Plans and Specifications (2 complete sets); Legal Description or Subdivision/Lot/Block Documentation. See the required-documents checklist on this page for details on each.

Per the City's current Building Permit Application, contact Chuck Pavelka at (208) 249-4244. Inspections are completed after 5:00 PM or on weekends, and 24-48 hours notice is required.

Apply through City of Melba — Building Department (Development Services) at 401 Carrie Rex Ave, PO Box 209, Melba, ID 83641. Phone: (208) 495-2722, email: cityclerk@cityofmelba.org. Office hours: Monday – Friday 8:00 AM – 12:00 Noon and 1:00 PM – 3:00 PM. Official information: https://cityofmelba.org/planning-zoning/.

Melba, Idaho has adopted: 2018 International Building Code (IBC), with Idaho amendments — Melba City Code §9-2-1 adopts "the International Building Code" by reference and binds the Building Department to it and State laws pertaining to buildings; Idaho Code §39-4116 requires local building-permit-issuing jurisdictions to enforce the edition currently adopted by the Idaho Building Code Board, which is the 2018 IBC (per DOPL's 2025 Updated Idaho Adopted Codes notice); 2018 International Residential Code (IRC), Parts I, II, III, and IX — Idaho Residential Code (2020 Edition amendments), statewide baseline applicable in Melba absent a more specific local amendment; 2018 International Energy Conservation Code (IECC) — Idaho Energy Conservation Code (2020 Edition amendments); 2018 International Existing Building Code (IEBC); 2018 International Mechanical Code (IMC) and 2018 International Fuel Gas Code (IFGC) — statewide baseline; Melba additionally requires its own separate Mechanical Permit (with published flat fees) per city practice; 2017 Idaho State Plumbing Code (based on the 2015 Uniform Plumbing Code); 2023 National Electrical Code (NEC), with Idaho amendments; Melba City Code Title 9, Chapter 2 ("General Building Regulations"), §9-2-1 (Building Permits and Fees) and §9-2-2 (Fences). Local amendments apply — see the Melba overview page for the full list.

Melba has its own independent Building Department, codified at Melba City Code Title 9, Chapter 2, §9-2-1. The City contracts with outside inspection and engineering professionals to perform the work, but the permit itself, its fee, and its legal authority belong to the City of Melba — not Canyon County. Canyon County's Development Services Department handles building permits only for unincorporated Canyon County land outside Melba's city limits.

Property Access

Melba's permit history is searchable by address

108 permits on record for Melba, 2016–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.

Start your 7-day free trial7 days free for new customers, then $79/mo · the guide above stays free