How to schedule

Inspections are requested through the building department below.

Address
500 12th Ave South, Nampa, ID 83651
Phone
(208) 468-5435
Office hours
Mon–Fri 8:00 AM – 5:00 PM

Published scheduling rules

  • All inspections must be requested through CSS before 12:00 AM the prior day for next-business-day scheduling. (Residential Building Permit (New Construction))
  • Schedule inspections through the CSS portal before 12:00 AM the prior day. Inspection line: (208) 468-5404. (Residential Electrical Permit)
  • All inspections must be requested through the CSS portal before 12:00 AM the prior business day. AM/PM slots are available only for footing, foundation, masonry grout, and open trench inspections. (General)
  • Inspection line: (208) 468-5404. Fire inspection line: (208) 468-5770. Nampa has a zone system for underfloor/concrete inspections — zones 1 and 3 are AM, zones 2 and 4 are PM. (General)

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation / Footings

    Before concrete pour — verify depth (24-inch frost line for full foundations), forms, rebar

  2. 2

    Framing

    Structural framing, egress windows, fire separation before walls covered

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-ins under separate trade permits

  4. 4

    Final

    All work complete, smoke/CO detectors, address posted; Certificate of Occupancy issued

Applies to: Residential Addition / Remodel Permit

  1. 1

    Framing / Structural

    After framing complete, before walls covered — verify structure, connections, blocking, egress

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-ins before wall cover — may require separate trade permits

  3. 3

    Insulation

    Insulation and vapor barrier before drywall (if conditioned space added)

  4. 4

    Final

    All work complete per approved plans; Certificate of Completion issued

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing / Foundation

    Before concrete pour — forms, rebar, anchor bolts; AM inspection available; city divided into four zones for underfloor/concrete inspections

  2. 2

    Framing

    After framing, sheathing, and rough-in trades complete — before insulation or wall cover

  3. 3

    Insulation / Energy

    Insulation installed per 2018 IECC before drywall

  4. 4

    Final

    All work complete per approved plans; Certificate of Occupancy issued upon passing

Applies to: Residential Mechanical / HVAC Permit

  1. 1

    Gas Piping Pressure Test

    Required before concealing gas piping — verify no leaks under test pressure

  2. 2

    Rough-In / Equipment

    HVAC equipment, ductwork, and gas lines rough-in before walls closed

  3. 3

    Final

    Equipment operational, combustion air verified, venting correct, controls functional

Applies to: Residential Plumbing Permit

  1. 1

    Underground / Slab Plumbing

    Before concrete pour — verify pipe slope, materials, cleanouts; AM inspection available in applicable zones

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Residential Pool Permit

  1. 1

    Excavation / Pre-Pour

    Verify pool shell dimensions, rebar, bonding grid before gunite or concrete

  2. 2

    Plumbing / Electrical Rough-In

    Verify pump, filter, bonding, and GFCI protection before backfill

  3. 3

    Final

    Completed pool with required fencing, bonding complete, equipment operational

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final — Building / Structural

    Panel mounting, racking attachment, roof penetration sealing verified

  3. 3

    Final — Electrical

    Electrical connections, inverter installation, and interconnection verified

Applies to: Accessory Structure Permit

  1. 1

    Foundation / Footings

    Accessory structures under 600 sq ft require minimum 12-inch depth on 12-inch wide footing (not full 24-inch frost depth). Larger structures require full frost-depth footings.

  2. 2

    Final

    Structure complete per approved plans

Applies to: Electric Vehicle (EV) Charger Permit

  1. 1

    Rough-In / Temporary Service

    After wiring installed, before walls closed — verify conductor sizing, box placement, and service connections

  2. 2

    Final

    EV charger circuit, GFCI/AFCI protection, and connections verified per 2023 NEC

Applies to: Residential Electrical Permit

  1. 1

    Rough-In / Temporary Service

    After wiring installed, before walls closed — verify conductor sizing, box placement, and service connections

  2. 2

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified per 2023 NEC

Re-inspection fees

Residential Building Permit (New Construction)Reinspection (after first reinspection for same item)
$55.00 flat fee
Residential Addition / Remodel PermitReinspection (after first reinspection for same item)
$55.00 flat fee
Residential Electrical PermitReinspection (after first reinspection for same item)
$55.00 flat fee
Residential Plumbing PermitReinspection (after first reinspection for same item)
$55.00 flat fee
Residential Mechanical / HVAC PermitReinspection (after first reinspection for same item)
$55.00 flat fee
Residential Roofing Permit (Re-roof)Reinspection (after first reinspection for same item)
$55.00 flat fee
Solar Photovoltaic (PV) PermitReinspection (after first reinspection for same item)
$55.00 flat fee
Accessory Dwelling Unit (ADU) PermitReinspection (after first reinspection for same item)
$55.00 flat fee
Accessory Structure PermitReinspection (after first reinspection for same item)
$55.00 flat fee
Residential Pool PermitReinspection (after first reinspection for same item)
$55.00 flat fee

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nampa building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Nampa building permits

Get alerts for Nampa

We'll email you when Nampa's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.