Accessory Dwelling Unit (ADU) Permit in Nampa, Idaho
Required for construction of a new accessory dwelling unit on a residential property in Nampa. Nampa provides a dedicated ADU Building Permit Application & Checklist.
Verified 2026-06-29 · Source
When you need this permit
- Verify ADU is permitted in the property's zoning district with Planning & Zoning
- Submit Residential ADU Building Application & Checklist
- Plans must comply with 2018 IRC
- Trade sub-permits (electrical, plumbing, mechanical) required separately
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footings
Before concrete pour — verify depth (24-inch frost line for full foundations), forms, rebar
- 2
Framing
Structural framing, egress windows, fire separation before walls covered
- 3
MEP Rough-In
Mechanical, electrical, and plumbing rough-ins under separate trade permits
- 4
Final
All work complete, smoke/CO detectors, address posted; Certificate of Occupancy issued
See the full Nampa inspection guide — scheduling & re-inspection fees →
Tips
- Nampa's plan review target for ADUs is 15 working days per the published Plan Review Processing Time Frames (Aug 2024) — same as new residential.
- Confirm ADU zoning eligibility with Planning & Zoning at (208) 468-4430 before spending resources on design.
- Trade sub-permits (electrical, plumbing, mechanical) are required separately for ADU construction.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nampa building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Nampa
Accessory Dwelling Unit (ADU) Permit in other cities
Compare accessory dwelling unit (adu) permit fees across Idaho →
Look up this fee in a different city →
Related guides
Now live
Build your Nampa project checklist
Describe your project once and get every permit, document, and fee it triggers in Nampa — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →