Commercial Tenant Improvement (TI) Permit — Nampa, Idaho · Requirements sheet
Verified 2026-08-02 · Source: https://www.cityofnampa.us/1378/Commercial-FAQ
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Improvement (TI) Permit in Nampa, Idaho
Required for finishing or remodeling an existing commercial building or tenant lease space in Nampa, and for any change of occupancy classification. Nampa issues four related products depending on the scenario: a Tenant Improvement permit ending in a Certificate of Completion (no new tenant), a Tenant Improvement (Occupancy Only) permit for a new shell/complete building with a tenant already designated, a Tenant Improvement permit ending in a Certificate of Occupancy (new tenant or occupancy-classification change), and a construction-free Certificate of Occupancy Only application for a like-for-like change of tenant or owner with no occupancy-classification change.
Verified 2026-08-02 · Source
When you need this permit
- A TI permit is required for tenant improvements, including finishing or remodeling of an existing building or tenant space, per Nampa's Commercial FAQ
- A TI permit is also required for any Change of Occupancy for an existing commercial building or tenant space, even without significant remodeling
- Per Nampa's Commercial FAQ, changes to or within certain use categories always require a TI permit due to differing code requirements: hospitals, medical or dental offices, custodial care and halfway houses, daycares, schools, hair salons, barbershops, restaurants, assembly uses, and storage or factory uses
- A simple change of tenant or building owner with no change in occupancy classification and no remodeling may instead use a Certificate of Occupancy Only application in place of a full TI permit (the FAQ's own example: a law office converting to an accounting office)
- Obtain any necessary entitlements for the specific tenant use from Planning & Zoning — they determine whether the use is allowed or requires a Conditional Use Permit — before or at submittal
- Tenant identity, specific use, and occupancy classification must be provided at the time of TI application
- A registered building contractor or the building owner may apply; licensed Mechanical, Electrical, and Plumbing contractors must separately purchase their own trade permits for MEP work Owner-builder
- A separate sign permit, installed by an Idaho-registered contractor and obtained through Planning & Zoning, is required after the TI if new signage is planned Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Nampa Exhibit A — Commercial Project Subcontractor Scope of Work Valuation Table, quoted as printed (the source's own top-bracket label reads 'over $1,000,000' though the formula continues from the… Show full citationHide
Nampa Exhibit A — Commercial Project Subcontractor Scope of Work Valuation Table, quoted as printed (the source's own top-bracket label reads 'over $1,000,000' though the formula continues from the $100,000 breakpoint — reproduced as-is rather than silently corrected). Add the $36.00 base fee below.Review timeline
Inspection process
- 1
Rough MEP
Mechanical, electrical, and plumbing rough-in for the tenant space scope, before wall or ceiling cover
- 2
Fire / Life Safety
Fire sprinkler and/or fire alarm inspection and testing where the occupancy classification or scope of work requires it
- 3
Final
All work complete per approved plans; a Certificate of Completion (no tenant/owner change) or Certificate of Occupancy (new tenant or occupancy-classification change) is issued — the tenant is eligible to occupy the space only after the Certificate of Occupancy is received
See the full Nampa inspection guide — scheduling & re-inspection fees →
Tips
- Nampa's TI plan review timeline depends on which certificate you'll receive at the end: 10 working days for a Certificate of Completion or an Occupancy-Only TI, versus 15 working days for a Certificate of Occupancy, per the Aug 14, 2024 Plan Review Processing Time Frames.
- If you're only changing tenant or ownership with the same occupancy classification and no construction, ask about the Certificate of Occupancy Only application instead of a full TI permit — Nampa's own example is an office space changing from a law practice to an accounting practice.
- Certain use categories always require a TI permit for any change, even within the same broad occupancy group, because of stricter life-safety requirements: hospitals, medical/dental offices, custodial care/halfway houses, daycares, schools, hair salons, barbershops, restaurants, assembly, storage, and factory uses.
- A sign permit is a separate step from the TI permit — it's obtained through Planning & Zoning and must be installed by an Idaho-registered contractor. Contractor
- MEP work for a TI needs its own trade permits under the commercial percentage-of-valuation fee schedule (not the flat residential sub-trade fees), plus the $36 base fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nampa building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Nampa.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Property Access
Nampa's permit history is searchable by address
319,920 permits in our copy of Nampa's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything Nampa has issued.
All 319,920 carry an issued date, running from 1981 to 2026.
98% of Nampa's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.
Other permits in Nampa
Commercial Tenant Improvement (TI) Permit in other cities
Compare commercial tenant improvement (ti) permit fees across Idaho →
Look up this fee in a different city →
Related guides
Now live
Build your Nampa project checklist
Describe your project once and get every permit, document, and fee it triggers in Nampa — in one checklist. Free, for any city and any number of projects.
Get started →