Gem County does not regulate electrical work at all — installing a Level 2 or DC fast EV charger's dedicated circuit is handled entirely by the Idaho Division of Occupational and Professional Licenses (DOPL) / Idaho Electrical Board under the state's standard electrical permit process, the same as any other electrical installation in the county. No county building permit is triggered unless the installation involves new structural construction (e.g., a new carport or garage). The state process is documented at dopl.idaho.gov/ele/ele-permits-and-inspections/, and the current Idaho Electrical Board fee schedule (dopl.idaho.gov/wp-content/uploads/2022/06/Electrical-6.13.22.pdf, IDAPA 24.39.10, effective 6/13/2022) supplies the governing figures; DOPL's Homeowner Electrical Permit Application & Fee Worksheet (dopl.idaho.gov/wp-content/uploads/2023/11/ELE-Home-Owner-Electrical-Permit-Application.pdf) sets the alternative homeowner figure of $65 + $10/branch-circuit. Because Gem County administers no electrical permitting at all, these statewide DOPL/Electrical Board figures are the actual governing mechanism.

Reviewed 2026-07-20 · Source

When you need this permit

  • Idaho DOPL Electrical Permit required for the EV charger's dedicated circuit or service work, purchased online through DOPL's permitting portal — not through Gem County Development Services
  • A county Building Permit is required only if the EV charger installation is paired with new structural construction subject to the 2018 IRC/IBC as enforced under Gem County Code Title 9
  • Homeowners self-installing on their own primary residence may use DOPL's Homeowners Electrical permit path; contractors must hold a valid Idaho electrical contractor license Contractor
  • Service panel changes or upsizes required to accommodate the charger must be obtained under a separate DOPL electrical permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

DOPL Electrical Permit — 'Other Installations' fee schedule (contractor-pulled; no dedicated EV charger fee line)
IDAPA 24.39.10 (Rules of the Idaho Electrical Board), Section 500.02.b — statewide fee set by DOPL, not by Gem County. Show full citationIDAPA 24.39.10 (Rules of the Idaho Electrical Board), Section 500.02.b — statewide fee set by DOPL, not by Gem County. Tier i: wiring cost not exceeding $10,000 = $60 plus 2% of total wiring cost. Tier iv (Small work): work not exceeding $500 in cost and not involving a change in service connections = $10. Both read verbatim from the current rule text at adminrules.idaho.gov/rules/current/24/243910.pdf, all provisions stamped (3-28-23) — supersedes the 6/13/2022 edition previously cited here.
Wiring cost up to $10,000: $60 plus 2% of total wiring cost; work under $500 with no service change: $10
State Electrical Permit — Existing Dwelling UnitIDAPA 24.39.10 (Rules of the Idaho Electrical Board), Section 500.02.a.ii, effective 3-28-23: "Existing Dwelling Unit Permit: sixty-five dollars ($65) per inspection."
$65.00 per inspection

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Unincorporated Gem County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    DOPL Final Electrical Inspection

    Verifies conductor sizing, breaker/panel work, grounding, and EVSE equipment connection; conducted by a DOPL electrical inspector, not Gem County

See the full Unincorporated Gem County inspection guide — scheduling & re-inspection fees →

Tips

  • Gem County itself has no EV-charger-specific permit or fee — the county's Building Department does not regulate electrical work at all, so an EVSE circuit is effectively a state (DOPL) permit end-to-end.
  • If only adding a branch circuit with no service change, the DOPL Homeowners Electrical fee ($65 + $10/circuit) or the 'Other Installations' schedule (contractor-pulled, proportional to wiring cost) may apply — confirm which applies to your scope with DOPL (208-334-3233).
  • Gem County has no county-level electrical permitting, so these statewide DOPL figures are the actual governing mechanism for an EV charger circuit.

Frequently asked questions

Unincorporated Gem County requires an ev charger / evse permit for: Idaho DOPL Electrical Permit required for the EV charger's dedicated circuit or service work, purchased online through DOPL's permitting portal — not through Gem County Development Services; A county Building Permit is required only if the EV charger installation is paired with new structural construction subject to the 2018 IRC/IBC as enforced under Gem County Code Title 9; Homeowners self-installing on their own primary residence may use DOPL's Homeowners Electrical permit path; contractors must hold a valid Idaho electrical contractor license; Service panel changes or upsizes required to accommodate the charger must be obtained under a separate DOPL electrical permit. If your project isn't listed, confirm with Gem County Development Services — Building Department at 208-365-5144 before starting work.

In Unincorporated Gem County, the published DOPL Electrical Permit — 'Other Installations' fee schedule (contractor-pulled; no dedicated EV charger fee line) is: Wiring cost up to $10,000: $60 plus 2% of total wiring cost; work under $500 with no service change: $10. Additional published fees: State Electrical Permit — Existing Dwelling Unit — $65.00 per inspection. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Gem County does not publish a plan-review timeline for this permit. Contact Gem County Development Services — Building Department at 208-365-5144 for current turnaround.

You'll need: DOPL Electrical Permit (online). Depending on your project, Unincorporated Gem County may also ask for: Gem County Building Permit Application. See the required-documents checklist on this page for details on each.

Unincorporated Gem County requires 1 inspection(s) for an ev charger / evse permit, in order: DOPL Final Electrical Inspection. Schedule each through Gem County Development Services — Building Department (208-365-5144).

Apply through Gem County Development Services — Building Department at 109 S. McKinley Avenue, Emmett, ID 83617. Phone: 208-365-5144, email: gcbuild@co.gem.id.us. Office hours: Mon 8:00 AM–4:00 PM; Tue 8:00 AM–5:00 PM; Wed 9:00 AM–5:00 PM; Thu CLOSED (until further notice for Land Use Code update work); Fri 8:00 AM–5:00 PM. Effective January 5, 2026, office may close intermittently — call ahead.. Official information: https://gemcounty.org/departments_offices/development_services/index.php.

Unincorporated Gem County, Idaho has adopted: 2018 International Building Code (IBC) as adopted by the State of Idaho — enforced under Gem County Code (GCC) Title 9: Building Regulations; 2018 International Residential Code (IRC) — enforced under GCC Title 9; 2018 International Energy Conservation Code (IECC) — enforced under GCC Title 9; Gem County is in Climate Zone 13 per IRC (minimum insulation: ceilings R-38, walls R-21, floors R-30, basement walls R-19, crawl space walls R-20); Gem County Code Title 11: Zoning Regulations (setbacks, property-line requirements); Gem County Code Title 12: Subdivision Regulations; Gem County Code Title 13: Flood Control (Gem County Flood Control Ordinance). Local amendments apply — see the Unincorporated Gem County overview page for the full list.

No. Gem County Development Services does not regulate electrical work of any kind — an EV charger's dedicated circuit is handled entirely by the Idaho Division of Occupational and Professional Licenses (DOPL) / Idaho Electrical Board under the state's standard electrical permit process. A county Building Permit is only needed if the charger is installed as part of new structural construction. Source: Gem County Building FAQs and DOPL Electrical Permits and Inspections.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Gem County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Gem County's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Unincorporated Gem County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Unincorporated Gem County lands. Privacy.