Electric Vehicle (EV) Charging Station Permit — Spirit Lake, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://dopl.idaho.gov/ele/ele-permits-and-inspections/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charging Station Permit in Spirit Lake, Idaho
Installing a residential or commercial EV charging station (EVSE) in Spirit Lake requires an electrical permit. Since electrical work is NOT permitted by the City of Spirit Lake at all, EV charger installations are administered statewide by the Idaho Division of Occupational and Professional Licenses (DOPL), which maintains a dedicated rotating inspector roster for the Spirit Lake zip code (83869). DOPL's own electrical permit worksheet has no dedicated EV-charging-station fee line; EV charger installations fall under its general 'Other Installations' fee formula, which by its own terms applies to 'any and all electrical installations not specifically mentioned elsewhere' on the fee worksheet.
Verified 2026-07-20 · Source
When you need this permit
- State of Idaho DOPL Electrical Permit required for the EV charging station's electrical installation — purchased online at dbs.idaho.gov (redirects to dopl.idaho.gov); the City of Spirit Lake does not issue electrical permits of any kind
- If adding a dedicated branch circuit to an existing residence, this may instead be billed as an additional branch circuit under DOPL's Existing Residence fee line ($65 base + $10 per additional branch circuit) rather than the 'Other Installations' formula — the worksheet does not disambiguate which line applies to EV charging equipment specifically
- New construction: EV charger circuits included with a new single-family dwelling's electrical rough-in are covered under the New Single Family Dwelling fee (based on square footage), with no separate EV line item
- No City of Spirit Lake building permit is required for a standalone EV charger installation (no structural component); a City Building Permit would only apply if the charger installation is bundled into broader construction work
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
DOPL Electrical Permit Worksheet (Fee Schedule), 'Other Installations including Solar/Renewable Energy' section, which applies to 'any and all electrical installations not specifically mentioned… Show full citationHide
DOPL Electrical Permit Worksheet (Fee Schedule), 'Other Installations including Solar/Renewable Energy' section, which applies to 'any and all electrical installations not specifically mentioned elsewhere' on the worksheet — no dedicated EV-charging line exists, so this general formula is the applicable mechanism when DOPL (not the local jurisdiction) issues the electrical permit, as is the case for all electrical work in Spirit Lake. The worksheet was revised 8/17/2022 and remains the current published version.DOPL Electrical Permit Worksheet, 'Existing Residence' line — may apply instead of the Other Installations formula if the EV charger is treated as a single added branch circuit rather than a full 'installation'; Show full citationHide
DOPL Electrical Permit Worksheet, 'Existing Residence' line — may apply instead of the Other Installations formula if the EV charger is treated as a single added branch circuit rather than a full 'installation'; DOPL does not publish guidance distinguishing which line applies to EV charging equipment.Review timeline
Inspection process
- 1
DOPL Electrical Rough-In/Final
State-inspected via DOPL's dedicated rotating inspector roster for the Spirit Lake zip code
See the full Spirit Lake inspection guide — scheduling & re-inspection fees →
Tips
- Spirit Lake does not issue any electrical permits itself, including for EV chargers — every electrical permit is a State of Idaho DOPL permit from end to end, the same structure documented for solar PV in this jurisdiction.
- DOPL's fee worksheet has no dedicated EV-charging-station line item; it is billed under the general 'Other Installations' formula (2% of system cost + $60, up to $10,000) unless treated as a simple added branch circuit on an existing residence ($10 flat).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Spirit Lake building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Spirit Lake's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Spirit Lake yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Spirit Lake lands. Privacy.
Other permits in Spirit Lake
Electric Vehicle (EV) Charging Station Permit in other cities
Compare electric vehicle (ev) charging station permit fees across Idaho →
Look up this fee in a different city →
Related guides
Now live
Build your Spirit Lake project checklist
Describe your project once and get every permit, document, and fee it triggers in Spirit Lake — in one checklist. Free, for any city and any number of projects.
Get started →