When you need this permit

  • Building permit required for new single-family homes, duplexes, and townhouses
  • Plans must comply with the City's adopted 2018 IBC and 2018 IRC (City Code § 8-1-1)
  • Submit online through the City's iworq Citizen Portal (linked from spiritlakeid.gov/buildingandpermits): fill out all required fields and upload plans/documents
  • Properties within the Historic District require Historic District Commission approval before work begins or a permit is issued
  • Plan Check Deposit due at plan submittal: $150.00 (single-family residential) or $300.00 (duplex), paid before plan review begins
  • Electrical and plumbing work require SEPARATE permits from the State of Idaho Division of Occupational and Professional Licenses (DOPL) — the City does not issue these; DOPL maintains a dedicated rotating inspector roster for Spirit Lake (zip 83869)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Check Deposit — Residential (single-family)Paid at plan submittal. City of Spirit Lake Fee Schedule, Resolution No. 2024-06-11, Attachment 5
$150.00
Plan Check Deposit — DuplexResolution No. 2024-06-11, Attachment 5
$300.00
Plan Check Deposit — TownhouseResolution No. 2024-06-11, Attachment 5
$150.00 per unit
General Building Permit FeeResolution No. 2024-06-11, Attachment 5 — no flat valuation table was published in the fee resolution itself; the Building Department applies a separate valuation chart
Based on project valuation, determined via the City's building valuation chart (per Building Safety Journal, July 2008 edition)
Residential Plan ReviewResolution No. 2024-06-11, Attachment 5
65% of the building permit fee
Foundation Only PermitResolution No. 2024-06-11, Attachment 5
10% of the building permit fee, IN ADDITION TO the full building permit fee
Provisional Certificate of OccupancyResolution No. 2024-06-11, Attachment 5
$250.00 flat fee
Board of Appeals Application FeeResolution No. 2024-06-11, Attachment 5
$150.00 flat fee
Work Performed without a valid permitResolution No. 2024-06-11, Attachment 5
Regular building/mechanical permit fee x 2
Additions to Residential HomesResolution No. 2024-06-11, Attachment 5
$72.62 per sq ft (use building valuation chart to calculate)
Special Inspection / Re-inspectionResolution No. 2024-06-11, Attachment 5
$100.00 per hour, one-half-hour minimum

Review timeline

Plan reviewSpirit Lake’s published plan-review target
10–14 business days

How long did your Residential Building Permit (New Construction) permit actually take in Spirit Lake?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footings

    Before concrete pour — forms, rebar, and anchor bolts verified

  2. 2

    Framing

    After framing and rough-in trades, before insulation or wall cover

  3. 3

    Final

    All work complete, ready for certificate of occupancy

See the full Spirit Lake inspection guide — scheduling & re-inspection fees →

Tips

  • Apply online through the iworq Citizen Portal linked from spiritlakeid.gov/buildingandpermits — a contractor access code is needed for contractor-submitted applications.
  • The City states building permit approval takes approximately 2 weeks; the Mechanical Permit Application (a separate, faster-reviewed permit type) is reviewed within 2-3 business days.
  • Electrical and plumbing work are NOT permitted by the City of Spirit Lake — apply separately through the Idaho Division of Occupational and Professional Licenses (DOPL) at (208) 334-3233 or https://dopl.idaho.gov/.
  • Properties within the Historic District require Historic District Commission approval before any work begins or a demolition permit is issued.
  • The Plan Check Deposit ($150 residential / $300 duplex) is due at plan submittal, before review begins.

Frequently asked questions

Yes. New single-family homes, duplexes, and townhouses require a Building Permit reviewed against the City's adopted 2018 IBC and 2018 IRC. Apply online through the City's iworq Citizen Portal at spiritlakeid.gov/buildingandpermits.

In Spirit Lake, the published Plan Check Deposit — Residential (single-family) is: $150.00. Additional published fees: Plan Check Deposit — Duplex — $300.00; Plan Check Deposit — Townhouse — $150.00 per unit; General Building Permit Fee — Based on project valuation, determined via the City's building valuation chart (per Building Safety Journal, July 2008 edition); Residential Plan Review — 65% of the building permit fee; Foundation Only Permit — 10% of the building permit fee, IN ADDITION TO the full building permit fee; Provisional Certificate of Occupancy — $250.00 flat fee; Board of Appeals Application Fee — $150.00 flat fee; Work Performed without a valid permit — Regular building/mechanical permit fee x 2; Additions to Residential Homes — $72.62 per sq ft (use building valuation chart to calculate); Special Inspection / Re-inspection — $100.00 per hour, one-half-hour minimum. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The City's own permit portal states to allow approximately 2 weeks for permit approval.

You'll need: Building Permit Application (iworq Citizen Portal); Construction Drawings / Plans. See the required-documents checklist on this page for details on each.

Spirit Lake requires 3 inspection(s) for a residential building permit (new construction), in order: Foundation / Footings, Framing, Final. Schedule each through City of Spirit Lake — Building & Permits ((208) 623-2131).

Apply through City of Spirit Lake — Building & Permits at 6042 W. Maine St. (PO Box 309), Spirit Lake, ID 83869. Phone: (208) 623-2131. Office hours: Monday–Thursday 8:00 AM – 5:00 PM; Friday 8:00 AM – 2:00 PM (no lunch hour). Official information: https://www.spiritlakeid.gov/buildingandpermits.

Spirit Lake, Idaho has adopted: Idaho has a mandatory statewide baseline building code under the Idaho Building Code Act (Idaho Code Title 39, Chapter 41). Spirit Lake is an INCORPORATED CITY within Kootenai County and administers its own building program, entirely distinct from Kootenai County Community Development's Building Division (which administers only the unincorporated area of the county). Kootenai County's own adopted-codes documentation explicitly lists Spirit Lake among the incorporated cities in the county with their own building departments and codes. Source: Kootenai County Code Title 7, Chapter 1, Section 7.1.103 (Applicability), https://codelibrary.amlegal.com/codes/kootenaicountyid/latest/kootenaicounty_id/0-0-0-2406; City of Spirit Lake City Code, Title 8 (Building Regulations), Chapter 1 (Building Codes), Section 8-1-1 'Building Codes Adopted': the City Council has adopted the 2018 International Building Code (IBC) and the 2018 International Residential Code (IRC), each as prepared by the International Code Council and as adopted by the State of Idaho through the Idaho Building Code Board. Source: Spirit Lake City Code § 8-1-1, https://codelibrary.amlegal.com/codes/spiritlakeid/latest/spiritlake_id/0-0-0-1349 (section text confirmed via indexed search excerpt of the amlegal-hosted code; the amlegal viewer itself is a JavaScript single-page app that does not expose section body text to non-browser fetches — this is a known access limitation of the amlegal platform, not a Spirit Lake-specific gap); Spirit Lake issues its own Building Permits and Mechanical Permits directly (confirmed via the City's own Building & Permits page and its iworq citizen permit portal, which lists 'Building Permit Application,' 'Mechanical Permit Application,' 'Community Development, Planning and Zoning, or Land Use' permit, and 'Right of Way/Encroachment Application' as the four permit types the City itself processes). Source: City of Spirit Lake Building & Permits page, https://www.spiritlakeid.gov/buildingandpermits; City of Spirit Lake iworq Citizen Portal, https://spiritlake_permit.portal.iworq.net/portalhome/spiritlake_permit; Electrical and plumbing permitting and inspection within Spirit Lake city limits are administered by the STATE of Idaho, not the City: the City's own Building & Permits page and citizen portal list only Building, Mechanical, Land Use/Planning & Zoning, and Right-of-Way/Encroachment permits — no electrical or plumbing permit option is offered by the City. This is confirmed independently by the Idaho Division of Occupational and Professional Licenses (DOPL) Building Codes, Rules & Enforcement Inspector List, which lists a dedicated rotating inspector roster for 'SPIRIT LAKE, 83869, KOOTENAI' across Electrical, HVAC, and Plumbing categories — the same statewide DOPL structure documented for unincorporated Kootenai County and for neighboring Hayden and Rathdrum. Electrical work is governed statewide by the Idaho Electrical Contractors Act / Idaho Electrical Board rules (Idaho Code Title 54, Chapter 10; IDAPA 24.39) and plumbing by the Idaho Plumbing Contractors Act / Idaho State Plumbing Code (Idaho Code Title 54, Chapter 26), both administered by DOPL, Boise, (208) 334-3233. NOTE: HVAC/mechanical also appears on the DOPL statewide inspector roster, but Spirit Lake is confirmed to issue its own Mechanical Permits directly (own portal application type, own fee schedule) rather than deferring to DOPL for that trade — mirroring the pattern documented for Kootenai County's unincorporated area and for Hayden, where mechanical is city/county-issued even though electrical and plumbing are not. Sources: City of Spirit Lake Building & Permits page and iworq portal (above); DOPL Building Codes, Rules & Enforcement Inspector List with Schedule, https://dopl.idaho.gov/wp-content/uploads/2025/08/BCRE-Inspector-list-with-schedule080725.pdf; All Spirit Lake fees (Building Permit Fees, Attachment 5; Mechanical Permit Fees, Attachment 6) were adopted and consolidated by Resolution No. 2024-06-11 (City of Spirit Lake Fee Schedule), effective June 11, 2024, amending prior Resolution No. 2023-02-14. Source: Resolution No. 2024-06-11, https://spiritlakeid.gov/api/blob/viewBlob?rf=t&i=kEmYQZlyIUVgVIzNaUloELheLumtqCFBZPObn5tbvAF1/LqmSoNPWgcyS6pAVdXo. Local amendments apply — see the Spirit Lake overview page for the full list.

No. Electrical and plumbing permits and inspections within Spirit Lake are handled by the State of Idaho Division of Occupational and Professional Licenses (DOPL), not the City. DOPL maintains a dedicated rotating inspector roster for Spirit Lake (zip 83869). Contact DOPL at (208) 334-3233 or https://dopl.idaho.gov/.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Spirit Lake building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.