Solar Permit in Unincorporated Madison County, Idaho
Madison County issues its own dedicated 'Solar Permit' for both roof-mounted and ground-mounted PV installations in unincorporated Madison County, via a distinct Solar Permit Application form separate from the general Building Permit application. Roof-mounted systems do not require Planning and Zoning review (and so cost less); ground-mounted systems do require P&Z review of setbacks and cost more. Directly confirmed by the county's own published 4-page Solar Permit Application and Submittal Checklist. Electrical inspection is performed under the county's contract with the City of Rexburg (per Idaho Code 54-1001), not by the county Building Department directly and not by DOPL.
Verified 2026-07-20 · Source
When you need this permit
- Solar Permit Application required for both roof-mounted and ground-mounted PV systems; select 'Roof Mount' or 'Ground Mount' on the application
- Recorded Warranty Deed (from the Clerk's Office); a notarized 'Affidavit of Legal Interest' is required if the applicant is not the legal property owner
- Site Plan showing setbacks for ground-mounted systems (front/back/side, from structure to property line, easements, right-of-way lines, and open surface water) or the panel location on the roof
- Copy of the Building Contractor's State Registration (Idaho contractor registration) Contractor
- Full plan set (electronic PDF, drawn to scale no smaller than 1/8" = 1'), covering PV array configuration, grounding, wire management, conductors, rapid shutdown of PV systems on buildings, charge controllers, disconnects, inverters, batteries, and anchoring type — ALL plans must bear a current Engineer's stamp
- Preliminary Elevation Certificate required before building permit issuance if the parcel is in a mapped floodplain; Final Elevation Certificate required before a Certificate of Occupancy is issued
- Copy of subdivision covenants if the property is located in a subdivision with covenants
- Fire Plan Review by the Madison County Fire District if determined necessary by the Building Department
- Ground-mount setback requirements per the county's published Site Plan Requirements: Agricultural (AG) zone — Front 30/60 ft, Side 10 ft, Back 25 ft; Trans-Agricultural (TRANS) zone — same; a 200 ft setback from 5 ft above the high-water mark of any waterway applies per Sec. 117-63(t)
- Review process requires a minimum of 10 working days (not counting the submittal day) after all required documents are submitted — an incomplete application is not accepted into the review queue at all
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Building Department Inspection(s)
Verifies mounting/anchoring, array configuration, and structural work per the engineer-stamped plans; permit number and address must be posted and visible from the road or inspection will not be performed
- 2
Electrical Inspection (City of Rexburg contract)
Performed under Madison County's contract with the City of Rexburg per Idaho Code 54-1001 — not by the county Building Department directly and not by DOPL, since Madison County (unlike most other Idaho counties in this corpus) has a county-city inspection arrangement instead
See the full Unincorporated Madison County inspection guide — scheduling & re-inspection fees →
Tips
- Roof-mounted solar is meaningfully cheaper to permit than ground-mounted ($170 vs $195 total) specifically because roof-mount does not trigger Planning and Zoning setback review — confirm which category your installation falls under before budgeting.
- Every plan sheet (array configuration, grounding, wire management, conductors, rapid shutdown, charge controllers, disconnects, inverters, batteries, anchoring) must carry a current Engineer's stamp — this is a more demanding plan-review bar than some neighboring counties that only require a stamp for larger/complex structures.
- An incomplete Solar Permit application is not accepted into the 10-working-day review queue at all — gather every checklist item (recorded deed, site plan, contractor registration, full engineer-stamped plan set, flood/covenant documentation) before submitting. Contractor
- Madison County's electrical inspection is handled by the City of Rexburg under an intergovernmental contract (Idaho Code 54-1001) — a different arrangement than the direct-to-DOPL model used in most other Idaho counties in this corpus. Apply/schedule via https://apply.rexburg.org/publicapp/.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Madison County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Madison County
Solar Permit in other cities
Compare solar permit fees across Idaho →
Look up this fee in a different city →
Now live
Build your Unincorporated Madison County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Madison County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →