Required for manufactured/mobile home, modular, and double-wide placement within the City of Rupert. Only Class A manufactured homes are permitted within city limits where single-family residences are allowed; Class B and C homes are restricted to unincorporated county areas and mobile home parks. Issued and reviewed by the Minidoka County Building Department.

Verified 2026-07-19 · Source

When you need this permit

  • Manufactured, modular, double-wide, or other factory-built home placement within Rupert city limits
  • Must qualify as a Class A manufactured home under the county's zoning-use table if placed on an individual residential lot within city limits (multisectional, minimum 20' wide, minimum 1,000 total sq ft, permanent foundation, constructed after June 15, 1976)
  • Homes manufactured before June 15, 1976 that are being relocated must have a Mobile Home Compliance Rehabilitation Certificate from the Idaho Division of Building Safety before a permit application, per Idaho Code 44-2503
  • Proof of ownership and proof that property taxes are current, per the Manufactured Home Permit Guide
  • Separate electrical, plumbing, and HVAC permits required — excluded from the placement fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Single-wide section placementPer Minidoka County's Manufactured Homes page (minidoka.id.us/183/Manufactured-Homes).
$150
Multiple-section placementPer Minidoka County's Manufactured Homes page (minidoka.id.us/183/Manufactured-Homes).
$200
Concrete foundationMinidoka County's Manufactured Homes page states a concrete foundation carries an additional cost that varies by home size, without publishing a specific dollar figure as of 2026-07-19.
Additional cost, varies by home size — specific dollar figure not published

Review timeline

Plan reviewRupert’s published plan-review target
5–10 business days

How long did your Manufactured Home Permit permit actually take in Rupert?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Blocking and Anchoring

    Verifies the foundation or blocking-and-anchoring design (spacing, sizing, locations) matches the submitted Foundation Plan.

  2. 2

    Final

    Final inspection prior to occupancy, including verification of landings/egress and skirting details.

See the full Rupert inspection guide — scheduling & re-inspection fees →

Tips

  • Only Class A manufactured homes are permitted within Rupert city limits in zoning districts where single-family residences are allowed — confirm classification (Class A vs. B vs. C, per the detailed definitions in the Manufactured Home Permit Guide) with the Building Department before purchasing a used unit for placement inside city limits.
  • The $150/$200 placement fees exclude electrical and plumbing work, which require separate permits from the Idaho Division of Building Safety/DOPL, per the Manufactured Home Permit Guide.

Frequently asked questions

Rupert requires a manufactured home permit for: Manufactured, modular, double-wide, or other factory-built home placement within Rupert city limits; Must qualify as a Class A manufactured home under the county's zoning-use table if placed on an individual residential lot within city limits (multisectional, minimum 20' wide, minimum 1,000 total sq ft, permanent foundation, constructed after June 15, 1976); Homes manufactured before June 15, 1976 that are being relocated must have a Mobile Home Compliance Rehabilitation Certificate from the Idaho Division of Building Safety before a permit application, per Idaho Code 44-2503; Proof of ownership and proof that property taxes are current, per the Manufactured Home Permit Guide; Separate electrical, plumbing, and HVAC permits required — excluded from the placement fee. If your project isn't listed, confirm with Minidoka County Building Department (serves as the building/permitting authority for the City of Rupert) at (208) 436-7183 (Building Department); (208) 436-7180 (Building & Zoning general line) before starting work.

In Rupert, the published Single-wide section placement is: $150. Additional published fees: Multiple-section placement — $200; Concrete foundation — Additional cost, varies by home size — specific dollar figure not published. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Rupert's published plan-review target for a manufactured home permit is 5–10 business days.

You'll need: Manufactured Home Application Packet; Two (2) sets of plans, minimum 11"x17", to scale; Legal documents showing ownership, make, model, and year. Depending on your project, Rupert may also ask for: Exterior photos of all sides. See the required-documents checklist on this page for details on each.

Rupert requires 2 inspection(s) for a manufactured home permit, in order: Foundation/Blocking and Anchoring, Final. Schedule each through Minidoka County Building Department (serves as the building/permitting authority for the City of Rupert) ((208) 436-7183 (Building Department); (208) 436-7180 (Building & Zoning general line)).

Apply through Minidoka County Building Department (serves as the building/permitting authority for the City of Rupert) at 715 G Street, Rupert, ID 83350 (P.O. Box 368, Rupert, ID 83350). Phone: (208) 436-7183 (Building Department); (208) 436-7180 (Building & Zoning general line), email: Building@minidokacounty.id.gov. Office hours: Monday-Friday, 8:30 a.m. to 5:00 p.m., per the Minidoka County Building and Zoning page. Building Official: Rick Nay (also the City of Rupert's Zoning Administrator, per the Residential and Manufactured Home Building Permit Guides). Building Inspectors: Taylor Podunovich, Kortnie Kent.. Official information: https://www.minidoka.id.us/179/Building-and-Zoning.

Rupert, Idaho has adopted: 2018 International Building Code (IBC), 2018 International Residential Code (IRC), 2018 International Energy Conservation Code (IECC), 2018 International Existing Building Code (IEBC), and 2018 International Mechanical Code (IMC), effective January 1, 2021, per Minidoka County's Adopted Building Codes page (minidoka.id.us/371/Building-Codes).; 2018 International Fire Code (IFC) and 2018 International Fuel Gas Code (IFGC) are also currently enforced per the Minidoka County Building Department's Commercial Building Permit Guide (Commercial Application Packet), which lists the full current-codes set for commercial/multi-family projects.; Effective February 1, 2021, all new residential construction Mechanical permit applications require Manual J design documents, per the county's Adopted Building Codes page.; The Residential Building Permit Guide (within the Residential Application Packet) separately publishes county-specific climate/geographic design criteria under the 2018 IRC: 20 lb (4800) ground snow load, 90 mph wind speed, Seismic Design Category B, 24-inch frost line depth, and a 5°F winter design temperature.. Local amendments apply — see the Rupert overview page for the full list.

Only if it qualifies as a Class A manufactured home under Minidoka County's zoning-use table — Class A homes must be multisectional (at least 20' wide at the narrowest point, minimum 1,000 total sq ft across sections). A true single-wide typically will not meet the Class A width/square-footage thresholds required inside city limits, though the county does charge a distinct 'single-wide placement' fee ($150) that applies more broadly to unincorporated areas and mobile home parks. Confirm with the Building Department at (208) 436-7183 before purchasing a unit for placement in Rupert.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rupert building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.