Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) — Donnelly, Idaho · Requirements sheet
Verified 2026-08-25 · Source: https://cityofdonnelly.org/wp-content/uploads/2021/06/Building-Permit-Application-Information-and-Instructions-2021.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) in Donnelly, Idaho
Covers new commercial construction, additions, and remodel or tenant-improvement work on commercial and community-type structures within Donnelly city limits. The City of Donnelly does not maintain a separate commercial application or fee schedule: the same Building Permit Application and the same valuation-based fee table used for the City's residential building permit apply to commercial work, per the City's own Building Permit Application Information and Instructions (2021). Commercial work is reviewed against the International Building Code rather than the International Residential Code that governs single-family homes on that same fee table; Donnelly City Code Section 15.05.050(A) adopts the International Building Code, current edition, and the City's Building Department currently identifies that edition as the 2018 IBC. Applications are submitted to Donnelly City Hall; Valley County Building Department provides plan review support and performs inspections under an interlocal service arrangement, but Valley County's own Building Department page states its office does not cover the City of Donnelly, and the County publishes its own separate building-fee structure for the area it does administer directly. The fees below are Donnelly's own.
Verified 2026-08-25 · Source
When you need this permit
- Building permit required for construction, alteration, addition, or demolition of any commercial or other structure within Donnelly city limits, per Donnelly City Code Section 15.05.120 (Permits Required)
- Commercial and community-type structures are reviewed against the International Building Code, current edition, adopted by Donnelly City Code Section 15.05.050(A); the City's Building Permit Application Information and Instructions (2021) and current Forms & Permits page identify the 2018 International Building Code, alongside the 2018 International Residential Code used for single-family residential work, as the edition currently in effect
- Plans must be stamped by a licensed architect or engineer certifying compliance with the 2018 International Codes and City of Donnelly Ordinances, per the City's Building Permit Application Information and Instructions (2021)
- An approved Conditional Use Permit from Donnelly Planning and Zoning may be required for a commercial or community-type structure, per the same Instructions document
- Donnelly City Code Section 15.05.090 designates property zoned Commercial ('C') or Industrial ('D') as Fire Zone 2, and all other areas of the city as Fire Zone 3, under the fire-zone provisions of the Uniform Building Code -- a reference standard that predates the City's currently-adopted International Building Code; no more recent fire-zone amendment to this section was found
- A Donnelly Rural Fire Protection District (DRFPD) impact fee is collected by the City at building permit application for new construction, calculated at $0.52 per square foot for commercial buildings rather than the flat $1,290.00 single-family-residence rate, effective October 2, 2023 under an Intergovernmental Agreement between the City and DRFPD
- A separate Change of Use Permit, filed through Planning and Zoning rather than the Building Department, is required when a project converts occupancy -- for example, a tenant-improvement project that converts residential space to commercial use
- Electrical, plumbing, and HVAC work require separate permits from the Idaho Division of Building Safety (dbs.idaho.gov); the City's Instructions state that all commercial installations of this kind must be performed by a licensed contractor Contractor
- Valley County Building Department provides plan review support and performs inspections for Donnelly commercial permits under the same interlocal service arrangement used for residential work; Valley County's own website states that its Building Department 'does not cover the City of McCall, the City of Cascade, or the City of Donnelly,' meaning the County does not independently administer or set fees for building permits inside Donnelly city limits
- No published fee for a Donnelly Rural Fire Protection District plan review of commercial construction was found beyond the per-square-foot impact fee above; the City's Instructions describe only a Donnelly Fire sign-off on propane tank installations prior to final inspection or certificate of occupancy
- No evidence was found that the Idaho State Fire Marshal reviews privately owned commercial construction in Donnelly -- the State Fire Marshal's own Plan Reviews page describes its scope as new construction, alterations, and renovations on state-owned and state-leased buildings
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Effective October 2, 2023, per the Intergovernmental Agreement between the City of Donnelly and DRFPD; Show full citationHide
Effective October 2, 2023, per the Intergovernmental Agreement between the City of Donnelly and DRFPD; collected by the City during the building permit application process for new commercial construction, per the City's Forms & Permits page (cityofdonnelly.org/government/permits/).City of Donnelly Fee Schedule, adopted August 18, 2025, Development fee table, listed alongside the Conditional Use Permit and Change of Use Permit fees. Show full citationHide
City of Donnelly Fee Schedule, adopted August 18, 2025, Development fee table, listed alongside the Conditional Use Permit and Change of Use Permit fees. The schedule does not state which permit applications trigger this fee, so confirm with City Hall before assuming it applies to a specific project.Review timeline
Inspection process
- 1
Soils / Excavation
Initial site/soils inspection prior to foundation work
- 2
Footing / Hole
Before concrete pour -- footing excavation and forms
- 3
Foundation
Foundation walls, rebar, anchor bolts
- 4
Slab
Slab-on-grade prior to concrete pour, where applicable
- 5
Frame
Structural framing complete before insulation or wall cover
- 6
Roof and Wall Sheathing
Sheathing verified before house wrap and roofing materials applied
- 7
Insulation
Insulation installer certification of type, manufacturer, and R-value required per 2018 IRC Sec. N1101.16 (or the corresponding IBC/IECC commercial provision)
- 8
Siding / Exterior Wall Covering
Exterior wall covering installation
- 9
Final
All work complete; Donnelly Fire must sign off on any propane tanks before final/certificate of occupancy
See the full Donnelly inspection guide — scheduling & re-inspection fees →
Tips
- Donnelly does not have a distinct commercial-building-permit application; commercial and community-type construction uses the same Building Permit Application and the same valuation-based fee table as the City's residential building permit.
- A commercial project is reviewed against the City's adopted International Building Code, not the International Residential Code used for single-family homes on that same fee table -- confirm which code sections apply for occupancy classification and construction type with the Building Official before submitting plans.
- Valley County Building Department performs plan review support and inspections for Donnelly on a service basis, but its own website states it does not cover the City of Donnelly -- Donnelly's own fee schedule, not the County's separate building-fee structure, sets what a commercial applicant pays.
- The Donnelly Rural Fire Protection District impact fee for commercial buildings is calculated per square foot ($0.52/sq ft), not the flat $1,290.00 rate charged for a single-family residence -- budget this based on total commercial square footage.
- The City's Fee Schedule (adopted August 18, 2025) lists a $500.00 'Engineering Plan Review for Building Permit' fee in its Development fee table alongside the Conditional Use Permit and Change of Use Permit fees; the schedule does not specify which projects it applies to, so confirm with City Hall before budgeting it into a specific commercial project.
- Donnelly City Code Section 15.05.090 still designates property zoned Commercial or Industrial as Fire Zone 2 under the Uniform Building Code's fire-zone system, a reference standard that predates the currently-adopted International Building Code -- ask the Building Official how this provision is applied today.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-25.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Donnelly building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Donnelly.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Donnelly
Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) in other cities
Look up this fee in a different city →
Now live
Build your Donnelly project checklist
Describe your project once and get every permit, document, and fee it triggers in Donnelly — in one checklist. Free, for any city and any number of projects.
Get started →