EV Charger / EVSE Permit (State of Idaho Electrical Permit) — Donnelly, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://dopl.idaho.gov/wp-content/uploads/2023/11/ELE-Contractor-Electrical-Permit-Application.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (State of Idaho Electrical Permit) in Donnelly, Idaho
Installation of an electric vehicle charging station in Donnelly is electrical work and is NOT permitted by the City of Donnelly or Valley County at all — like all electrical work in Donnelly (per this file's residential-building-permit entry), it requires a separate State of Idaho electrical permit issued by the Division of Occupational and Professional Licenses (DOPL) / Division of Building Safety (dbs.idaho.gov). DOPL's own Contractor Electrical Permit Worksheet (Fee Schedule), directly fetched and reviewed this session, has NO distinct 'EV charger,' 'electric vehicle,' or 'EVSE' line item — a dedicated Level 2 charger circuit added to an existing residence is billed under the worksheet's 'Existing Residence / Modular, Manufactured or Mobile Homes / Detached Shop' bucket: $65 base fee plus $10 per additional branch circuit beyond the one circuit included in the base fee.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit issued by the State of Idaho DOPL/Division of Building Safety, not the City of Donnelly or Valley County Building Department — purchased online at dbs.idaho.gov (required for all permits as of January 1, 2023)
- Confirmed directly against DOPL's own Contractor Electrical Permit Worksheet (Fee Schedule, Rev. 8/17/2022): no distinct EV-charger/EVSE fee line exists; a new circuit added at an existing residence for a charger falls under the 'Existing Residence... Detached Shop' bucket ($65 + $10 per additional branch circuit)
- Work must be performed by, or under, an electrical contractor holding a current Idaho DOPL electrical license, or by the homeowner personally under Idaho's homeowner electrical permit provision for their own primary/secondary residence
- If the charger circuit is bundled into a solar/renewable-energy or larger commercial/industrial electrical scope, it may instead fall under the worksheet's 'Other Installations including Commercial/Industrial/Solar/Renewable Energy' valuation-based tier rather than the flat existing-residence fee
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring and conduit installed before walls closed (if applicable)
- 2
Final
Charger circuit/unit installed, breaker sized correctly, energized
See the full Donnelly inspection guide — scheduling & re-inspection fees →
Tips
- Do not apply for an EV charger permit through the City of Donnelly or Valley County — like all electrical work in Donnelly, it is a State of Idaho DOPL permit purchased online at dbs.idaho.gov.
- There is no distinct 'EV charger permit' anywhere in Idaho's statewide electrical fee worksheet — a dedicated charger circuit at an existing home is billed at the flat $65 existing-residence fee plus $10 for each additional branch circuit beyond the first.
- A homeowner may self-permit an EV charger circuit at their own primary/secondary residence under Idaho's homeowner electrical permit provision rather than hiring a licensed contractor. Contractor
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Donnelly building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Donnelly
EV Charger / EVSE Permit (State of Idaho Electrical Permit) in other cities
Compare ev charger / evse permit (state of idaho electrical permit) fees across Idaho →
Look up this fee in a different city →