Building Permit (New Construction / Addition / Remodel) — Stevensville, Montana · Requirements sheet
Verified 2026-07-04 · Source: https://www.townofstevensville.com/sites/default/files/fileattachments/building/page/86/789bc2c058d1d47fe71e192015a7f1ba.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Building Permit (New Construction / Addition / Remodel) in Stevensville, Montana
Required for new construction, additions, remodels, expanded footprint, garages/sheds, decks/porches, re-roofing, fences, and other structural work in Stevensville. Reviewed against the Town's adopted 2018-cycle IBC/IRC/IEBC and related codes (see codesAdopted) by the Building Official, Public Works, and Zoning divisions. Applications are submitted to Town Hall, 206 Buck Street / PO Box 30.
Verified 2026-07-04 · Source
When you need this permit
- Complete, signed Building Permit application including project address, project type, scope of work, square footage, and property owner/contractor/architect information
- Site plan required for new construction, remodels, and expanded-footprint projects, per the Residential Site Plan Check List
- Two (2) copies of complete project plans (one may be digital)
- Two (2) copies of a signed ResCheck energy-compliance certification (energycodes.gov)
- Two (2) copies of a signed affirmation of knowledge of the Stevensville Lighting District Resolution
- Total project valuation (materials + labor) declared on the application; Building Official may require proof of valuation or will set the value using ICC tables if unverifiable
- Reviewed by the Building Official, Public Works, and Zoning divisions
- Permit becomes null and void if work is not commenced within 180 days of issuance or is suspended/abandoned for 180 days
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation
Before concrete pour, per the Town's required-inspections list (Building FAQs page)
- 2
Framing
Structural framing per approved plans before walls are closed
- 3
Insulation
Insulation inspection prior to enclosing walls, per the Town's required-inspections list
- 4
Final
Completed work verified against approved plans; Building Official sign-off required before occupancy
See the full Stevensville inspection guide — scheduling & re-inspection fees →
Tips
- The Building FAQs page explicitly states the Town's published materials 'don't specify exact review timeframes' — after plan approval, 'the building official will calculate the permit fees and notify the applicant that the permit is ready for issuance.' No numeric review-timeline figure (days or weeks) was found published anywhere on the Town's site, its permit application PDFs, or the Building Permit Fees schedule. Chase trail: checked the Building department page, Forms page, Building FAQs page, Do-I-need-a-permit FAQ, and all four permit application PDFs plus the fee schedule (rendered visually from its scanned-image PDF) — none state a turnaround figure. Left null with reviewTimelineVerified:false rather than inventing or borrowing a neighboring jurisdiction's figure. Note: some third-party permit-aggregator sites (not the Town's own domain) publish an unsourced '1-2 weeks' estimate — this was NOT used here since it does not trace to an official Town or DLI source.
- Regular inspection hours are Monday, Wednesday, and Friday, 10:00 am - 12:30 pm; inspections are by appointment only with 24 hours' notice required. Call (406) 552-3238 or Tim Netzley directly at (406) 880-5832.
- Site plans and two full sets of plans (one may be digital) are required for new construction, remodels, and expanded-footprint projects — incomplete submittals are returned un-reviewed per the Residential Site Plan Check List.
- Decks are only permit-exempt if both under 30 inches high AND under 120 sq ft; attached or detached decks exceeding either threshold require a Building Permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Stevensville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Stevensville
Building Permit (New Construction / Addition / Remodel) in other cities
Compare building permit (new construction / addition / remodel) fees across Montana →
Look up this fee in a different city →
Now live
Build your Stevensville project checklist
Describe your project once and get every permit, document, and fee it triggers in Stevensville — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →