EV Charger / EVSE Permit in Stevensville, Montana

The Town of Stevensville has no dedicated electric-vehicle-charging-station permit or fee line. As a Montana DLI-certified jurisdiction for electrical (E) permitting, the Town issues and inspects an EV charger circuit through its standard Electrical Permit (2017 NEC as adopted), with the fee computed from the same itemized Electrical Permit Application fee table used for any other residential electrical work — most closely the 'New addition, remodel, interior rewire' line ($100.00) for a new dedicated circuit, or 'Misc. work not considered interior remodel/rewire' ($30.00) for simpler scope. No EV/EVSE-specific dollar figure was found published.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for the EV charger circuit, governed by the 2017 NEC as adopted by the Town — same requirement and application track as this file's Electrical Permit entry
  • Montana state license number required for licensed electrical contractors; a homeowner may secure the permit and perform the work only in a private structure occupied for their own personal use
  • Work must commence within 180 days of permit issuance
  • Installer must call for inspection prior to covering the electrical work
  • No dedicated EV/EVSE line-item was found on the Town's Electrical Permit Application fee table

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

New addition, remodel, interior rewire (closest applicable line for a new EV charger circuit)Town of Stevensville Electrical Permit Application; no dedicated EV/EVSE fee line exists
$100.00
Misc. work not considered interior remodel/rewire (alternate applicable line for simpler scope)Town of Stevensville Electrical Permit Application
$30.00
Service change-out or upgrade (if a panel upgrade is required to support the charger)Town of Stevensville Electrical Permit Application
$75.00

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Stevensville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In / Prior to Covering

    Installer must call for inspection prior to covering the charger circuit wiring

  2. 2

    Final

    Charging equipment installed and safety verified per 2017 NEC before permit final

See the full Stevensville inspection guide — scheduling & re-inspection fees →

Tips

  • Stevensville has no EV-specific permit category — apply through the standard Electrical Permit application, and expect the fee to land on the 'New addition, remodel, interior rewire' line ($100) for a typical new dedicated circuit, or the flat $30 'Misc. work' line for simpler scope.
  • If your installation requires a service panel upgrade to support the charger's amperage, budget for the separate $75 Service change-out/upgrade fee in addition to the circuit fee.

Frequently asked questions

Stevensville requires an ev charger / evse permit for: Electrical permit required for the EV charger circuit, governed by the 2017 NEC as adopted by the Town — same requirement and application track as this file's Electrical Permit entry; Montana state license number required for licensed electrical contractors; a homeowner may secure the permit and perform the work only in a private structure occupied for their own personal use; Work must commence within 180 days of permit issuance; Installer must call for inspection prior to covering the electrical work; No dedicated EV/EVSE line-item was found on the Town's Electrical Permit Application fee table. If your project isn't listed, confirm with Town of Stevensville Building Department at (406) 777-5271 before starting work.

No. The Town's Electrical Permit Application fee table has no EV/EVSE-specific line-item. An EV charger circuit is billed under the general electrical fee table, most closely the 'New addition, remodel, interior rewire' line ($100.00) or the 'Misc. work' line ($30.00), depending on scope.

Stevensville does not publish a plan-review timeline for this permit. Contact Town of Stevensville Building Department at (406) 777-5271 for current turnaround.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Stevensville requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In / Prior to Covering, Final. Schedule each through Town of Stevensville Building Department ((406) 777-5271).

Apply through Town of Stevensville Building Department at 206 Buck Street, Stevensville, MT 59870 (mailing: PO Box 30, Stevensville, MT 59870). Phone: (406) 777-5271, email: INSPECTOR@constructmt.com. Office hours: Town Hall main line (406) 777-5271, Building Office extension 105. Regular inspection hours: Monday, Wednesday, and Friday, 10:00 am - 12:30 pm (inspections by appointment only, 24 hours' notice required). Building Inspector Tim Netzley: (406) 880-5832. Inspection scheduling / general inspector line: (406) 552-3238, INSPECTOR@constructmt.com. Source: Town of Stevensville Building page (townofstevensville.com/building) and Building FAQs page (townofstevensville.com/building/page/building-faqs).. Official information: https://www.townofstevensville.com/building.

Stevensville, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code; a certified local program's adopted code 'may include only codes adopted by the Building Codes Bureau' (ARM 24.301.202). Non-certified areas fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs (bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf, updated 04/22/2026).; Stevensville is a Montana DLI-certified jurisdiction for Building (B), Plumbing (P), Electrical (E), Mechanical (M), and Swimming Pool (SP) — full-trade certification — within Stevensville city limits. Certified program contact on file with DLI: Tim Netzley, 880-5832. Source: Montana DLI Building Codes Bureau, 'Certified City, County and Town Programs' roster (bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf, updated 04/22/2026), row 'Stevensville — B,P,E,M,SP — Tim Netzley — 880-5832 — City Limits'. Directly verified by fetching and extracting the PDF text during this research pass (2026-07-04).; Per the Town's own 'Adopted Building Codes' notice (currently_adopted_building_codes.docx): Montana adopted several updated building code editions with amendments under ARM 24.301.202(1) on December 7, 2019, giving municipalities 90 days to formally adopt. The Town of Stevensville complied with adoption and enforcement of new projects as of February 17, 2020. Codes in effect per that notice: 2018 Uniform Plumbing Code, 2018 International Mechanical Code, 2018 International Fuel Gas Code, 2018 NFPA 99C (Gas and Vacuum Systems), 2017 National Electrical Code, 2018 International Building Code, 2018 International Residential Code, 2012 International Energy Conservation Code (explicitly stated to remain in effect, not updated to a later edition), 2018 International Existing Building Code, 2018 International Swimming Pool and Spa Code. Signed by Tim Netzley, Building Official, Town of Stevensville. Source: Town of Stevensville, 'Currently Adopted Building Codes' (townofstevensville.com/forms, currently_adopted_building_codes.docx).; This code-edition set (2018-vintage IBC/IRC/UPC/IMC/IFGC/IEBC/ISPSC, 2017 NEC, 2012 IECC) is older than the 2021-cycle codes now in effect statewide per the DLI's Current Codes page and is one edition cycle behind Hamilton's and Darby's currently-adopted 2021 codes; this is Stevensville's own most recently published adoption notice and is reported as-is rather than assumed to have been silently updated to the 2021 cycle without a superseding notice found on the Town's site.; Montana uses the Uniform Plumbing Code (UPC), not the International Plumbing Code.. Local amendments apply — see the Stevensville overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Stevensville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.